N4008023R0015 Amendment 0003.pdf

PDF 333 KB Posted

Attached to
Replace Failing Yard Patrol (YP) Pier and Wave Screen, 87NS, Naval Support Activity (NSA) Annapolis, MD
Solicitation number
N4008023R0015
Issued by

About this file

This document provides an amendment to a solicitation for a federal construction contract. The amendment extends the proposal due date from May 2nd to May 9th, 2023 at 2:00 PM. It also provides revisions to specifications, drawings, and responses to pre-proposal inquiries. The work involves replacing a failing yard patrol pier and wave screen at Naval Support Activity Annapolis, Maryland. Relevant changes include extensions to submittal requirements, revised price proposal forms, updated permit drawings, and clarifications to structural and electrical details, coating requirements, and pile installation specifications. The Navy is the contracting agency for this project, which aims to replace deteriorating waterfront infrastructure.

View the file

Other files

File Type Posted
23R0015 0006.pdf PDF
23R0015 Amendment 0005.pdf PDF
8005.pdf PDF
215492.pdf PDF
23R0015 Amendment 0004.pdf PDF
215491.pdf PDF
E-514.pdf PDF
E-511.pdf PDF
ATTACHMENT H - Price Proposal Form V3.docx DOCX document
E-601.pdf PDF
22-SF-0205 Approved Plans YP Basin Pier and Quaywall.pdf PDF
23R0015 Amendment 0002.pdf PDF
ATTACHMENT H - Price Proposal Form V2.docx DOCX document
ATTACHMENT G - SB Subcontracting Plan.docx DOCX document
YP Pier Replacement site visit 11 APR 23.pdf PDF
23R0015 Amendment 0001.pdf PDF
ATTACHMENT G - SB Subcontracting Plan.pdf PDF
23R0015 Final Specifications.pdf PDF
Attachment A- PIEE Vendor Access Instructions.pdf PDF
ATTACHMENT C - Construction Experience Project Data Sheet.pdf PDF
ATTACHMENT H - Price Proposal Form.pdf PDF
23R0015 Final Drawings.pdf PDF
ATTACHMENT E - SB Subcontracting Record.pdf PDF
ATTACHMENT D - PPQ.pdf PDF
Attachment B - PPI Log.xlsx XLSX spreadsheet
ATTACHMENT F - SB Participation and Commitment.pdf PDF
N4008023R0015 RFP.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment hereby provides an extension to the proposal due date, revisions to specifications and draw ings, and PPI responses. See Continuation Page.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 32

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 22-Apr-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008023R0015

X 9B. DATED (SEE ITEM 11)

29-Mar-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

22-Apr-2023

CODE

NAVAL FACILITIES ENGINEERING SYS COMMAND

1314 HARWOOD STREET SE

WASHINGTON DC 20374

N40080 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008023R0015

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0003

22 APRIL 2023

This amendment hereby:

1. Revises proposal due date FROM 02 May 2023 1400 local time TO 09 MAY 2023, 1400 LOCAL TIME

2. Provides Revised Attachment H – Price Proposal Form

3. Provides 22-SF-0205 Approved Plans YP Basin Pier and Quaywall PDF

4. Provides Updated Wage Determination MD20230012 04/07/2023 State: Maryland, Construction Type:

Heavy, County: Anne Arundel County in Maryland.

5. Provides revisions to Specifications and Drawings

6. Provides Revised Drawings PDF

7. Provides PPI Response

5. Provides revisions to Specifications/Drawings

The specifications and drawings are hereby amended as follows:

A. In Section 01 14 00 insert the following paragraph: 1.2.e. Wave screen and pier 87NS demolition must be executed in a manner to ensure the basin remains protected and operational as active Navy operations will continue throughout the project. Develop and present plan for work in coordination with submittals under sections 01 32 17 and 02 41 00 to ensure efficient execution of the work while maintaining safe operating conditions within the basin.

B. In Section 01 14 00 insert the following paragraph: 1.2.f. There are no wildlife-related time of year restrictions for this project. Contractor must remain observant of onsite conditions and notify the Government in the event any nesting wildlife or changes in marine activity are observed within or up to 50 feet adjacent to the project limits.

C. On sheet S-519 under Detail D5 insert the following: Note: If fender system is installed as pre-assembled system and access for welding the “heel” side of the bracket is not possible without damage to the fender welding may be reduced to three sides.

D. In Section 03 62 16 add the following to paragraph 2.1.1: Jacket system must provide at least three inches (3”) coverage around any face of the wave screen pile. Jacket system may be round or rectangular in shape and will be submitted for approval. The jacket system shall be aligned and set in a manner to ensure a uniform bottom elevation of the wave screen system, will bear on, or partially embedded in, the mudline. The jacket system will support the installation of material to support the wave screen panels in the design position with minimum 2’-0“ clearance to the mudline and will remain in place as part of the finished construction.

E. On sheet S-502 under Detail C5 insert the following: Note: 2’- 0” elevation minimum with variation not to exceed 2’- 3” from the mudline. Refer to section 03 62 16 for details on material, configuration, and installation of jacket system.

F. On sheet E-516 add the following: Sheet note 1: Concrete for temporary pier electrical components is to be standard concrete, not marine concrete.

G. In Section 32 62 23.13 Delete text of paragraph 3.1.1.c in its entirety and replace with: not used.

H. In Section 26 42 13 paragraph 2.1.2.1 delete the sentence “Provide a minimum of 14 aluminum anodes with an unpackaged weight of 240 pounds at uniform distances along the sheet pile wall.” Insert as the replacement second sentence of 2.1.2.1 "Provide a minimum of 170lb anodes every 20'-0" along the sheet pile wall at a minimum and no more than 10’ – 0” from the starting point of new sheet pile."

