Atch(1a)_PWS_Section_C,_SOW_Kitchen_Exhaust_System_Part1.pdf

PDF 480 KB Posted

Attached to
Kitchen Exhaust Systems Cleaning, Inspection and Constituent Parts Replacement Services various location at MCAS Iwakuni Japan
Solicitation number
N4008419B5403
Issued by

About this file

Atch_1a_PWS

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION NO

N40084-19-B-5403

DEPARTMENT OF THE NAVY

FACILITIES ENGINEERING AND ACQUISTION DIVISION (FEAD)

FACILITIES DEPARTMENT

MCAS IWAKUNI, JAPAN

KITCHEN EXHAUST SYSTEM CLEANING, MINOR INSPECTION AND PARTS

REPLACEMENT SERVICES

AT U. S. MARINE CORPS AIR STATION (MCAS) IWAKUNI, JAPAN

PREPARED BY: FACILITIES SUPPORT CONTRACTS

FACILITIES DEPARTMENT

MCAS IWAKUNI, JAPAN

SPECIFICATION PREPARED BY:

MIYAKO HAYASHI DATE

SPECIFICATION WRITER / ENGINEERING TECHNICIAN

FACILITIES SUPPORT CONTRACTS

SPECIFICATION APPROVED BY:

OTIS G. GIDDENS DATE

FACILITIES SUPPORT CONTRACTS MANAGER

SPECIFICATION ACCEPTED BY: NAVFAC FE PW2 FSC PLC

K. L. GRANVILLE DATE

NOTICE: All inquiries concerning any phase this specification, prior to bid opening, shall be made to the office of the Facilities Engineering and Acquisition Division, Facilities Department, MCAS Iwakuni, Japan. The Government specification, forms mentioned, and other information necessary may be obtained or examined and non-Government publication may be examined, on application to the above office.

18 April 2019

0100000 – General Information Spec Item Title 1 General Information

1.1 Outline of Services

1.2 Project Location

1.3 Acquisition of Additional Work

1.4 Background Information

1.5 Verification of Workload and Conditions

1.6 Climate Patterns

1.7 Related Information

1.8 Navy Approach to Service Contracting

1.8.1 Partnering Philosophy

1.8.2 Contractor's Knowledge

1.8.3 Industry Best Practices

1.9 Standard Template

1.10 Navy PBSA Approach

1.11 Technical Proposal Certification

Spec Item Title Description 1 General Information

1.1 Outline of Services Except where otherwise stated, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide the services outlined below and described in this Performance Work Statement (PWS) at U. S. Marine Corps Air Station (MCAS) Iwakuni and outlying areas supported by this installation under a performance-based contract that is comprised of Recurring Work Items.

The PWS is organized into annexes. Annex 1 is "General Information".

Annex 2 contains the on-site project management and administration requirements. Annexes 3 through 18 contain the technical requirements.

The annex numbers are identified as 1 through 18 in the description column, but the full expanded annex numbers include seven digits (e.g., Annex 1 expanded number is 0100000 as shown in the header row at the top of this page).

Annex 1 General Information Annex 2 Management and Administration Annex 3 Command and Staff: Not Applicable (N/A) Annex 4 Public Safety: N/A Annex 5 Air Operations: N/A Annex 6 Port Operations: N/A Annex 7 Ordnance: N/A Annex 8 Range Operations: N/A Annex 9 Health Care Support: N/A Annex 10 Supply: N/A Annex 11 Personnel Support: N/A Annex 12 Morale, Welfare and Recreation Support: N/A Annex 13 Galley: N/A Annex 14 Housing: N/A Annex 15 Facilities Support

• Sub-Annex 1502 Facility Investment

Annex 16 Utilities: N/A Annex 17 Base Support Vehicles and Equipment: N/A Annex 18 Environmental: N/A

1.2 Project Location The work shall be performed at various locations aboard MCAS Iwakuni and could vary from location to location. The following is an example of the dispersion of work at the various locations.

(1) Kitchen Exhaust Systems Cleaning, Inspection and Constituent Parts Replacement Services: various locations

1.3 Acquisition of

Additional Work

The Government reserves the right to acquire additional services at additional locations, within the scope of the annexes and areas included in Spec Item 1.1 Outline of Services, in addition to the services and locations identified in the requirements of this contract. Additional services will be incorporated into the contract in accordance with the CHANGES clause, SECTION I. Items of work not covered by this contract but within the general intent are considered in the scope of this contract.

1.4 Background Information The intent of this solicitation is to obtain Kitchen Exhaust Systems Cleaning, Inspection, and Constituent Parts Replacement Services. The contract is a performance-based specification relying on the Contractor’s experience and expertise determining the best method of providing those services. The Contractor is required to have in place a Quality Management System, providing quality control measure of both the prime and subcontractors requirements.

1.5 Verification of

Workload and Conditions

Throughout the PWS, the workload data is generally referred to as being located in Sections C and J. Section C provides data such as descriptions, specifications, and the statement of work. Section J provides data such as system descriptions, inventories, maps, floor plans, and tables to represent the type, quantity, and location of services to be provided.

