Potable Water Manpower Estimated Work Zones 2021-08-02 - Copy.pdf
PDF 110 KB Posted
- Solicitation number
- N4008021R1827
About this file
This document outlines a federal contract opportunity for replacement of potable water lines and fire suppression systems at Naval Support Facility Indian Head in Indian Head, Maryland. The project involves replacing approximately 140,000 linear feet of aging potable water and fire suppression lines across the site. Special construction features are required due to the sensitive site involving unexploded ordinance surveying and safety work permitting. The Government has provided a portion of the 95% design package for industry feedback prior to finalizing the project design. Interested offerors should review solicitation number N4008021R1827 for additional details on this opportunity being procured by the Department of the Navy Naval Facilities Engineering Command.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
100 LF/day (See Assumption Note 1) Total Quantities LF Miles Weather Days - https://dgs.maryland.gov/Documents/ofp/GeneralConditionsforConstruction2018.pdf (Page 30) 125 LF/day North (P233) 31,815 6.0
24 Months Central (P232) 34,845 6.6 730 Calendar Days South (P234) 46,460 8.8 521 Working Days Energetics 36,461 6.9 60 Mob./Notification Time/Submittal Review/Material Procurement 149,581 28 73 per year 30 Final Restoration
146 Weather Days (73/yr) 285 Installation Time (No Float Time)
Project Area North (P233 & Energetics)
Work Zone Project Area Phase
Approx. Length of Potable Water main
(LF)
Approx. Length of Energetics Water main
(LF)
Approx. Length of Potable Service lines
(LF)
Approx. Length of Energetics Service lines
(LF)
Complexity Work Zone
Main Line Production Rate (LF/Day)
Work Zone Service Line
Production Rate (LF/Day)
Flush, Disinfect & Test (Days)
Construct Main(s) (Days)
Construct Service(s)
(Days)
Single Crew Anticipated
Calendar days to complete Number of crews
Construction Duration W/ Multi Crews
(Days) W1 1 15,958 404 8,989 0 1.1 90.9 113.6 5 180 79 264 3 106 W2 1 707 0 1,010 0 1 100.0 125.0 5 7 8 20 1 24 W3 3 3,030 707 1,313 0 1.25 80.0 100.0 5 47 13 65 2 39 W4 2 0 0 808 0 1.5 66.7 83.3 5 0 10 15 1 18
Total 19,695 1,111 12,120 0 20 234 110 364 187
Project Area Central (P232 & Energetics)
Work Zone Project Area Phase
Approx. Length of Potable Water main
(LF)
Approx. Length of Energetics Water main
(LF)
Approx. Length of Potable Service lines
(LF)
Approx. Length of Energetics Service lines
(LF)
Complexity Work Zone
Main Line Production Rate (LF/Day)
Work Zone Service Line
Production Rate (LF/Day)
Flush, Disinfect & Test (Days)
Construct Main(s) (Days)
Construct Service(s)
(Days)
Single Crew Anticipated
Calendar days to complete Number of crews
Construction Duration W/ Multi Crews
(Days) W5 1 3,939 505 0 0 1 100.0 125.0 5 44 0 49 3 20 W6 2 5,353 4,545 2,626 1,212 1.25 80.0 100.0 5 124 38 167 3 67 W7 2 3,333 0 1,111 0 1.1 90.9 113.6 5 37 10 52 2 31 W8 1 3,636 303 1,010 0 1.1 90.9 113.6 5 43 9 57 3 23 W9 2 7,373 6,464 2,222 2,828 1.5 66.7 83.3 5 208 61 274 3 110
W10 2 1,818 0 202 0 1.1 90.9 113.6 5 20 2 27 2 16 W11 2 1,616 505 606 404 1.1 90.9 113.6 5 23 9 37 2 22 Total 27,068 12,322 7,777 4,444 35 499 129 663 289
Project Area South (P234 & Energetics)
Work Zone Project Area Phase
Approx. Length of Potable Water main
(LF)
Approx. Length of Energetics Water main
(LF)
Approx. Length of Potable Service lines
(LF)
Approx. Length of Energetics Service lines
(LF)
Complexity Work Zone
Main Line Production Rate (LF/Day)
Work Zone Service Line
Production Rate (LF/Day)
Flush, Disinfect & Test (Days)
Construct Main(s) (Days)
Construct Service(s)
(Days)
Single Crew Anticipated
Calendar days to complete Number of crews
Construction Duration W/ Multi Crews
(Days) W12 1 11,009 3,535 1,919 909 1 100.0 125.0 5 145 23 173 3 69 W13 2 4,747 4,848 4,747 3,535 1.3 76.9 96.2 5 125 86 216 3 86 W14 3 3,434 2,424 2,525 1,212 1.5 66.7 83.3 5 88 45 138 3 55 W15 2 0 0 1,111 808 1.1 90.9 113.6 5 0 17 22 2 13 W16 1 2,323 1,111 505 202 1 100.0 125.0 5 34 6 45 2 27 W17 2 2,525 0 707 0 1.1 90.9 113.6 5 28 6 39 2 23 W18 2 1,313 0 1,212 0 1.1 90.9 113.6 5 14 11 30 2 18 W19 2 1,717 0 1,212 0 1.1 90.9 113.6 5 19 11 35 2 21 W20 2 909 0 1,919 0 1.2 83.3 104.2 5 11 18 34 2 20 W21 2 1,212 0 1,414 0 1.2 83.3 104.2 5 15 14 34 2 20 Total 29,189 11,918 17,271 6,666 50 479 237 766 352
Assumes a maximum of 3 crews per work zone
For multiple crews, assumes a 20% diminishing rate of productivity
Assumptions:
1. The main construction rate per day considers time for initial utility locates, potholing efforts, potential alignment shifts due to unknown utilities, pavement repair, other non-pipeline related work that is necessary, and mobilization between work zones.
2. No delays in permitting review/approval or access with the Base.
3. No new archeological sites will be encountered during construction.
4. No UXO delays will occur.
5. No failed pressure or Bac-t tests.
6. The contractor and field personnel can work through any alignment and/or profile modifications to keep the production rate utilized for each zone.
7. Work is only allowed Monday - Friday. Saturday work would provide an opportunity to make up lost time or reduce construction duration; however, productivity for working six days a week is likely to be reduced and the full number of crews may not be available for Saturday work.
8. All facilities needing water service have been properly identified. If a facility is identified to need water service during the abandonment period additional time will be required.
9. Limited number of temporary connections will be necessary.
10. Materials will be readily available and delivered on time. There are some larger gate valves on Energetics that could be troublesome with work zone W12 being in Phase 1 in the south project. Larger gate valves can have lead times of 12+ weeks.
11. Abandonment activities for existing mains can occur during the time when service lines are being transferred/installed.
Main Base Construction Rate Service Base Construction Rate
Contract Period
Input Tables