I. In Section 05 50 13 make the following changes:

Delete paragraphs 2.9.2 e., f., and g.

Delete paragraphs 2.9.3.1, 2.9.3.2, 2.9.3.3, 2.9.3.4, and 2.9.3.5.

Delete the first two paragraphs of 2.9.5 and replace with:

“Manufacturer Qualifications: All primary products specified in this section will be supplied by a single manufacturer with a minimum of 5 years experience in design and manufacturer of deployable stairway systems and evidence of a minimum of 15 projects.

Installer Qualifications: All work listed in this section is to be installed by a contractor approved by the manufacturer. Manufacturer representative must be on-site during installation to provide advisory services."

J. In Section 09 97 13.26 paragraph 3.2 second sentence delete the phrase “steel wave screen wales, and pile to pier connection assemblies”.

K. For details D1 and D3 on sheet S-519 insert as follows: Note 1 all connecting hardware materials to be galvanized.

L. Section 05 12 00 paragraph 1.5.3 delete in its entirety.

M. Existing utilities at the head of Pier 87NS are provided below.

There is no requirement for underground utility work at the temporary piers that will impact existing utilities.

N. Anchor rod and bolt additional details:

Anchors on the drawings that are not shown as hooked, headed, or secured via an embedded plate are post concrete casting installed. Table on S-002 provides the tension capacity requirements for anchors by size.

The following summary categorizes post installed versus embedded in the drawings:

Post installed anchors:

1. A1 of S-503 wave screen wale anchors

2. S-507 Rubber fender anchors

3. S-511 Utility Trench Support Frame anchors

4. S-512 Handrail mounting anchors

5. S-513 ladder mounting anchors

6. Overhang walkway mounting to pier C4 and C5 on S-516

7. Rubber push knee fender for monopoles S-519

8. C5 of S-526 Utility Platform base plate anchorage

9. Misc. utility and electrical anchors

Cast in place embedded anchors:

1. A2 of S-504 wave screen retainer anchor rods

2. C1 of S-514 cleat foundation anchors

3. A3 of S-514 hooked light pole anchorage

4. D3 of S-519 monopile pad eye anchor rods to finger pier

5. L-bolts for strut channel anchorage per E-516 and E-517

Any instance not outlined in this summary must be cast in place embedded unless specifically approved otherwise by the Government.

All anchors are subject to submittal requirements for material, manufacturer performance data, and shop drawing requirements as defined in the specifications.

O. This amendment includes updated drawings. These drawings are to be integrated into the contract drawings as follows:

Sheet Action G-001 Delete original, replace with Amendment 0003 version that includes MDE stamp.

G-002 Delete original, replace with Amendment 0003 version that includes MDE stamp.

G-100 Delete original, replace with Amendment 0003 version that includes MDE stamp.

EC-101 Delete original, replace with Amendment 0003 version that includes MDE stamp.

EC-102 Delete original, replace with Amendment 0003 version that includes MDE stamp.

EC-103 Delete original, replace with Amendment 0003 version that includes MDE stamp.

EC-104 Delete original, replace with Amendment 0003 version that includes MDE stamp.

EC-105 Delete original, replace with Amendment 0003 version that includes MDE stamp.

EC-500 Delete original, replace with Amendment 0003 version that includes MDE stamp.

EC-501 Delete original, replace with Amendment 0003 version that includes MDE stamp.

EC-502 Delete original, replace with Amendment 0003 version that includes MDE stamp.

E-511 Delete original, replace with Amendment 0003 updated details for power pedestals including emergency shutoff requirement and additional components.

E-514 Delete original, replace with Amendment 0003 updated single line diagram, temporary pier single line diagram, and additional wiring for shunt trip breakers.

E-601 Delete original, replace with Amendment 0003 updated panel schedules including shunt trip breaker for emergency shutoffs.

6. Provides Revised Drawings PDF

E-511 E-514 E-601

7. Provides PPI Response

# Reference Question Government Response

Page Para Sect 6 19 01 57 19.00

3.5.1 Section states, "Notify the Air

Program Manager, through the Contracting Officer, at least 6

No, Bid per RFP. If the selected offeror has a specific piece of equipment months prior to bringing equipment, assembled or unassembled, onto the installation, so that air permits can be secured." If this is the case, please confirm that out of the 720 calendar day contract duration for at least the first 180 days no work will be allowed onsite that requires equipment per this specification section.

that is subject to CAA permitting notification should be made immediately so the Government can obtain these permits promptly to minimize any impacts.

7 26 27 29 2.3 Please provide a Basis of Design for the Power Pedestals

See Amendment 0003 for attached updated electrical sheets

8 CU101-

Drawings Please verify that the only system requiring Heat Trace is the 2" domestic water line within the new utility trench, and corresponding branches to yard hydrants and power pedestals.

Confirmed.

9 E-108 Drawings Please provide a One-line diagram for the Temporary Distribution equipment as depicted on Drawing E-108.

See Amendment 0003 for attached updated electrical sheets

10 G-100 Drawings Note. 3 on G-100 describes a partial demolition and reconstruction approach at the T- Head. Can the entire existing YP Pier and Wave Screen be demolished and then the new Main Pier with Wave Screen constructed or is there a staged demolition/construction approach that needs to be followed?

See Amendment 0003 for addtional information in section 01 14 00.