As prescribed in FAR 52.237-1, offerors or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

1.6 Climate Patterns Refer to the historical data provided by the Japan Meteorological Agency for climate patterns. Website link:

http://www.data.jma.go.jp/obd/stats/etrn/index.php?prec_no=81&block_n o=0940&year=&month=&day=&view

1.7 Related Information There are four types of Related Information that can be found in the Description and Related Information columns of the specification as follows:

Informational Notes as used throughout this PWS provides additional information to offerors to be used in developing a thorough understanding of the work to be performed in this contract. Any block of text marked “Informational Notes” throughout Annexes 1 through 18 is subject to this disclaimer. Offerors may not rely upon the "Informational Notes" as material representations of the Government. Information provided in "Informational Notes" does not create a contractual requirement on either party to this contract.

Clarifying Information describes client expectations in a more detailed manner than the Performance Objective and Performance standard alone.

Constraining Information describes limitations to the work performed to meet the Performance Objective and Performance Standard.

Requirement Information further describes client requirements associated with each Performance Objective.

1.8 Navy Approach to

Service Contracting

The Department of Navy (DoN) spends over $1 billion in annual obligations to meet global requirements for facility operations and maintenance provided through Facility Support Contracts (FSC) and additional billions to provide other base operations support services (OBOS). The Head of the Contracting Activity (HCA) of the Naval Facilities Engineering Command (NAVFAC) has focused increased attention on re-engineering FSC contracts in response to customer and industry feedback, budget constraints, and the impact of a variety of contracting, program management and financial management regulations.

The Navy also supports the following principles:

http://www.data.jma.go.jp/obd/stats/etrn/index.php?prec_no=81&block_no=0940&year=&month=&day=&view http://www.data.jma.go.jp/obd/stats/etrn/index.php?prec_no=81&block_no=0940&year=&month=&day=&view

1.8.1 Partnering Philosophy The first principle is that the Navy views its contractors as partners and not just abstract service providers. The Navy wants its contractors to succeed because partners' success drives the Navy's successful mission completion.

Within the bounds of acquisition policy the Navy intends to work to find solutions that will be beneficial to both the Government and its partners.

1.8.2 Contractor's Knowledge The second principle is that the Navy will receive insightful management from its contractors. This management will include the knowledge, skills, authority and willingness to use Contractor resources to find better ways of serving Navy clients’ strategic and operational goals and objectives. The Navy's use of performance-based objectives evidences this principle.

Although performance work statements will typically contain several levels of performance assessment, the Navy wants its contractors to exercise maximum discretion within bounds of prudent risk management to adjust processes and resources needed to reach specified objectives at the highest performance level.

1.8.3 Industry Best Practices The third principle is that the Navy will adopt industry best commercial practices and maintain state-of-the-art service delivery. To that end, the Navy's emphasis will be in evaluating performance objectives (end results).

1.9 Standard Template Key to implementing a programmatic approach is using a standard template that ensures Navy-wide consistency yet affords appropriate tailoring to meet local needs. This contract conforms to the standard template and has been tailored for this solicitation. NAVFAC intends to use this template-based approach for future service contracts. Offerors should develop an understanding of the template as part of performing due diligence in reaching an understanding of the Navy’s requirements and expectations.

The standard template contains 18 standard annexes. Annex 1 will always contain information that is relevant to the entire scope of the contract.

Annex 2 contains on-site project management and administration requirements that are relevant to the entire scope of the contract. Annexes 3 through 18 contain the technical information and requirements peculiar to that technical annex. Within each technical annex, the organization of information and requirements are also standardized. Specification Item 1 will always contain General Information. Specification Item 2 will always contain the management and administrative requirements. Specification Item 3 will always contain the Recurring Work requirements.

Specification Item 4 will always contain the Non-Recurring Work requirements. Requirements and standards for higher level specification items apply to all subordinate specification items, e.g., Specification Item 3 standards apply to all recurring work specification items. Specification Item 3.1 is applicable to all 3.1 subordinate specification items.

Specification Items 3.2 and 3.3 are not considered subordinate to 3.1. All costs associated with Annexes 1 and 2 and Specification Items 1 and 2 must be priced and their price must be allocated across the Exhibit Line Items.

1.10 Navy PBSA Approach The Navy’s approach to performance-based service acquisition (PBSA) includes four component parts which are 1) performance outcomes, 2) measurable standards, 3) consideration of incentives, and 4) performance assessment plan.

1.11 Technical Proposal

Certification

The Contractor warrants that its proposal incorporated herein by reference will meet or exceed the performance objectives set forth in this contract.

