ENERGY REPAIRS MULT BLDGS NSF IH Federal contract opportunity
Solicitation number
N4008018R3519
Issued by
Department of the Navy Naval Facilities Engineering Command

About this file

Amendment07__P-231_CBIRF.pdf

View the file

Other files for this federal contract opportunity

Other files attached to ENERGY REPAIRS MULT BLDGS NSF IH, newest first.
File Type Posted
Amendment0010.pdf PDF
Vetting_Form_SECNAV_5512-1.pdf PDF
Amendment0009.pdf PDF
Amendment0008.pdf PDF
Amendment0007.pdf PDF
Amendment0006_N4008018R3519.pdf PDF
SiteVisitLog.pdf PDF
DB_MD180055_07062018.docx DOCX document
AMENDMENT_0001_EnergyRepairs.docx DOCX document
NAVFAC_WASH_PWD_SP_IH_Visit_Request.docx DOCX document
SECNAV_5512_1_11787_APPROVED_AC_PASS_ID_FORM1_(003)_Attachment_C.pdf PDF
Request_for_Information_EnergyReparis_Attachment_A.doc DOC document
SECNAV_5512_1_11787_APPROVED_AC_PASS_ID_FORM1_(003)_Attachment_C.pdf PDF
IH_EnergyRepair_Specs_Final.pdf PDF
IH_EnergyRepair_Drawing_Set_Final.pdf PDF
N4008018R3519_IH_EnergyRepair_Drawing_Set_Final.pdf PDF
N4008018R3519_IH_EnergyRepair_Specs_Final.pdf PDF
N4008018R3519_PreSolicitationForEnergy_Repairs.pdf PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT 07

N40080-16-R-0155: P-231 CBIRF Facilities 901, 902, 1542, and 1752

RFIs 1-67

Changes to the Solicitation dated May 17, 2018 are as follows:

A) DELETE/ADD the following Construction Wage Grade Requirement:

Delete: MD180055 07/06/2018 MD55

Add: MD180055 07/13/2018 MD55

General Decision Number: MD180055 07/13/2018 MD55

Superseded General Decision Number: MD20170055

State: Maryland

Construction Type: Building

County: Charles County in Maryland.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.35 for calendar year 2018 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January

1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.35 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year

2018. The EO minimum wage rate will be adjusted annually.

Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date

0 01/05/2018

1 01/12/2018

2 02/09/2018

3 02/23/2018

4 03/23/2018

5 04/20/2018

6 05/04/2018

7 05/11/2018

8 05/25/2018

9 06/15/2018

10 06/29/2018

11 07/06/2018

12 07/13/2018

ASBE0024-007 10/01/2017

Rates Fringes

ASBESTOS WORKER/HEAT & FROST

INSULATOR........................$ 35.13 16.22

Includes the application of all insulating materials, protective coverings, coatings and finishes to all types of mechanical systems

ASBE0024-010 10/01/2017

ASBESTOS WORKER: HAZARDOUS

MATERIAL HANDLER (Removal of hazardous material from ceilings, floors, mechanical systems, and walls)..............$ 22.81 7.34

BRMD0001-006 04/29/2018

TILE SETTER......................$ 28.20 11.67

BRMD0001-009 04/29/2018

TILE FINISHER....................$ 23.28 10.72

BRMD0001-011 04/29/2018

BRICKLAYER (Excluding

Pointing, Caulking and

Cleaning)........................$ 31.36 10.78

BRMD0001-012 04/29/2018

MASON - STONE....................$ 37.91 17.08

BRMD0001-013 04/29/2018

TERRAZZO WORKER/SETTER...........$ 28.20 11.67

* CARP0197-001 05/01/2018

CARPENTER (Including

Acoustical Ceiling

Installation, Drywall

Hanging, Metal Stud

Installation and Form Work)......$ 28.71 12.08

CARP0219-001 05/01/2018

MILLWRIGHT.......................$ 34.24 11.23

ELEC0026-021 09/11/2017

ELECTRICIAN (Communication and Sound Equipment).............$ 27.80 10.55

ELEC0026-022 11/06/2017

ELECTRICIAN (Including low voltage wiring for and installation of alarms, HVAC controls)........................$ 45.15 17.15+a a.PAID HOLIDAYS: New Year's Day, Inauguration Day, Martin

Luther King Jr.'s Birthday, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, the day after

Thanksgiving Day and Christmas Day.