11 S-109-

Drawings Are the five (5) temporary mooring/swing piers, associated 48" monopile mooring dolphins and timber walkway to be removed after the new Main Pier is commissioned?

No, Bid per RFP.

12 2 Attachment H Price Proposal

Form

Sub-CLIN 0003AE item description is for 30" Dia. Steel Piling, but no 30" Dia. Steel Piling is shown on the plans.

There also appears to be missing items for 36" and 48" Dia. Steel Piling. Please clarify the basis of bid for the Price Proposal Form.

See Amendment 0003, revised Price Proposal Form.

13 8 31 62 23.13 3.2.7 The referenced specification states that all soils and other extraneous material shall be removed from pile prior to placing concrete. Please confirm this specification is only for the

Confirmed.

two (2) 36" Dia Anchor Pile excavation depth shown and it is not the intent to fully excavate the 24" and 36" monopile.

14 C1/S-

D3/S-

Drawings The referenced details show chain tensioner U-bolt assemblies. Please provide details indicating dimensions and material requirements for the U-bolts and center plate as shown.

Use a 2" U-Adjuster Tensioner (other product names include Double Adjustable Shackle, Dog Bone Shackle, and U-Chain Tensioner). The tensioner shall use 2"Ø bolts (M52 equivalent). Basis of design chain tensioner is a Dawson Group Ltd product, but several equivalents are manufacturered and must be submitted for approval under section 35 59 13.16 paragraph 2.1.7.

15 D1/S-

B3 and B5/S-

C4/S-

Drawings The referenced details show a 1- 1/2" thick pad-eye attached with a 5/16" fillet weld. Two of the details show pad eyes mounting to a 1/2" base plate. This is notably lighter than other components in the assemblies.

Please confirm that 1/2" base plates and 5/16 fillet welds are what are required in these details.

Bid per RFP.

16 C1/S-

B2/S-

Drawings The referenced drawing shows a "stair stepped" configuration for composite panels and support steel. We have not found any detail for enclosing the risers of these steps. Is a closure required at these risers? If so, please provide a details for that closure.

No, Bid per RFP.

17 09 97 13.26 09 97 13.27

The both referenced specifications, para 1.4.6.4, indicates that the Quality Assurance Inspector for coatings be employed by an SSPC QP 5 certified company. Please confirm that this is intended for field coating applications and that shop coating inspector qualifications are to be in accordance with the shops quality programs audited under their AISC Certification (with coatings endorsement) and/or NACE Certification. (Note: Both the Welding and Structural Steel

Bid per RFP. 09 97 13.26 and 09 97 13.27 covers both field and shop applications for new steel components respectively to each coating system. The intent of both specifications is to require the quality assurance coatings inspector to be qualified in accordance with an SSPC QP5 company.

spec indicated AISC Certification BU is required.)

18 09 97 13.27 The referenced specification, para 1.4.6.5, indicates field coating to be performed by contractor certified to SSPC QP1 and QS1 requirements. Does this requirement also apply to field application of touch-up coatings, eg, field welds, handling damage, etc?

Confirmed. Section 09 97

13.27 1.4.6.5 requires coating contractor company to be certified to both SSPC QP 1 and SSPC QS 1 for all coating applications including holiday and spot repairs per 3.6.3.7.

19 01 57 19 1.8 Please provide all permit documents for this project.

See Amendment 0003 for stamped MDE permit drawings. Replace existing sheets with MDE approved set. There are no changes beyond MDE approval stamps.

20 01 57 19 1.8 Has the Army Corp of Engineers Permit been obtained for this project?

Yes

21 01 14 00.00

Will there be any in-water work restriction windows on this project that would limit the pile driving or demo activities?

No, Bid per RFP. However, To the degree we can minimize work with high impact on migratory waterfowl nesting season (15 NOV-01MAR) it is desirable, but not required.

22 D5/S-

Drawings The referenced detail shows a 5/16 fillet weld "all-around" for the attachment of the L7x4x3/4 to the monopile. Welding this clip angle along the heel of the angle is not possible as the rubber fender will obstruct the joint. Please confirm that these angle are to be welded on 3-sides only.

See Amendment 0003 for additional information on this detail.

23 A5/S-

D5/S-

Drawings The referenced details show a gusset plate inside the L7x4x3/4 clip. D5/S-519 references C5/S- 519, which does not exist; we assume the intended detail is A5/S-519. This detail does not show location or thickness of gusset. Note, if gusset is located in middle of angle it will clash with the fender rod and nut.

Other details on S-518 that show this angle clip do not show a gusset at all. Question: is the gusset required and if so, what is its thickness and how is it positioned to not interfere with the fender rod and nut?

Yes, Bid per RFP, and reference detail as shown in A5/S-519.

24 E-001 Drawings Please specify the type of conduit to be installed within the utility YP Pier Trench--PVC, Fiberglass, RGS or PVC-coated

RGS.

Bid per RFP. Fiberglass conduit shall be used for conduits in the utility trench, parapet, and underneath the utility platform per details C1 on sheet E-506, C1 and A1 on sheet E-507, C1 on sheet E- 508, A1 on sheet E-510, and B1 on sheet E-512.

25 2 and 3 03 62 16 The specification states to install the pile jackets with a clear distance from piles as indicated.

There is no detail provided in the drawings with this dimension.

Please provide a pile jacket detail and/or the required clear distance from the pile.

See Amenment 0003 for additional information in section 03 62 16.

26 E-101 to E-104

Drawings The drawings indicate a 2" communication conduit to each power pedestal. Please provide information on what is required for communication cables within these conduits.

