About this file

This document outlines requirements for a federal construction contract to replace aging potable water lines and fire suppression systems at Naval Support Facility Indian Head in Maryland. The project includes approximately 140,000 linear feet of potable water and fire protection lines across three zones (P232, P233, and P234) that will be replaced in phases over an estimated 57-74 week timeline. Offerors must consider special construction requirements such as unexploded ordnance surveys and safety permitting. The Navy has provided a partial design package for industry feedback.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Area Work Zone Phase # of Crews Duration Weeks* Work Zone 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 North (P233 & Energetics) W1 1 3 106 21.2 W1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 North (P233 & Energetics) W2 1 1 24 4.8 W2 1 1 1 1 1 North (P233 & Energetics) W4 2 1 18 3.6 W4 1 1 1 1 North (P233 & Energetics) W3 3 2 39 7.8 W3 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Central (P232 & Energetics) W5 1 3 20 4 W5 3 3 3 3 Central (P232 & Energetics) W8 1 3 23 4.6 W8 3 3 3 3 3 Central (P232 & Energetics) W6 2 3 67 13.4 W6 3 3 3 3 3 3 3 3 3 3 3 3 3 3 Central (P232 & Energetics) W7 2 2 31 6.2 W7 2 2 2 2 2 2 2 Central (P232 & Energetics) W9 2 3 110 22 W9 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 Central (P232 & Energetics) W10 2 2 16 3.2 W10 2 2 2 2 Central (P232 & Energetics) W11 2 2 22 4.4 W11 2 2 2 2 2 South (P234 & Energetics) W12 1 3 69 13.8 W12 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 South (P234 & Energetics) W16 1 2 27 5.4 W16 2 2 2 2 2 2 South (P234 & Energetics) W13 2 3 86 17.2 W13 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 South (P234 & Energetics) W15 2 2 13 2.6 W15 1 1 1 South (P234 & Energetics) W17 2 2 23 4.6 W17 1 1 1 1 1 1 1 1 1 1 South (P234 & Energetics) W18 2 2 18 3.6 W18 2 2 2 2 South (P234 & Energetics) W19 2 2 21 4.2 W19 2 2 2 2 2 South (P234 & Energetics) W20 2 2 20 4 W20 1 1 1 1 1 1 1 1 South (P234 & Energetics) W21 2 2 20 4 W21 2 2 2 2 South (P234 & Energetics) W14 3 3 55 11 W14 2 2 2 2 2 2 2 2 2 2 2

Total Crews 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 6 6 6 6 7 7 7 5 5 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 6 6 6 6 6 5 5 5 4 2 2 2 2 2 2 2 0 0 0 0

* Partial weeks extended to not start work in next zone until following week 57 wks 74 wks

Installation Days (w/ full avg weather days) Total Installation Days 285 370

Timeline_12limit

File details come from the government source that posted it. Updated .