0200000 – Management and Administration

2 Management and Administration

2.1 Definitions and Acronyms

2.2 General Information

2.2.1 Government Regular Working Hours

2.2.1.1 Observed Federal Holidays

2.2.1.2 Restriction to Contractor Working Hours

2.2.2 Wage Determinations

2.2.3 Requirements Hierarchy

2.3 General Administrative Requirements

2.3.1 Required Conferences and Meetings

2.3.2 Training for Maintenance and Operation of New and Replacement Systems and

Equipment

2.3.3 Partnering

2.3.3.1 Informal Partnering

2.3.3.2 Contract Partnering Administration

2.3.3.3 Contract Partnering Session Attendees

2.3.4 Permits and Licenses

2.3.5 Insurance

2.3.5.1 Certificate of Insurance

2.3.5.2 Minimum Insurance Amounts

2.3.6 Protection of Government Property

2.3.7 Government Information Technology (IT) System

2.3.8 Directives, Instructions, and References

2.3.9 Invoicing Procedures

2.3.10 Forms

2.4 Government-Furnished Property, Materials and Services

2.4.1 Government-Furnished Facilities (GFF)

2.4.2 Government-Furnished Utilities

2.4.3 Government-Furnished Materials (GFM)

2.4.4 Government-Furnished Equipment (GFE)

2.4.5 Government-Furnished Services (GFS)

2.5 Contractor-Furnished Items

2.6 Management

2.6.1 Work Reception

2.6.2 Work Control

2.6.3 Work Schedule

2.6.4 Deliverables

2.6.5 Service Interruptions

2.6.6 NAVFAC MAXIMO

2.6.7 Quality Management System (QMS)

2.6.7.1 Quality Management (QM) Plan

2.6.7.2 Quality Inspection and Surveillance

2.6.7.3 Quality Inspection and Surveillance Report

2.6.8 Property Management Plan

2.6.9 System and Equipment Replacement

2.7 Personnel Requirements

2.7.1 Key Personnel

2.7.1.1 Project Manager (PM)

2.7.1.2 Quality Manager (QM)

2.7.1.3 Site Safety and Health Officer (SSHO)

2.7.1.4 Environmental/Energy Manager

2.7.2 Employee Requirements

2.7.2.1 Employee Certification and Training

2.7.2.2 Employee Appearance

2.7.2.3 Employee Conduct

2.7.2.4 Identification as Contractor Employee

2.7.2.5 Removal of Employees

2.7.2.6 Proof of Legal Residency

2.7.3 Enterprise-wide Contractor Manpower Reporting Application (eCMRA)

2.8 Security Requirements

2.8.1 Employee Listing

2.8.2 Vehicles

2.8.3 Passes and Badges

2.8.3.1 Access Pass Endorsement

2.8.4 Access to Installation

2.8.4.1 DBIDS Program

2.8.4.2 DBIDS Credentials

2.8.5 Access to Buildings

2.8.6 Access Arrangements

2.8.6.1 Escort Arrangement for Secured Areas

2.8.7 Security Clearances

2.8.8 Access to Sensitive Unclassified Information

2.8.9 Access to Navy Marine Corps Intranet (NMCI)

2.8.10 Employee Status

2.8.11 Permission to Use a Camera

2.8.12 Permission to Use Commercial Radio Transmitter Equipment

2.8.13 Permission to Use Heavy Construction Equipment

2.9 Contractor Safety Program

2.9.1 Accident Prevention Plan (APP)

2.9.2 Activity Hazard Analysis (AHA)

2.9.3 Safety and Occupational Health (SOH) Risks and Compliance Plans

2.9.3.1 Alcohol and Drug Abuse Prevention Plan

2.9.3.2 Chemical Hazard Communication Program

2.9.3.3 Confined Space Program

2.9.3.4 Critical Lift Plan

2.9.3.5 Fall Prevention and Protection Plan

2.9.4 Crane Operations

2.9.4.1 Crane Inspections

2.9.4.2 Rigging Gear

2.9.4.3 Crane Operators

2.9.5 Accident and Damage Reporting

2.9.5.1 Accident Reporting and Notification Criteria

2.9.6 Fire Protection

2.9.7 Monthly On-Site Labor Report

2.9.8 OSHA Citations and Violations

2.9.8.1 Japanese Labor Standards Inspection Office (LSIO) Citations and Violations

2.9.9 Safety Inspections and Monitoring

2.9.10 Safety Certification

2.9.11 Safety Apparel on Jobsites

2.9.12 Emergency Medical Treatment

2.9.13 Excavations

2.10 Environmental Management and Sustainability

2.10.1 Energy Management Program

2.10.1.1 Water Conservation Plan

2.10.1.2 Energy Efficient Products

2.10.2 Environmental Protection

2.10.2.1 Sampling, Testing and Laboratory Services

2.10.2.2 Ozone-Depleting Substances Requirements for Refrigerant Recycling

2.10.2.3 Solid Waste Management and Recycling

2.10.2.4 Non-Regulated Waste Disposal

2.10.2.5 Regulated Waste (RW) Disposal

2.10.2.6 Universal Waste (UW)

2.10.2.7 Spill Prevention, Containment, and Clean-up

2.10.2.8 Hazardous Material Management

2.10.2.9 Protection of Endangered and Threatened Species (Flora and Fauna)

2.10.2.10 Noise Control

2.10.2.11 Salvage

2.10.2.12 Asbestos Containing Material (ACM)

2.10.2.13 Clean Air Act

2.10.3 Sustainable Procurement and Practices

2.10.3.1 Environmentally Preferable Products

2.10.3.2 Use of Recovered Materials

2.10.3.3 Use of Biobased Products

2.11 Disaster Preparedness

2.12 Technical Library

2.13 Warranty Management

2.14 Recurring Work Procedures

2.14.1 Notification to the Government for Work Above the Recurring Work Limitations

2.14.2 Recurring Work Exhibit Line Item Numbers (ELINs)

2.15 Non-Recurring Work

2.16 Performance Evaluation

0200000 - Management and Administration

2 Management and

Administration

2.1 Definitions and

Acronyms

Definitions and Acronyms are listed in J-0200000-01.

2.2 General

Information

2.2.1 Government

Regular Working Hours

The Government's regular working hours are from 0800-1630, five days per week, Monday through Friday, except observed Federal holidays and the days specifically designated by the Government. Exceptions to the regular hours of operation are detailed in subsequent sections of this performance work statement (PWS). Work in certain annexes or sub-annexes require Contractor continuous operations outside of the Government’s regular working hours including weekends and holidays. The performance of other work requirements shall be accomplished within the Government’s regular working hours and approved time frame coordinated with clients (hereinafter referred to as Contractor Working Hours), unless the specific work requirement specified herein necessitates otherwise. Any other work outside Contractor Working Hours requires prior Government approval.

