Potable Water 7 Crew Maximum 2021-08-02 - Copy.pdf
PDF 98 KB Posted
- Solicitation number
- N4008021R1827
About this file
This document outlines requirements for a federal construction contract to replace aging potable water lines and fire suppression systems at Naval Support Facility Indian Head in Maryland. The project includes approximately 140,000 linear feet of potable water and fire protection lines across three zones (P232, P233, and P234) that will be replaced in phases over an estimated 57-74 week timeline. Offerors must consider special construction requirements such as unexploded ordnance surveys and safety permitting. The Navy has provided a partial design package for industry feedback.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Area Work Zone Phase # of Crews Duration Weeks* Work Zone 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 North (P233 & Energetics) W1 1 3 106 21.2 W1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 North (P233 & Energetics) W2 1 1 24 4.8 W2 1 1 1 1 1 North (P233 & Energetics) W4 2 1 18 3.6 W4 1 1 1 1 North (P233 & Energetics) W3 3 2 39 7.8 W3 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Central (P232 & Energetics) W5 1 3 20 4 W5 3 3 3 3 Central (P232 & Energetics) W8 1 3 23 4.6 W8 3 3 3 3 3 Central (P232 & Energetics) W6 2 3 67 13.4 W6 3 3 3 3 3 3 3 3 3 3 3 3 3 3 Central (P232 & Energetics) W7 2 2 31 6.2 W7 2 2 2 2 2 2 2 Central (P232 & Energetics) W9 2 3 110 22 W9 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 Central (P232 & Energetics) W10 2 2 16 3.2 W10 2 2 2 2 Central (P232 & Energetics) W11 2 2 22 4.4 W11 2 2 2 2 2 South (P234 & Energetics) W12 1 3 69 13.8 W12 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 South (P234 & Energetics) W16 1 2 27 5.4 W16 2 2 2 2 2 2 South (P234 & Energetics) W13 2 3 86 17.2 W13 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 South (P234 & Energetics) W15 2 2 13 2.6 W15 1 1 1 South (P234 & Energetics) W17 2 2 23 4.6 W17 1 1 1 1 1 1 1 1 1 1 South (P234 & Energetics) W18 2 2 18 3.6 W18 2 2 2 2 South (P234 & Energetics) W19 2 2 21 4.2 W19 2 2 2 2 2 South (P234 & Energetics) W20 2 2 20 4 W20 1 1 1 1 1 1 1 1 South (P234 & Energetics) W21 2 2 20 4 W21 2 2 2 2 South (P234 & Energetics) W14 3 3 55 11 W14 2 2 2 2 2 2 2 2 2 2 2
Total Crews 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 6 6 6 6 7 7 7 5 5 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 6 6 6 6 6 5 5 5 4 2 2 2 2 2 2 2 0 0 0 0
* Partial weeks extended to not start work in next zone until following week 57 wks 74 wks
Installation Days (w/ full avg weather days) Total Installation Days 285 370
Timeline_12limit