Communications conduits are shown with no communications cables installed. Per specification section 26 27 29 3.1.4.4, empty conduits shall have pull wire installed within.

27 Drawing S-001

03 31 29 & 03 30 00

In reference to plan sheet S-001

– Structural Notes Sheet 1 of 2, under the “CONCRETE” heading, Note 1 states;

“PROVIDE MARINE

CONCRETE AND MARINE

CONCRETE FILL WITH A

MINIMUM COMPRESSSIVE

SRENGTH OF 5000 PSI AT 28

DAYS”. This note, along with the lack of other notes referencing any different type of concrete, leads us to believe that all transit-mixed concrete on the project is required to be

“MARINE CONCRETE”,

however, in addition to Specification Section 03 31 29 –

MARINE CONCRETE WITH

SERVICE LIFE MODELING,

there is also a Specification Section 03 30 00 – CAST IN PLACE CONCRETE, which is conventional “NON-MARINE CONCRETE”. Please clarify:

Are there any elements on the project to be constructed with transit mixed “NON-MARINE CONCRETE”? If so, please identify these elements.

Per Line 03 31 29 Paragraph 1.2 definition "q." indicates the applicability of "Marine Concrete" is to be used in all locations where contact with seawater is possible, including buried elements.

As such, applications for the project are based upon utlizing Marine Concrete where reinforcement is present.

Elements that may be constructed with "NON-

MARINE CONCRETE":

Monopile concrete fill

28 Drawing S-001

03 31 29 & 03 30 00

Are the Temporary Pier utility pedestals to be cast with “MARINE CONCRETE” or

“NON-MARINE CONCRETE”?

Non-Marine Concrete. See Amendment 0003.

29 Drawing S-001

03 31 29 & 03 30 00 &

03 45 33

Are the Specification Section 03

45 33 - PRECAST

PRESTRESSED

STRUCTURAL CONCRETE –

(Wave Screen Panels) to be cast with “MARINE CONCRETE” or “NON-MARINE

CONCRETE”?

Marine Concrete. See Drawing S-001, Concrete, Note 1

30 Drawing S-001

03 31 29 & 03 30 00 & 31 62 13.20

Are the Specification Section 31 62 13.20 -

PRECAST/PRESTRESSED

CONCRETE PILES to be cast with “MARINE CONCRETE” or “NON-MARINE

CONCRETE”?

Marine Concrete. See Drawing S-001, Concrete, Note 1

31 Drawing S-001

03 31 29 & 03 30 00 & 31 62 23.13

Are the Specification Section 31

62 23.13 CONCRETE-FILLED

STEEL PILES to be filled with “MARINE CONCRETE” or

“NON-MARINE CONCRETE”?

Marine Concrete. See Drawing S-001, Concrete, Note 1

32 Attachment G

Could a word document of Attachment G - SB Subcontracting Plan be provided to make it easier to fill out the required information? Also, Pages 9 and 10 the columns on the right were cut off in the PDF.

Yes, See Amendment 0002.

33 12 4.1 Can you please provide a copy of the sign in sheet for the pre-proposal meeting?

Yes, See Amendment 0002.

34 5 01 45 00.00 1.5.6.1 Is the structural QC specialist required to have post installed anchor certification and/or training?

Yes, Bid per RFP.

35 5 01 45 00.00 1.5.6.1 Is the structural QC specialist required to have weld inspection certification and/or training?

Yes, Bid per RFP.

36 5 01 45 00.00 1.5.6.1 Is the intent for weld inspection to be visual only or is testing required? If so, what testing is anticipated?

Both. Visual inspection of all welds. Nondestructive testing inspection type and frequency table is provided in Paragraph 3.7.1.2 of Section 05 12 00.

37 I’m writing on behalf of Michels Marine, a division of Michels Construction, Inc. to request a bid extension for the Annapolis, MD Replace Failing YP Pier and Wave Screen project. Our team needs additional time to complete the necessary research

No, Bid per RFP.

For the PIEE link, see Amendment 0002.

and finalize the bid. The bid is currently due May 2, 2023 and we would like an extension to May 19, 2023 if possible.

I did log in to PIEE but struggled to find a location in which to submit this request online. If needed, any guidance on that topic would also be appreciated.

38 1 13 RFP Date Time Extension - Two Weeks.

Bid per RFP.

39 Are there any Time of Year Restrictions for this project?

See Amendment 0003 for addtional information in section 01 14 00.

40 Are all the permits acquired already? Where can we see them?

Yes, See Amendment 0002.

41 51 RFP Can you provide a Diver Prevailing wage rate?

Adding additional classifications not listed in applicable prevailing Wage Determinations are rquested through the Department of Labor.

42 S-502 Drawings What is the diameter of the Pile Jacket located on the Wave Screen Piling?

See Amendment 0003 for addtional information for sheet S-502.

43 S-502 Drawings What type of grout do you require to be placed in this jacket?

Bid Per RFP Section 03 62 16, paragraph 2.1.2, "provide non-shrink cementitious grout."

44 S-502 Drawings Can you provide a detail of the pile jackets being placed on the 30” Notched Wave Screen Pile?

See Section 03 62 16 paragraph 2.1.1 including additoinal detail in Amendment 0003.

45 Is there any vibration monitoring required on this project?

Bid per RFP. Section 31 41 16, Part 3.7 and 31 62 13.20, Part 3.4 incorporates vibration controls. While vibration control was not incorporated in to 31 62

23.13 for the anchor piles near Building 66NS, their installation will be in support of the sheet piles for the stabilization of the Reach B corner and as such, the vibration control plan for that work under 31 41 16 shall be in place prior to installation of the two anchor piles such that the installation of these piles is included within the monitoring and control effort associated with the sheet piles they will support.