ELEV0010-001 01/01/2018

ELEVATOR MECHANIC................$ 44.12 32.645+a+b

a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence

Day, Labor Day, Veterans' Day, Thanksgiving Day, Christmas

Day and the Friday after Thanksgiving.

b. VACATIONS: Employer contributes 8% of basic hourly rate for 5 years or more of service; 6% of basic hourly rate for

6 months to 5 years of service as vacation pay credit.

ENGI0077-017 05/01/2018

POWER EQUIPMENT OPERATOR:

Backhoe.....................$ 31.50 9.20+a

Bulldozer...................$ 31.50 9.20+a

a. PAID HOLIDAYS: New Year's Day, Inaugural Day, Decoration

Day, Independence Day, Labor Day, Martin Luther King's

Birthday, Veterans' Day, Thanksgiving Day, Friday after

Thanksgiving and Christmas Day.

IRON0005-011 06/01/2017

IRONWORKER.......................$ 31.15 20.63

LABO0657-017 06/01/2015

LABORER: Mason Tender -

Cement/Concrete..................$ 22.63 7.31

LABORER: Pipelayer..............$ 22.63 7.31

PAIN0051-014 06/01/2018

GLAZIER

Glazing Contracts $2 million and under...........$ 26.07 12.15

Glazing Contracts over $2 million.....................$ 30.31 12.15

PAIN0051-019 06/01/2017

PAINTER

Brush, Roller, Spray and

Drywall Finisher/Taper......$ 25.06 9.66

Industrial..................$ 30.90 10.49

PLAS0891-005 07/01/2018

PLASTERER........................$ 29.53 6.80

PLAS0891-006 02/01/2018

CEMENT MASON/CONCRETE FINISHER...$ 28.15 10.58

PLAS0891-008 08/01/2016

PLASTERER (Fireproofing

Including Sprayer, Mixer, and

Handler)

Handler.....................$ 16.50 4.89

Mixer/Pump..................$ 18.50 4.89

Sprayer.....................$ 23.00 4.89

PLUM0005-010 02/01/2018

PLUMBER..........................$ 41.67 17.60+a

a. PAID HOLIDAYS: Labor Day, Veterans' Day, Thanksgiving Day and the day after Thanksgiving, Christmas Day, New Year's

Day, Martin Luther King's Birthday, Memorial Day and the

Fourth of July.

PLUM0602-013 08/01/2017

PIPEFITTER (HVAC Pipe and

System Installation Only)........$ 40.69 21.07+a

a. PAID HOLIDAYS: New Year's Day, Martin Luther King's

Birthday, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day and the day after

Thanksgiving and Christmas Day.

ROOF0030-016 05/01/2016

ROOFER...........................$ 28.75 11.74

SFMD0669-001 04/01/2017

SPRINKLER FITTER (Fire

Sprinklers)......................$ 34.40 19.24

SHEE0100-015 03/01/2018

SHEET METAL WORKER (Including

HVAC Duct Installation)..........$ 40.27 18.87+a

a. PAID HOLIDAYS: New Year's Day, Martin Luther King's

Birthday, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day and Christmas Day

SUMD2010-089 08/20/2010

LABORERS

Common or General...........$ 11.38

Grade Checker...............$ 16.00 2.90

Landscape...................$ 9.23

Mason Tender - Brick........$ 13.00

Mason Tender - Stone........$ 14.03

Mason Tender for Pointing, Caulking and Cleaning.......$ 13.25

Mortar Mixer................$ 16.61 9.09

PIPEFITTER (Excluding HVAC

Pipe and System Installation)....$ 28.96 11.35

POINTER, CAULKER, CLEANER,

Includes pointing, caulking, cleaning of existing masonry, brick, stone and cement structures (restoration work); excludes pointing, caulking, cleaning of new or replacement masonry, brick, stone or cement...........................$ 19.17

POWER EQUIPMENT OPERATOR:

Asphalt Roller..............$ 21.35 5.38

Bobcat/Skid Loader..........$ 18.05 8.78

Boom........................$ 21.44 8.29

Crane.......................$ 20.95 6.18

Excavator...................$ 20.00

Forklift....................$ 16.00 5.12

Gradall.....................$ 20.50 8.42

Grader/Blade................$ 14.50 5.18

Loader......................$ 22.75 4.91

Paver.......................$ 17.47 6.36

Roller excluding Asphalt....$ 17.60 3.88

TRUCK DRIVER

Dump Truck..................$ 15.90 1.12

Tractor Haul Truck..........$ 17.87 9.98

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the

Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate

(weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or

"UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010

08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour

Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the

Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the

Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations

Wage and Hour Division

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator

(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator

U.S. Department of Labor

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative

Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board

U.S. Department of Labor

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION