Attachment J - N4008017R0006 - Multiple HVAC - PPI 4-6 Government Response.xlsx

XLSX spreadsheet 26 KB Posted

Attached to
REPAIR HVAC – MULTIPLE BUILDINGS – FY23
Solicitation number
N4008017R0006
Issued by

About this file

This document contains the government's responses to pre-proposal inquiries for federal solicitation number N4008017R0006 to repair HVAC systems at multiple buildings on a Marine Corps base in Virginia. The Navy seeks HVAC repairs and replacements at several buildings, including new air handlers, condensing units, a chiller, and ductwork testing and balancing. The responses clarify equipment details, control systems, and temporary cooling requirements. Pricing should account for potential material cost increases over six to eight months. Drawings were previously provided except for one building.

View the file

Other files

File Type Posted
RFP Attachment A - Statement of Work revised 8-22-2023.pdf PDF
N4008017R0006- RFP Amendment 0006 - Repair HVAC Multiple Bldgs FY23.pdf PDF
RFP Attachment C - Price Proposal Form revised 8-22-2023.xlsx XLSX spreadsheet
N4008017R0006- RFP Amendment 0005 - Repair HVAC Multiple Bldgs FY23.pdf PDF
N4008017R0006- RFP Amendment 0004 - Repair HVAC Multiple Bldgs FY23.pdf PDF
Attachment H - N4008017R0006 - Multiple HVAC - PPI 2 Government Response.xlsx XLSX spreadsheet
N4008017R0006- RFP Amendment 0003 - Repair HVAC Multiple Bldgs FY23.pdf PDF
Attachment I - N4008017R0006 - Site Visit Bldg 3098 7-26-23.pdf PDF
N4008017R0006- RFP Amendment 0002 - Repair HVAC Multiple Bldgs FY23.pdf PDF
RFP_Attachmen A - SOW Repair HVAC Multiple Bldgs FY23 revised.pdf PDF
Attachment F - N4008017R0006 - Site Visit Log 7-19-23.pdf PDF
N4008017R0006- RFP Amendment 0001 - Repair HVAC Multiple Bldgs FY23.pdf PDF
Attachment E - N4008017R0006 - Multiple HVAC - PPI Government Response.xlsx XLSX spreadsheet
Attachment D - DBA Wage Determination VA20230162.pdf PDF
Attachment B - Pre-Bid Proposal Inquiry Form.xlsx XLSX spreadsheet
Attachment A - SOW Repair HVAC Multiple Bldg FY23.pdf PDF
N4008017R0006- Request For Proposal - Repair HVAC Multiple Bldgs. FY23.pdf PDF
Attachment C - Price Proposal Form.xlsx XLSX spreadsheet
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