46 S-001, S-600-

Drawings Note #4, in the Pipe pile Section on sheet S-001 of the drawings states “Drive Piles to the minimum depths as indicated in the pile schedule on S-600 to S- 603”. Sheets S-600 through S- 603 have a column titled Estimated tip elevation, but no minimum tip elevation. Please verify that the Estimated tip elevation on these sheets are considered the minimum tip elevation for the pipe pile.

Confirmed.

47 1 Attch H CLIN

CLIN 0001 Base Bid. Is it the owner’s intention to include all the items that are not Piling, and group them in one lump sum item? (i.e. Cast-in-Place concrete, Reinforcing steel, Precast Concrete, Electrical, Utility, Fenders and anchorages, Miscellaneous Fabricated steel like handrails, steps, walkways).

Yes, Bid per RFP, Revised Price Proposal Form.

48 1 Attch H CLIN

CLIN 0002 Temporary Mooring Piers. Please verify that this refers to everything pertaining the the Temporary Swing piers as stated on the drawings?

Confirmed with the exception of the timber pile driving that is listed in CLIN 0003 as an estimated quantity item.

49 2 Attch H CLIN

Is CLIN0003 supposed to be the subtotal of all the Pile Items labeled 0003AA-0003AG?

Yes, Bid per RFP.

50 2 Attch H CLIN

The price proposal form seems to have a higher linear footage than the pile schedule on the drawings, the 24” Concrete pile being as high as 10,000 linear feet. Which numbers would the owner like the contractors to price? If it is what is on the price proposal form, can we see where these numbers came from?

Bid per RFP, See revised Price Proposal form in Amendment 0003.

52 E-516 Will the Concrete Pedestals installed for the Shore Power Pedestals be removed after the Power Pedestals are put in storage?

No, Bid per RFP.

53 S-001, S-600 - S-603

Drawings Note 4 under Prestressed Concrete Piles on S001 says to drive piles to minimum embedment depths as indicated in the pile schedule on S-600 to S-603. The pile schedule only

Estimated tip elevation shall be considered miminum tip elevation.

provides the estimated pile tip elevations. Please provide the minimum tip elevations.

54 8 31 62 19.13 3.1.2.1 The Timber Marine Piles specification states to provide 5 test piles and perform static loading and measuring; however, the drawings and pile schedule do not indicate any test pile for the timber pile. Please confirm no testing of the timber piles are required.

Confirmed.

55 5 31 62 23.13 3.1.1.c. The specification states to perform a refined Wave Equation Analysis upon completion of the dynamic and static testing programs outlined in this specification section;

however, no testing program is included. Please provide the testing program for the concrete-filled steel piles.

See Amendment 0003 for addtional information updating this paragraph.

56 31 62 23.13 The Precast/Prestressed Concrete Piles and Timber Marine Piles specifications state to provide test pile 5 feet longer in length than the bid length; however, the Concrete-Filled Steel Pile section does not have that language.

Please clarify if the concrete-filled steel test pile shall be ordered 5 feet longer than the bid lengths on the pile schedule.

Concrete filled steel pile Test monopiles shall be ordered 5 feet longer than bid length on the pile schedule similar to concrete piles. No testing of timber piles is required, order as necessary.

57 Will piping located inside the fiberglass Hot Box require insulation?

No, Bid per RFP.

58 21 12 00 3.4 Please define the limits of coatings required on the Dry Fire Suppression water piping. Will all Dry Fire Water Suppression piping require Field Painting as stated in section 21 12 00 3.4 Feld Painting?

Only the valves and risers exposed/accessible above the deck surface will require painting in accordance with NFPA standards for identification and system differentiation.

59 S-303 Please provide a typical pavement section for the areas adjacent to the proposed Power pedestal Foundations and Electrical Conduit Support Posts with Concrete Foundations. The plans indicate that there is 3 inches of existing Asphalt Pavement in these areas. Is pavement patching anticipated in these areas?

No, Bid per RFP.

60 33 61 14 Does Section 33 61 14 Exterior Buried Preinsulated Water Piping apply to the proposed 2-inch galvanized underground water piping?

No, insulation is only required for sections of water pipe that are exposed and it does not apply for pipe buried in soil.

61 4 thru 5 01 45 00.00

1.5.6 The third party Underwater QC

Team, Structural QC Team and Geotechnical QC Team specs all state that the frequency of inspection and surveillance will be weekly, after each milestone and final inspection. Do these third party inspectors need to be onsite continuously while the work they are responsible for is taking place or can they be onsite once a week to inspect previously installed work?

No, Bid per RFP.

62 7 31 62 13.20 1.8.4 Specification section states, "Registered Professional Geotechnical Engineer......is to observe test pile installation and production pile installation as specified herein." Spec Section 01 45 00.00 23 for the Geotechnical QC Team references weekly inspection and surveillance. If these spec sections are referring to the same position please clarify if continuous observation is required during driving or just a weekly inspection of previously driven piles is required.

The functions described in each section are not prohibitied from being performed by the same consultant if qualified to meet qualification requirements of each specification section. Based upon the requirements of 31 62 13.20 relating to test pile monitoring and instrumentation, the "Contractor's Geotechnical Consultant" is required to be onsite continuously performing the required duties during test pile installation and subsequent testing. The Geotechnical Specialist described in 01 45 00.00 23 is required to meet the frequency listed in

1.5.6.2 of weekly, after each major milestone (listed in 1.5.6.2), and a final inspection.