2.2.1.1 Observed Federal

Holidays

The Government observes the following holidays: New Year’s Day, Martin Luther King Jr.’s Birthday, President’s Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, and Christmas Day.

2.2.1.2 Restriction to

Contractor Working Hours

If the Contractor wishes to work outside of the Contractor Working Hours for the Contractor’s convenience, the Contractor shall submit a written Request to Work Outside Contractor’s Working Hours per Section F. Excludes work to be performed during specified hours. Any services performed outside of the Contractor Working Hours for the Contractor’s convenience shall be provided at no additional cost to the Government.

Note: The Provost Marshall’s Office (PMO) Pass and Registration Section will process gate passes for Contractor access. The Contractor will have access during the timeframe and days indicated on the gate pass. When the Request to Work Outside Contractor Working Hours has been approved for which the requested working hours are outside of gate pass hours, the Contractor shall obtain access to the Installation in accordance with the instructions specified in Spec Item 2.8.4, Access to Installation of this Annex.

2.2.2 Wage

Determinations

Not applicable (N/A).

2.2.3 Requirements

Hierarchy

Requirements or definitions specified in each spec item of this contract apply to subordinate paragraphs. For example, requirements shown in spec item 3.1 would apply to spec items 3.1.1, 3.1.2, 3.1.2.1 and so on.

Likewise, Performance Standards specified at a lower digit level (i.e. spec item 3.1.1, 3.1.2, 3.1.2.1) apply when performance is assessed at a higher tier (i.e., spec item 3.1) based on the composite work requirements.

2.3 General

Administrative Requirements

2.3.1 Required

Conferences and Meetings

The Contractor shall attend administrative and coordination meetings as required. If requested, in advance by the Contracting Officer (KO), Contracting Officer’s Representative (COR), or the Performance Assessment Representative (PAR), the Contractor shall provide sign-in sheets and prepare minutes of the meetings and submit per Section F. Comments received within two working days shall be incorporated into the minutes and a copy of the final revision shall be submitted per Section F. Recording of meetings is prohibited.

2.3.2 Training for

Maintenance and Operation of New and Replacement Systems and Equipment

When construction, renovation, or repair work is performed by means other than this contract, the Contractor shall attend Government provided training, as applicable, for maintenance and operation of new and replacement systems and equipment at no additional cost to the Government.

2.3.3 Partnering To increase the likelihood of successful performance of this contract, the Government requires cohesive partnerships with its Contractors and subcontractors. Key stakeholders, including the supported commands who will receive services, principal individuals from Naval Facilities Engineering Command (NAVFAC), the performance assessment (PA) team, and representative(s) of the installation(s) will be invited to participate in the partnering process. Key members of the prime and sub-contractor teams, including senior management personnel must participate. The partnership will draw on the strength of each organization in an effort to achieve quality contract services done right the first time, within the contract price, as scheduled, and without any safety mishaps.

Partnering should accomplish three goals:

− The first goal is to develop a cohesive team with common purpose, commitment and established communication processes.

− The second goal of partnering is contract specific, identifying risks and opportunities for the team to address.

− The third goal is to sustain the Partnership throughout the contract by identifying and addressing issues that affect the Partnership.

2.3.3.1 Informal Partnering The KO shall organize the initial Partnering Meeting with key personnel of the project team, including Contractor's personnel and Government personnel.

The initial session will be scheduled concurrent with the Pre-Performance Conference and held no later than 30 days after award and will be held at a Government provided facility as designated by the KO.

The Initial Informal Partnering Session will be conducted and facilitated by the KO. The senior Government stakeholder present will lead the meeting, however, the Contractor’s Project Manager (PM) or senior representative is encouraged to participate as co-lead.

The Partners will determine the frequency of the follow-on sessions.

2.3.3.2 Contract Partnering

Administration

Upon award, the Administrative Contracting Officer (ACO) will contact the Contractor, supported command(s), Region, and Installation(s) stakeholders, and the PA team to discuss implementation of partnering. A partnership agreement, The Charter, should be in place as early as possible so issues arising, even before work begins, can be resolved using the issues resolution process. Replacement of Core Management Team members (stakeholders who attended the initial session and manage the contract work day-to-day) is discouraged since it will disrupt the synergy that has been developed. If replacement of a team member proves to be unavoidable, a follow-on partnering session must be held to officially turn the responsibilities of the position over to the new member.

The Core Management Team consisting of the attendees below must be present during the initial and all follow-on partnering sessions. These are the core mandatory attendees. Other stakeholders may attend if they desire or as recommended by the partners.

2.3.3.3 Contract Partnering

Session Attendees

The Contractor shall bring the necessary personnel to successfully partner on this contract. Asterisk (*) indicates mandatory personnel.

President/Vice President

* PM

* Quality Manager (QM)

* Interpreter (if Contractor mandatory personnel do not read, speak or understand English) Site Safety and Health Officer (SSHO)

2.3.4 Permits and

Licenses

The Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable Federal, host nation (Japanese), prefecture, and local laws and regulations.

The Contractor shall submit copies of Permits and Licenses per Section F.

