2 Coefficient Contractor Estimate Worksheet.xlsx
XLSX spreadsheet 14 KB Posted
- Solicitation number
- N4008022R9543
About this file
This document contains a federal contract opportunity and related cost estimation worksheet. The federal contract opportunity is a solicitation for a general construction Indefinite Delivery Indefinite Quantity Contract for job order contracts valued between $2,000 and $1,000,000. The work locations are the Chesapeake Bay Detachment of the Naval Research Laboratory in Washington, DC, and the Naval Warfare Center Carderock in Maryland. The contract type is a single award IDIQ with a one year base period and four one-year options and a maximum value of $50 million. The source selection process is lowest price technically acceptable. This is a 100% set-aside for 8(a) small businesses under NAICS code 236220 with a size standard of $39.5 million. The cost estimation worksheet provides pre-priced and non-pre-priced coefficient factors and costs for estimating construction projects under the potential contract.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N4008022R9543 Amd 0006 - Corr Email and Ext 27JUN22.pdf | ||
| N4008022R9543-0005.pdf | ||
| N004022R9543--0004.pdf | ||
| N4008022R9543-0003.pdf | ||
| N004022R9543--0002.pdf | ||
| N004022R9543-0001.pdf | ||
| ATTACHMENT 4-Teaming Consent F.docx | DOCX document | |
| ATTACHMENT 5-RFI Form F.docx | DOCX document | |
| ATTACHMENT 1 - Project Data Sheet F.docx | DOCX document | |
| ATTACHMENT 2 - Safety Data Sheet F.docx | DOCX document | |
| ATTACHMENT 3-Past Performance Questionnaire F.docx | DOCX document | |
| Coefficient Breakdown Form with profit language.pdf | ||
| N4008022R9543 NRDE Gen Construction RFP NRL-CARD 17May22.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRE-PRICED COEFFICIENT
| PRE-PRICED COSTS | MATERIALS | LABOR | EQUIPMENT | AMOUNT |
| PRE-PRICED COEFFICIENT | ||||
| RS MEANS BARE COST (PRESUMED ANNUAL AMOUNT) | $6,300,000.00 | $3,500,000.00 | $200,000.00 | $10,000,000.00 |
| WORKER'S COMP INSURANCE | $0.00 | |
| AVERAGE FIXED LABOR OVERHEAD | $0.00 | |
| PROJECT OVERHEAD PRE-PRICED | $0.00 | |
| MATERIAL MARKUP | $0.00 | |
| EQUIPMENT MARKUP | $0.00 | |
| SUBTOTAL | $0.00 | |
| GENERAL AND ADMINISTRATIVE | $0.00 | |
| PROFIT | $0.00 | |
| TOTAL | $0.00 | |
| COEFFICIENT FACTOR (TOTAL DIVIDED BY PRESUMED ANNUAL AMOUNT) | 0 | |
| RS MEANS BARE COST ADJUSTMENT (PRODUCTION/DISCOUNT - FACTOR) | 0.9 | |
| PRE-PRICED COEFFICIENT | 0.9 |
NON PRE-PRICED COEFFICIENT
| PRE-PRICED COSTS | MATERIALS | LABOR | EQUIPMENT | AMOUNT |
| NON PRE-PRICED COEFFICIENT | ||||
| NON PRE-PRICED BARE COSTS (PRESUMED ANNUAL AMOUNT) | $630,000.00 | $350,000.00 | $20,000.00 | $1,000,000.00 |
| WORKER'S COMP INSURANCE | $0.00 | |
| AVERAGE FIXED LABOR OVERHEAD | $0.00 | |
| PROJECT OVERHEAD NON PRE-PRICED | $0.00 | |
| MATERIAL MARKUP | $0.00 | |
| EQUIPMENT MARKUP | $0.00 | |
| SUBTOTAL | $0.00 | |
| GENERAL AND ADMINISTRATIVE | $0.00 | |
| PROFIT | $0.00 | |
| TOTAL | $0.00 | |
| COEFFICIENT FACTOR (TOTAL DIVIDED BY BARE COST) | 0.000 | |
| NON-PRE-PRICED BARE COST ADJUSTMENT (PRODUCTION/DISCOUNT - FACTOR) | 1 | |
| NON PRE-PRICED COEFFICIENT | 1 |
File details come from the government source that posted it. Updated .