63 26 42 13 1.6.3 Article 1.6.3 “Services of the Corrosion Expert” Indicates three trips are required and describes soil resistivity testing and pipeline coatings. The drawings indicate water-side galvanic CP, but this is not mentioned in the specification. Does the Corrosion Expert need to be present for water side CP

No, the second paragraph states the "Corrosion Expert" will be available (but not necessarily be on site the entire time) during the installation of the CP system... Exactly how this is achieved is to be determined by the contractor QC operations.

installation QC? Also, please indicate where the pipeline CP is required.

There is no pipeline related CP for this project

64 26 42 13 1.5.1, 1.5.2

Article 1.5.1 “Spare Parts” and

1.5.2 “Extra Materials” indicate spare parts, test stations, and extra anodes are to be provided. Is this necessary? To whom do we deliver this material to?

Yes, Bid per RFP. Submit to the Contracting Officer's Representative in accordance with 01 33 00.

Have on site and available for conducting training in accordance with 01 78 23.

65 26 42 13 1.9 Article 1.9 “Warranty” Please indicate what warranty items are expected. Galvanic cathodic protection systems indicated in the drawing notes are permanently attached and have no equipment or moving parts. These systems are just replaced when consumed. How long is the galvanic anode systems expected to last? What is the expected galvanic anode design life?

Refer to requirements for Mainteance Materials listed in paragraph 1.5. The system design service life of 25 years is listed in paragraph 3.3.1.

66 26 42 13 2.1.1 Article 2.1.1 “Corrosion Control System Description” Are other corrosion protection systems operating in the area, (for example gas or water piping)? Will the proposed galvanic water-side corrosion protection system described in the drawing notes be the only cathodic protection system operating in the area?

No other systems are operating in the area. Yes.

67 26 42 13 2.1.2 Article 2.1.2 “Design Requirements” Does a “Corrosion Specialist” need to develop design calculations and drawings, or just test and approve the system described in the drawing notes?

The "Corrosion Specialist" will need to develop design calculations and drawings for a system that will meet design life and protection requirements using the components and materials selected by the contractor and approved via the submittal process. The drawings define the minimum system requirements generically.

The contractor shop drawing design shall account for manufacturer specific requirements, connection details, and vendor specific details.

68 26 42 13 2.1.2 Article 2.1.2. What piping is required to receive cathodic protection?

No piping is required to recieve cathodic protection.

69 26 42 13 2.1.2.1 Article 2.1.2.1 “Anode and Bond Wires” Indicates 170 lb aluminum anodes for each monopile and 14 ea. 240 lb aluminum anodes along the sheet pile wall. Article 2.2.1.1.2 indicates 170 lb anodes for the sheet pile wall. Drawing Notes on S-001 indicate 170 lb anodes.

What size anode and what quantity is required for the sheet pile wall?

See Amendment 0003 for corrections to section 26 42 13 paragraph 2.1.2.1.

70 26 42 13 2.2.2.1, 2.2.2.2, 2.2.2.3

Articles 2.2.2.1, 2.2.2.2, and

2.2.2.3 “Wiring” We normally weld this type galvanic anode system directly to the piling. Are these requirements only related to the single test station specified, or do you expect all anodes to be wired? Does this requirement only apply to soil anodes for piping, if applicable?

The connection system is dependent on the manufacturere and selected products. Wiring requirements are defined and are applicable if the selected manufacturer system requires it. There are no anodes required for utility piping.

71 26 42 13 2.2.2.5 Article 2.2.2.5 “Resistance Bond Wires” Is welding sheet pile interlocks or welding the wale to the sheet pile within the concrete cap sufficient in lieu of thermite welding copper wires across interlocks?

Yes, this should be submitted as a variation in accordance with 01 33 00 for consideration if that is the method used to achieve this aspect of peformance requirement.

72 26 42 13 2.2.4 Article 2.2.4 “Permanent Reference Electrodes” This article calls out copper sulfate permanent reference electrodes. Copper sulfate reference electrodes are not stable in salt water. May silver chloride permanent reference electrodes be substituted instead?

This may be acceptable dependent on contractor system design. Submit as part of the shop drawing design, or independently as appropriate and comply with the vairation requirements of 01 33 00 for consideration.

73 S-303 Please provide a typical pavement section for the areas adjacent to the proposed Power pedestal Foundations and Electrical Conduit Support Posts with Concrete Foundations. The plans indicate that there is 3 inches of existing Asphalt Pavement in these areas. Is pavement patching anticipated in these areas?

No pavement patching is anticipated in this area.

74 33 61 14 Does Section 33 61 14 Exterior Buried Preinsulated Water Piping apply to the proposed 2-

No.

inch galvanized underground water piping?

75 7 31 62 13.20 1.8.4 Specification section states, "Registered Professional Geotechnical Engineer......is to observe test pile installation and production pile installation as specified herein." Spec Section 01 45 00.00 23 for the Geotechnical QC Team references weekly inspection and surveillance. If these spec sections are referring to the same position please clarify if continuous observation is required during driving or just a weekly inspection of previously driven piles is required.

Geotechnical Engineer is required to be on site during test pile installation.

Production pile QC is defined in section 01 45 00 within the Geotechnical team. Provided this individual meets the qualifications as defined in both sections they could be the same individual. This would be subject to submittal approval as defined in the contract.