2.3.5 Insurance The Contractor shall submit a Certificate of Insurance per Section F as evidence of the existence of the following insurance coverage in amounts not less than the amounts specified below in accordance with the FAR Clause

52.228-5, INSURANCE – WORK ON A GOVERNMENT

INSTALLATION. This insurance must be maintained during the performance period.

2.3.5.1 Certificate of

Insurance

The Certificate of Insurance shall provide for at least 30 calendar days written notice to the KO by the insurance company prior to cancellation or material change in policy coverage. Other requirements and information are contained in the aforementioned insurance clause.

2.3.5.2 Minimum

Insurance Amounts

The Contractor shall procure and maintain, during the entire period of performance under this contract, the following minimum insurance coverage:

Comprehensive General Liability: ¥50,000,000 per occurrence

Automobile Liability: ¥20,000,000 per person, ¥50,000,000 per occurrence for bodily injury, ¥2,000,000 per occurrence for property damage

Workmen's Compensation: As required by Japanese worker's compensation and occupational disease statutes

Employer's Liability coverage: ¥10,000,000, except in states where worker's compensation may not be written by private carriers

Other as required by Japanese law

2.3.6 Protection of

Government Property

During execution of the work, the Contractor shall protect Government property. The Contractor shall return areas damaged as a result of negligence under this contract to their original condition at no cost to the Government.

2.3.7 Government

Information Technology (IT) System

Information delivered to the Government via the internet shall be compatible with, and meet the requirements of MCAS Iwakuni Marine Corps Enterprise Network (MCEN) to ensure Government receipt of such information.

2.3.8 Directives, Instructions, and References

Department of Defense (DoD), Secretary of the Navy (SECNAV), Chief of Naval Operations (OPNAV), and other applicable Directives, Instructions, and References are listed in J-0200000-02. Additional directives, instructions, and references are listed in Section J of Annex 15. Publications from U.S. Government agencies can be obtained from the Construction Criteria Base website at: http://www.ccb.org/.

The Contractor shall comply with the most current version of directives, instructions, and references including versions published during the term of the contract.

There may be agreements between the Host Nation (Japan) and military Installation rather than Federal and state laws. The Government will provide directives, instructions, and references as necessary and when requested.

The Contractor shall obtain commercial publications as required for their use and these publications shall remain the property of the Contractor.

2.3.9 Invoicing

Procedures

The Contractor shall follow the procedures set forth in Section G in accordance with DoD Federal Acquisition Regulation Supplement (DFARS) Clause 252.232-7003 titled “Electronic Submission of Payment Requests and Receiving Reports” and DFARS 252.232-7006 titled “Wide Area Workflow Payment Instructions.” This contract/order requires use of the DoD Wide Area Workflow (WAWF) Receipt and Acceptance system for the submission of invoices.

The web-based system located at http://wawf.eb.mil provides the technology for Government Contractors and authorized DoD personnel to generate, capture, and process receipt and payment-related documentation in a paperless environment. Invoices rendered under this contract shall be submitted per set procedures that will be provided by the KO or the COR after contract award.

Refer to Invoice Cover Form (NAVFAC/7300/30) in J-0200000-03 for sample.

2.3.10 Forms Forms referenced in this Annex, e.g. accident reporting, and damage reporting will be provided to the Contractor by the Government after contract award. The forms are subject to change and the Contractor shall confirm with the KO or the COR the most updated versions prior to submission.

2.4 Government-

Furnished Property, Materials and Services

In accordance with Section H, relevant paragraph stated for the Government- Furnished Property and the following paragraphs, the Government will furnish or make available to the Contractor certain Government-owned facilities, utilities, materials, equipment and services for use in connection with this contract as stated below.

The use of the Government-Furnished Property, Materials, and Services for any other purpose is prohibited.

2.4.1 Government-

Furnished Facilities

(GFF)

None.

2.4.2 Government-

Furnished Utilities

The Government will furnish water and electricity at existing outlets required for the work to be performed under the contract. The Contractor shall provide and maintain, at its expense, the necessary service lines from the existing Government outlets to the work site. Provide and maintain backflow prevention devices on connections to domestic water lines and electrical transformer provisions on connections to electric lines. Meet all Federal, Japanese, prefectural, local, and Installation codes and regulations for backflow prevention devices and electrical transformer provisions. Services http://www.ccb.org/ http://wawf.eb.mil/ required by the Contractor, for which there are no available Government outlets, shall be provided by the Contractor at no cost to the Government.

The Contractor is not responsible for the cost of all utilities at all Government-provided facilities.

2.4.3 Government-

Furnished Materials (GFM)

None.

2.4.4 Government-

Furnished Equipment (GFE)

None.

2.4.5 Government-

Furnished Services

(GFS)

None.

2.5 Contractor-

Furnished Items

Except for items identified as Government Furnished, the Contractor shall provide all equipment, materials, parts, supplies, components, and facilities to perform the requirements of this contract. The KO or the COR may inspect Contractor-furnished items for adequacy and compliance with contract requirements. Inadequate or unsafe items shall be removed and replaced by the Contractor at no cost to the Government. Materials containing asbestos, lead, and polychlorinated biphenyls (PCB) shall not be brought onsite.

Energy efficient tools and equipment shall be used when available. The KO or the COR may at any time require Samples, Safety Data Sheets (SDS) or Manufacturer’s Data Cut Sheets of Materials used in this contract. The Contractor shall submit the Samples, SDS or Manufacturer’s Data Cut Sheets of Materials per Section F when requested.