76 26 42 13 2.4.1 Article 2.4.1 “Non-Destructive Testing of Anodes” describes a test procedure to establish the anode potential in fresh water. Aluminum anodes are specified, but aluminum will passivate in fresh water. This test is not appropriate for aluminum. Failure of this test is expected for any aluminum anode. Aluminum needs salt water to remain active. The aluminum potential will vary depending on the salinity of the water. Can we modify the procedure to verify the native anode potential in the brackish Severn river water?

This is dependent on contractor material and system design choices.

Submit proposed plan in accordance with shop drawings and calculations required in the specification. Note, the actual site conditions have highly variable salinity which must be accounted for in the contractor system design, testing, and placment into operation.

77 26 42 13 2.4.2 Article 2.4.2 “Destructive Testing of Anodes” It is standard practice for marine anodes to be directly welded to the piling and not be wired. This specified test appears to be unnecessary. Can this requirement be waived/removed?

This is dependent on contractor material and system design choices.

Submit proposed plan in accordance with shop drawings and calculations required in the specification. Identify variations from specification as required in section 01 33 00.

78 33 Please provide additional information regarding the Stainless Steel Water Piping type and grade required for the new water line.

Pipe shall be Type 316 Stainless Steel.

79 Price Proposal

Form

Will the demolition of the dolphins, curbing, and fencing in the vicinity of the proposed

Yes, Bid per RFP.

Temporary Mooring Piers be paid under CLIN 002?

80 Solicitation We respectfully request a one week bid extension from May 2nd to May 9th. Additional time is required due to the amount of temporary engineering required to fully evaluate the driving requirements for the multiple concrete and steel pile sizes.

Once the pile hammers are sized then temporary designs can completed on the pile templates.

We also are still waiting on lead times on long lead electrical components required for the temporary swing piers which will dictate our critical path schedule and be addressed in the narrative.

See Amendment 0003.

81 Factor 1 Experience

If a minimum of two (2) past construction projects meet the Size and Scope requirements can additional projects (under $45,000,000) be submitted in order to demonstrate experience for each of the Complexity requirements?

No, Bid per RFP.

82 7, 8, & 9 Spec 05 50

2.9 The specification 05 50 13 part

2.9 Deployable Self-Adjusting

Stairs appears to have information pertaining to the passive flood barrier within this section (2.9.3.1 through 2.9.5) please clarify

See Amendment 0003 for corrections.

83 G-300, G-301, G-302

Drawings & Spec 05 50

2.9.2 The design requirements, as they

relate to the platform beneath the deployable self-adjusting stairs, Spec 05 50 13 part 2.9.2 provide a height of 13.5 and are to be galvanized steel. Are there any other design criteria that should be considered for this platform?

Bid per RFP.

84 S-107 & S-108

Drawings & Spec 05 50

3.1 Are the 42" x 6" bollards at both

the utility platform and by the utility pedestals to be mounted to the top of the concrete pier and secured with 4 concrete anchors as stated in Spec 05 50 13 Part

3.10. Or can these be embedded

into the pier concrete and anchored with additional concrete to meet the 10,000 lb / 5 mph design criteria?

Bid per the RFP. A variation could be proposed in accordance with the contract, but bidders are advised there is a maintenance need to be able to remove and reinstall the bollards without damage which will affect consideration of such an idea.

85 D3/S-

C1/S- 503 and Note 1

Spec 09 97 13.26

3.2 On the referenced documents, spec indicates wave screen wales and pile-to-pier connections (shackles, U-bolts, and padeyes) to be coated in accordance with SZC specification. Note 1 on S- 503 indicates wales are to be galvanized. Please confirm (or clarify) that shackles, U-bolts, wave screen wales, and padeyes attached to concrete pier or concrete pile are to be galvanized.

See Amendment 0003.

86 Spec 05 12

1.5.3 The referenced specification

indicates structural steel connection design is the responsibility of contractor. The structural framing connections on this Project appear to all have been designed by the EOR.

Please clarify what is expected to be the contractors’ responsibility with regard to structural connection design.

See Amendment 0003 for corrections.

87 Spec 05 52

2.2.6 The referenced specification

indicates handrail design is the responsibility of contractor. The handrail member sizes and connections on this Project appear to have all been designed by the EOR. Please clarify what is expected to be the contractors’ responsibility with regard to handrail design.

Contractor is responsible for any additional details beyond those already provided as may be required in their shop drawings.

88 Spec 09 97 13.27

What are the coating requirements for bollards, cleats, and other non-galvanized steel at or above elev. 10.5' (main pier deck)? Are these components to be coated in accordance with 09 97 13.27?

All steel elements above water exposure and not called out for galvanized coating shall be considered coated according to 09 97 13.27.

89 S-303, E106 thru

E108,E-

Drawings On drawings S-303, the power pedestal shown near the existing chain link fence appears to be mounted on a single concrete pier at 5 locations shown on E- 106 thru E-108. On drawing E- 516 the foundation for these pedestals appears to be a 3 sides concrete stair with pipe handrail along the top edge. Please confirm that the details shown on E-516 is what is required at all 5 locations.

Confirmed.

90 E-513 Drawings Please clarify to whom takes ownership of the electrical equipment to be removed from existing pier.

Comply with Section 02 41 00 3.3.1. Any salvage items will be removed by the Government prior to the contractor mobilizing.

91 Spec 05 05

The majority of the concrete anchors and anchor bolts shown throughout the drawings are not entirely clear with regard to their embedment lengths. In addition it is not clear which anchors are post installed vs embedded into the concrete. Could you please provide additional details?

See Amendment 0003 for additional details.

92 9 of 18 Amendment

1/RFP

Factor 1 "Submit a minimum of two (2) up to a maximum of five (5) construction projects performed by the Offeror as the prime contractor that best demonstrates the Offeror’s relevant experience (projects similar in size, scope, and complexity to this project).

Projects submitted for the offeror shall have been completed within the past ten (10) years from the date of issuance of this RFP or be at least 75% complete by the date of issuance of the RFP.

Size: $45,000,000 or greater & 500 LF of pier/wharf construction.” Can the project experience be extended to 15 years and the size of the past project be lowered to $30,000,000? Pier/wharf projects of this magnitude are not regularly available, and due to inflation in the past several years, a $45 million project today could have been between $30M and $35M 10 to 15 years ago.

No, bid per RFP.

93 Due to the complexity of this project, the coordination with small businesses, possible amendments to answer questions, and the overall effort required to prepare the best value offer to NAVFAC, we respectfully request a 3-week extension on the Bid Proposal Date.

See Amendment 0003.

As-Built request for existing Utilities (CU100)

See Amendment 0003.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 02-May-2023 02:00 PM to 09-May-2023 02:00 PM.

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

The following have been modified:

WAGE DETERMINATION

"General Decision Number: MD20230012 04/07/2023

Superseded General Decision Number: MD20220012

State: Maryland

Construction Type: Heavy

County: Anne Arundel County in Maryland.

HEAVY CONSTRUCTION PROJECTS (including sewer/water construction).

Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.

Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60).

|If the contract is entered |. Executive Order 14026 |into on or after January 30, | generally applies to the |2022, or the contract is | contract.

|renewed or extended (e.g., an |. The contractor must pay

|option is exercised) on or | all covered workers at |after January 30, 2022: | least $16.20 per hour (or | | the applicable wage rate | | listed on this wage | | determination, if it is | | higher) for all hours | | spent performing on the | | contract in 2023.

|If the contract was awarded on|. Executive Order 13658 |or between January 1, 2015 and| generally applies to the |January 29, 2022, and the | contract.

|contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least |30, 2022: | $12.15 per hour (or the | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | hours spent performing on | | that contract in 2023.

The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.

Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/06/2023 1 02/03/2023 2 04/07/2023

CARP0197-007 05/01/2022

Rates Fringes

CARPENTER (Form Work ONLY).......$ 31.40 13.86

CARP0219-001 05/01/2022

Rates Fringes

MILLWRIGHT.......................$ 36.00 14.07

CARP0474-002 05/01/2022

Rates Fringes

PILEDRIVERMAN....................$ 34.62 16.36

* ELEC0024-002 12/04/2022

Rates Fringes

ELECTRICIAN......................$ 43.50 5.25%+17.19

ENGI0037-019 04/01/2022

Rates Fringes

OPERATOR: Bobcat/Skid Steer/Skid Loader................$ 27.99 12.60+a OPERATOR: Bulldozer.............$ 30.95 12.60+a OPERATOR: Drill.................$ 30.95 12.60+a OPERATOR: Gradall...............$ 31.95 12.60+a OPERATOR: Grader/Blade..........$ 31.95 12.60+a OPERATOR: Mechanic..............$ 30.95 12.60+a OPERATOR: Paver (Asphalt, Aggregate, and Concrete).........$ 30.95 12.60+a OPERATOR: Piledriver............$ 31.95 12.60+a OPERATOR: Roller................$ 30.05 12.60+a

a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.

IRON0005-018 06/01/2021

Rates Fringes

IRONWORKER, REINFORCING AND

STRUCTURAL.......................$ 31.17 24.16

LABO0710-002 04/01/2022

Rates Fringes

LABORER: Landscape..............$ 19.90 6.06 LABORER: Mason Tender - Cement/Concrete..................$ 21.06 6.06

PAIN0051-021 06/01/2022

Rates Fringes

PAINTER (Steel)..................$ 41.68 13.97 PAINTER: Brush, Roller, and Spray............................$ 26.61 11.41

PLAS0891-006 02/01/2020

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 28.82 11.68

PLUM0486-015 12/16/2022

Rates Fringes

PLUMBER/PIPEFITTER...............$ 44.66 23.38

TEAM0570-002 06/01/2020

Rates Fringes

TRUCK DRIVER: Lowboy Truck......$ 30.98 8.15+a+b+c

a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.

b. VACATION: Employees with 1 year of service - 2 week paid vacation

c. HEALTH AND WELFARE: $981 per month

* SUMD2010-065 07/08/2010

Rates Fringes

BRICKLAYER.......................$ 18.70 0.00

CARPENTER, Excludes Form Work....$ 15.91 ** 6.90

LABORER: Common or General......$ 12.28 ** 2.63

LABORER: Flagger................$ 15.71 ** 8.58

LABORER: Grade Checker..........$ 14.62 ** 3.08

LABORER: Mason Tender - Brick...$ 15.93 ** 7.83

LABORER: Pipelayer..............$ 13.49 ** 2.04

OPERATOR: Backhoe...............$ 16.73 4.97

OPERATOR: Crane.................$ 22.00 8.85

OPERATOR: Excavator.............$ 18.93 4.92

OPERATOR: Loader................$ 18.00 3.73

OPERATOR: Trackhoe..............$ 20.47 10.20

TRUCK DRIVER: Dump Truck........$ 11.84 ** 0.00

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($16.20) or 13658 ($12.15). Please see the Note at the top of the wage determination for more information.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the

EO

is available at https://www.dol.gov/agencies/whd/government-contracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification…

This is the start of the file's text. The full file is on GovTribe.