2.6 Management The Contractor shall manage the total work effort associated with the services required herein to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality assurance. The Contractor shall provide a staff with the necessary management expertise to ensure performance objectives and standards are met.

2.6.1 Work Reception The Contractor shall provide a work reception function with the bilingual (English/Japanese) capability to receive, prioritize, correspond, and respond to Government inquiries during Government regular working hours and provide a point of contact (POC) at a local or toll free number who can perform the above function during other than Government regular working hours.

2.6.2 Work Control The Contractor shall implement all necessary work control procedures to ensure timely accomplishment of work requirements, as well as to permit tracking and reporting of work in progress. The Contractor shall plan and schedule work to assure material, labor, and equipment are available to complete work requirements within the specified time limits and in conformance with the quality standards established herein. Verbal scheduling and work status updates shall be provided when requested by the KO, the COR, or the PAR. A written status update of any item of work must be provided in Daily Report per Section F. A copy of the Daily Report form is provided in J-0200000-04. The Contractor shall refer to and include all applicable contents in the above mentioned form as part of the contents of the work status report (daily report). Refer to the relevant sections in the technical Sub-annex for more information.

2.6.3 Work Schedule The Contractor's work shall not interfere with normal Government business.

In those cases where some interference is unavoidable, the Contractor shall minimize the impact and effects of the interference. The Contractor shall provide advance access of all of its work schedules to the Government. The Contractor shall notify the KO or the COR of any difficulty in scheduling work due to Government controls.

The performance at night is anticipated in locations and times as specified below:

The following locations require performance during the specified working days and times. The day ad timeframes are subject to change.

Bldg # Facility Name Day Time (*See Note below)

600 Club Iwakuni

First Floor Dining Kitchen

Monday through Thursday

2400 – 0500

600 Club Iwakuni

Second Floor Dining Kitchen

Sunday through Thursday

2400 – 0500

410 Food Court

Burger King (BK) Monday through Friday

2400 – 0500 Kentucky Fried Chicken (KFC) Taco Bell and Pizza Hat

222 South Side Mess Hall Monday through Thursday

1800 – 0500

1562 North Side Mess Hall Monday through Thursday

1800 – 0500

1333 Bowling Alley Monday through Friday

1800 – 0500

615 Defense Commissary Agency (DeCA) Store

Monday 0800 - 1630

6222 Flight Line Dining *Note: updates will be made in future modification if necessary.

637 Child Care Center (CCC) *Note: updates will be made in future modification if necessary.

1600 The Hanger E-Club

Taco Bell (First Floor)

Sunday through Saturday

2200-0600

BK (First Floor) Sunday through Saturday

2200-0600

Enlisted Club (Second Floor)

Monday 0800 – 1600* see note (2)

Tuesday through Saturday

1330 – 1700

9520 Chili’s Restaurant Monday 0800 – 1600

Tuesday through Sunday

2400 - 0700

*Note:

(1) Specified times in the above table are anticipated timeframes.

(2) Bldg #1600 enlisted club (second floor) is temporarily closed on Monday’s at the point of solicitation. The indicated time (hours) will be changed and provided by the Government (either the COR, PAR or the supporting commands) when the enlisted club is open on Monday’s.

The Contractor shall provide close coordination with supported commands and departments as appropriate to establish the schedules of this contract.

The POC for all relative supported commands and departments will be provided by the COR after the award of the contract.

Work schedules required for Recurring Work under the technical sub-annex shall be submitted for Government acceptance per relevant sections in technical sub-annex. In no event shall the Contractor change the accepted schedule without prior written approval of the Government. For changes or additions to any job that prevent the Contractor from completing the work on time or which change the scope of work, the Contractor shall report the work in Daily Report.

2.6.4 Deliverables Records and reports are specified in Sections C, F, H, I, J, and within the Directives, Instructions, and References. The Contractor shall submit accurate and complete documents within the specified timeframes. The Contractor shall revise/modify records and reports, as directed by the KO, at no additional cost to the Government. All Contractor submittals shall be in English or may be submitted in Japanese with English translations.

Government acceptance of deliverables shall not relieve the Contractor of the responsibility for any error or omission which may exist in the deliverable, as the Contractor is responsible for all requirements of this contract.

2.6.5 Service

Interruptions

If any utilities or other services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the KO or the COR, affected tenants, and customers in accordance with local procedures, which will be provided by the KO or the COR after contract award. If the discontinued service is due to an emergency breakdown the Contractor shall notify the KO or the COR, affected tenants and customers as soon as practicable.

2.6.6 NAVFAC

MAXIMO

N/A.

2.6.7 Quality

Management System (QMS)

The Contractor shall establish and maintain a complete QMS program in accordance with the provisions specified herein. The Contractor’s QMS program shall provide an effective and efficient means of identifying and correcting problems throughout the entire scope of operations. The Contractor's QMS program shall address:

• Accurate documentation of work processes, procedures, and output measures.

• A systematic procedure for assessing compliance with performance objectives and standards.

• Accurate documentation of quality inspections and surveillance conducted throughout the execution of work.

• Assessment-driven corrective actions and process adjustments as appropriate in a timely manner.

The Contractor QMS Pre-Performance Review Checklist (self-checklist) for compliance with this requirement is provided in J-0200000-05.

2.6.7.1 Quality

Management (QM) Plan

The Contractor shall develop and submit a QM Plan per Section F. The QM Plan shall describe the QMS methodology and approaches used under this contract. If any changes are made during the period of performance, submit a revised QM Plan per Section F.

2.6.7.2 Quality Inspection

and Surveillance

The Contractor shall establish and maintain an inspection and surveillance system in accordance with the FAR Clause 52.246-4, INSPECTION OF SERVICES – FIXED PRICE, to ensure that the work performed conforms to the contract requirements. The Contractor shall document and maintain a file of all scheduled and performed inspections and surveillances, inspection and surveillance results, and dates and details of corrective and preventive actions. The Quality Inspection and Surveillance File shall be the property of the Government and made available during the Government’s regular working hours. The file shall be submitted per Section F.

2.6.7.3 Quality Inspection

and Surveillance Report

The Contractor shall submit a copy of the Contractor Quality Inspection and Surveillance Report per Section F. The Government may adjust the frequency of the submittal based on the Contractor’s quality of performance.

2.6.8 Property

Management Plan

The Contractor shall establish and maintain a plan that meets the contract clause requirements of Specification Item 2.4, Government-Furnished Property, Materials and Services, of this Annex. This plan shall identify the Contractor’s policies, procedures, and practices in receiving and performing physical inventories, repairing and maintaining, preserving and protecting, and reporting the disposition of accepted government property in its possession. The Property Management Plan shall be submitted per Section F.

2.6.9 System and

Equipment Replacement

The Contractor shall maintain the integrity and performance of existing energy saving, water conservation or other sustainability design features of systems and equipment in the performance of repair and replacement work.

Except where otherwise specified, replacement components shall be of the same model/style or equivalent as the component being replaced. Substitutes for replacement components must be accepted by the KO or the COR prior to use. The KO or the COR will furnish available information for the existing systems and equipment.

2.7 Personnel

Requirements

The Contractor shall comply with the personnel requirements stated below.

2.7.1 Key Personnel The Contractor shall submit a List of Key Personnel and Qualifications per Section F. The Contractor shall provide any additional information requested by the KO or the COR necessary to certify their qualifications.

When the Contractor intends to appoint new Key Personnel and/or interpreter, prior acceptance shall be obtained from the KO or the COR per Section F.

The Contractor shall submit an Organizational Chart per Section F showing lines of authority of the key personnel, on-site supervisor(s) and the interpreter (if applicable) for this contract. The chart shall include names of personnel and their position title in this contract. As a minimum, include the PM, QM, SSHO, and on-site supervisor(s) and who they will report directly to for this contract. The key personnel and interpreter shall be revised as applicable for the contract and as requested by the KO or the COR.

Key personnel shall be able to speak, read and comprehend English to the extent that they can perform the contract requirements and comply with Installation emergency procedures or an interpreter shall be made available at no additional cost to the Government.

2.7.1.1 Project Manager

(PM)

The Contractor shall provide a PM and designated alternate, as applicable, who has the have full authority to act for the Contractor on all contract matters relating to this contract. The PM or alternate shall be available on-site (any given work site) within one hour after Government request both during and after the Government's regular working hours.

The PM shall have satisfactory relevant experience at a comparable level of responsibility on contracts of similar size, scope and complexity.

The PM shall not be the same person as the QM.

2.7.1.2 Quality Manager

(QM)

The Contractor shall provide a QM or designated alternate who shall be on-site during performance of work and shall be available on-site within two hours after the Contractor’s Working Hours. The QM must report directly to a senior corporate official and shall not report directly to the PM.

The QM shall have fulfilled the following pre-requisite training and experiences before being hired as the QM under this contract:

The QM shall have satisfactory experience in preparing and enforcing QMS programs on contracts of similar size, scope and complexity.

The QM may be the same person as the SSHO.

The QM shall not be the same person as the PM.

2.7.1.3 Site Safety and

Health Officer

(SSHO)

The SSHO must meet the requirements of EM 385-1-1 Section 1 and ensure that the requirements of 29 Code of Federal Regulations (CFR) 1926.16 are met for the project. Provide a Safety oversight team that includes a minimum of one Competent Person at each project site to function as the SSHO. The SSHO or an equally-qualified Designated Representative (DR)/alternate shall be on-site at all times when work is being performed to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan (APP). The SSHO's training, experience, and qualifications shall be as required by EM 385-1-1 paragraph 01.A.17, entitled SITE SAFETY AND HEALTH OFFICER (SSHO), and all associated sub-paragraphs.

A Competent Person shall be provided for all of the hazards identified in the Contractor's Safety and Health Program in accordance with the accepted APP, and shall be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. Provide the credentials of the Competent Persons(s) to the KO for acceptance in consultation with the Safety Office when requested.

The Contractor shall provide a SSHO whose primary duty and responsibility is to prepare and enforce the Contractor’s safety program on this contract.

The SSHO shall have fulfilled the following pre-requisite training and experiences before being hired as the SSHO under this contract:

The SSHO shall have satisfactory experience in preparing and enforcing safety programs on contracts of similar size and complexity in the past, and have completed the OSHA 30-hour construction safety class or equivalent.

The SSHO shall maintain competency through 24 hours of formal safety and health related coursework every four years.

Note: The Japan Construction Occupational Safety and Health Association (JCOSHA) provides the construction site safety and health management course “KOUJI SHUNIN COURSE”, or “SYOCHOU COURSE”, which is as acceptable equivalent to the 30-hours OSHA safety class. This training can be viewed at the JCOSHA website.

https://www.kensaibou.or.jp/ or https://www.kensaibou.or.jp/eng/index.html

This training course has five (5) years of validated date. SSHO shall maintain renewal of certificate. The refresher course is also an equivalent course after the initial training course has been completed.

The Contractor shall submit the certificate(s) or documentation for completion of the training(s) per Section F. 24 Hours of Formal Safety Training shall be competent and qualified safety training from sources such as JCOSHA. Refer to the Q and A of SSHO 24 Hours of Formal Safety Training provided in J-0200000-02.

The SSHO may be the same person as the PM or QM but shall have fulfilled the pre-requisite qualification and experience.

2.7.1.4 Environmental/

Energy Manager

Not required.

2.7.2 Employee

Requirements

The Contractor shall provide experienced, qualified, and capable personnel to perform the work in this contract. Personnel shall be fully knowledgeable of all safety, environmental, and energy requirements associated with the work they perform. The Contractor shall provide personnel who can speak, read, and comprehend English to the extent that they can perform the contract requirements and comply with Installation emergency procedures or an interpreter shall be furnished at no additional cost to the Government.

Personnel shall be revised as applicable for the contract and/or as requested by the KO or the COR.

The Contractor shall ensure that all Contractor personnel have received proper safety training, appropriate to their respective jobs.

After contract award, when available and within the base period, the Contractor shall complete the Government provided training entitled “Environmental Compliance Course (ECC)” which will be provided at no cost to the Contractor. Once completed, the Contractor shall ensure all personnel within their organization working aboard the Installation are familiar and in compliance with the contents and requirements provided from the training in the performance of their daily work.

https://www.kensaibou.or.jp/eng/index.html

The Contractor shall implement an ongoing training program that refreshes the safety skills, qualifications and awareness of the Contractor workforce on a regular, periodic basis. The details of the Contractor’s safety training program shall be included as part of the Contractor’s APP, as required in Spec Item 2.9.1 of this Annex.

2.7.2.1 Employee

Certification and Training

The Contractor shall maintain personnel certification, training, and licensing records for employee requirements specified herein and within all technical annexes/sub-annexes. Certification, training, and licensing records shall be kept current and on file for the duration of the contract including all option periods. Records shall be made available for Government review within four hours of request.

2.7.2.2 Employee

Appearance

The Contractor shall ensure that all employees present a professional appearance that is appropriate for their position. The KO reserves the right to determine the acceptability of any clothing worn. All Contractor and subcontractor employees working under this contract shall be identified by a distinctive nameplate, emblem, or patch attached in a prominent place on an outer garment. Employee identification shall not be substituted for Installation-required passes or badges.

2.7.2.3 Employee Conduct Contractor employees shall conduct themselves in a proper, efficient, courteous and businesslike manner.

2.7.2.4 Identification as

Contractor Employee

Contractor employees shall identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel and displaying distinguishing badges or other visible identification for meetings with Government personnel. All Contractor employees shall appropriately identify themselves as Contractor employees in telephone conversations and in formal and informal written correspondence.

2.7.2.5 Removal of

Employees

The Contractor shall remove from the site any individual whose continued employment is deemed by the KO to be contrary to the public interest or inconsistent with the best interests of National Security.

2.7.2.6 Proof of Legal

Residency

No employee or representative of the Contractor will be admitted to the site of work unless satisfactory Proof of Citizenship is furnished or Alien Legal Residency within Japan is confirmed.

2.7.3 Enterprise-wide

Contractor Manpower Reporting Application (eCMRA)

The Contractor shall report all Contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract via a secure data collection site. The Contractor is required to completely fill in all required data fields using the following web address: https://www.ecmra.mil

Per Section F, reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk, linked at https://www.ecmra.mil.

2.8 Security

Requirements

The Contractor shall comply with all Federal, Japanese, prefectural, and local security statutes, regulations, and requirements. The Contractor shall become acquainted with and comply with all Government regulations as posted, or as requested by the KO or the COR when required to enter a Government site.

The Contractor shall ensure that all security/entrance clearances are obtained.

2.8.1 Employee Listing The Contractor shall maintain a current Employee List and submit per Section F.

2.8.2 Vehicles The company name shall be displayed on each of the Contractor's vehicles in a manner and size that is clearly visible. All vehicles shall display a valid https://www.ecmra.mil/ https://www.ecmra.mil/ license plate that complies with Japanese Vehicle Code. Vehicles shall meet all other requirement of the Japanese Vehicle Code, such as safety standards, and shall carry proof of insurance and state registration, if applicable.

The Contractor shall submit a Vehicle List per Section F along with the Employee List described in Spec Item 2.8.1, Employee Listing.

2.8.3 Passes and Badges All Contractor employees shall obtain the required employee passes per Marine Corps Air Station Order (MCASO) 5560.8, Motor Vehicle Traffic Supervision and MCASO 5500.2, Installation Access Control. The procedures of obtaining the passes will be provided by the KO or the COR after contract award.

Refer to Spec Item 2.8.3.1, Access Pass Endorsement, if Contractor employees already possess MCAS Iwakuni access passes for other contracts (their primary contracts).

The PMO Pass and Registration Section will issue access passes without charge. Each employee shall have their pass in their possession at all times and present it when requested by security authorities.