AMENDMENT 0004
ATTACHMENT J - N4008017R0006 - GOVERNMENT RESPONSE TO PRE-PROPOSAL INQUIRIES
Question No.Date ReceivedREFERENCEQUESTIONGOVERNMENT RESPONSEPosted on Amend No.
PageSectionPara.
18/4/23---CLIN 0001 Building 2077: The RFP requires the condensing units to be replaced in kind. CU-1 and 3 are located adjacent to the exterior wall of the building and may not meet the manufacturer clearance requirements. Should alternative pricing be provided to locate the condensing units at grade to meet clearance requirements?If new equipment doesn’t meet manufacturer clearance requirements, provide alternate recommendations and pricing.0004
1.a.8/4/23---Please provide any deficiency list for any associated equipment. If no deficiency list is provided is the contractor to assume only deficiencies needed for repair are the three air handlers and three condensers as shown on the walkthrough.The three (3) Carrier condensing units are all inoperable. We are unable to provide a deficiency report at this time. The Governemnt wants to ensure that all components (electrical,DDC, control valves & dampers and hydronic components)associated with each DX system are operable and will not prevent the new systems from fuinctioning properly.0004
1.b8/4/23---Please confirm that the return fans for the three air handlers are existing to remain.If the return fans are all operational, they can remain. If components/parts are needed, Provide pricing.0004
28/4/23---CLIN 0002 Building 26100 (RTC): Is temporary cooling required to be provided to serve the spaces served by the split system AHU to be replaced?Yes.0004
38/4/23---CLIN 0002 Building 26100 (RTC): The existing AHU appears to be controlled by an Automated Logic DDC system. Is this building connected to the Siemens network?This building does not have Siemens brand controls.0004
48/4/23---CLIN 0004 - Temporary HVAC: Will the temporary cooling currently located at the existing buildings (2074, 2077, 24193, 3240) be retained by the government until construction is complete or will it be removed at the time of award?The construction contractor will be able to negotiate with the QBOS contractor to take over the rental of the temporary chiller/HVAC after their contract award.
0004
58/4/23---CLIN 0004 and CLIN 0011 – Temporary HVAC: Which buildings are covered by which CLIN? What is the difference between CLIN 0004 and 0011?CLIN 0004 covers temporary cooling for the buildings listed in the Base Bid and CLIN 0011 covers temporary cooling for the buildings listed in the Option bid.0004
68/4/23---CLIN 0005 – TAB and DALT: Please confirm that the TAB of all distribution systems means the systems being replaced as part of this contract and not all air distribution systems in the buildings.Confirmed. Distribution systems associated with the equipment/system replacements in RFP.0004
6.a8/4/23---Please confirm that DALT testing on all existing ductwork means that DALT testing on all sections of ductwork in accordance with the pressure class recommendations from UFC referenced standards.Confirmed and ANSI/ASHRAE Standards.0004
6.b8/4/23---Please confirm the only DALT testing needed is on new work and not the existing systems.Is needed for existing duct systems associated with the new system/equipment.0004
6.c8/4/23---Please confirm we are only to test and balance new equipment provided during peak cooling and heating seasons.Test and balance new equipment and associated ductwork during peak seasons.0004
78/4/23---CLIN 0006 – Bldg 3240: Please provide any deficiency list for any associated equipment. If no deficiency list is provided is the contractor to assume only deficiencies needed for repair is the Trane packaged heating and cooling unit?Known deficiencies are within existing package unit.0004
88/4/23---CLIN 0007 – Bldg 3255: Please provide any deficiency list for any associated equipment. If no deficiency list is provided is the contractor to assume no work is needed in this building?The known deficiencies are within the building air handlers and associated controls.0004
98/4/23---CLIN 008 – Bldg 2074: Please provide any deficiency list for any associated equipment. If no deficiency list is provided is the contractor to assume only deficiency needed for repair is the Trane air-cooled chiller.The known deficiencies are within the chiller. However, we will need the chiller plant (pumps, valves,controls, electrical) assessed to verify the existing components are functional and can accommodate new chiller manufacturer specifications.0004
108/4/23---CLIN 0009 – Bldg 3314 (CDC South): Can the controls work required by this RFP be performed during the day or are there specific restrictions to work in the CDC?Dependent on how extensive the work is in the classrooms. Assume after hours work.0004
10.a8/4/23---Is the intent of the scope to only replace the room thermostats with temperature and humidity sensors?The intent is to upgrade the thermostats to read temperature and humidity and make any programming changes and/or adjustments if necessary.0004
118/4/23---CLIN 0010 – Bldg 3098 Diamond Hall: How many of the existing ducted 33 WSHP systems located ceilings are currenting not functional? Are the existing 3 water sourced AHUs still being utilized?Cannot verfiy how many WSHP have issues. Will need all 33 assessed and replace all R-22 WSHP's in-kind. All 3 AHU's are being utilized.0004
128/4/23---CLIN 0012 – TAB and DALT:Please confirm that the TAB of all distribution systems means the systems being replaced as part of this contract and not all air distribution systems in the buildings.Confirmed. Distribution systems associated with the equipment/system replacements in RFP.0004
12.a8/4/23---Please confirm that DALT testing on all existing ductwork means that DALT testing on all sections of ductwork in accordance with the pressure class recommendations from UFC referenced standards.Confirmed and ANSI/ASHRAE Standards.0004
12.b8/4/23---Please confirm the only DALT testing needed is on new work and not the existing systems.New work and associated duct system.0004
12.c8/4/23---Please confirm we are only to test and balance new equipment provided during peak cooling and heating seasons.Test and balance new equipment and associated ductwork during peak seasons.0004
18/4/23---Please confirm CLIN 0004 and 0005 are also for B24193Only CLIN 0004 and part 6c of CLIN 0005.0004
28/4/23---Please confirm CLIN 0011 and 0012 are also for B3098Confirmed.0004
38/4/23---Please provide Mechanical duct drawings for B3098 in order to provide TAB and DALT pricingDesigns and Drawing of all buildings with the exception of Building 26100 were provided in Amendment 0001 posted on SAM.Gov.0004
48/4/23---Please provide quantities and sizes of WSHP’s in building 3098 being replacedReported that there are 33 WSHP's. Sizes are unknown. KTR shall verify through site visit(s).0004
58/4/23---Please verify if there is an existing DDC control system in building 26100 and 3240. If so please verify who the manufacturer/installer is?B-26100 has off brand controls. B-3240 is standalone/thermostat controlled.0004
68/4/23---If there is not an existing DDC system in buildings 26100 and 3240; should new DDC controls be installed for the new HVAC equipment being replaced or just standalone electric controls?B-26100 provide upgraded controls for equipment. B-3240 replace thermostat to accommodate new HVAC equipment.0004
78/4/23---If new DDC controls are needed what manufacturer/installer is preferred to provide the new DDC controls?Siemens.0004
18/4/23---Building 3314-Please provide drawings to show quantities and locations of temp sensorsDrawings were distrubuted via DoD Safe link to all 8(a) Mechanical MACC Contract holders, as a part of Amendment 0001 issued 25 July 2023.0004
28/4/23---Please provide drawings if available for each buildingProvided in Amendment 0001, with exception to B-26100.0004
38/4/23---Please provide any deficiency reports for all buildings.Do not have record of reports.0004
48/4/23---Since deficiencies for each building are unknown, please provide the type of repairs needed for all buildings so all bidder are pricing same SOW.The repairs for deficiencies (if needed) pertain to the SOW for each building listed in the RFP. For example; If it’s a chiller replacement SOW, ensure pumps, electrical,DDC and associated chiller plant components are functional and can accommodate new chiller maufacturer specifications.0004
58/4/23---The acceptance period is 180 days.Given the current market conditions our subs typically hold their pricing for only 15 to 30 days. Can the acceptance period be adjusted or will we have the options of submitting a MOD if increase occur?Provide pricing with anticipated material costs increase for a 6-8 month period.0004
68/4/23---Please provide the MEP drawings on all building for this project?Drawings were distrubuted via DoD Safe link to all 8(a) Mechanical MACC Contract holders, as a part of Amendment 0001 issued 25 July 2023.0004
78/4/23---B2077 – Do you have the equipment tags of the 3 units listed, the RFP only has one listed?The equipment schedule is listed in the drawings.0004
88/4/23---B26100 – Please provide the chiller equipment tag information and what issues have they been having?Chiller tag was provided in Part 6 with attachments. Chiller has reported refrigerant leak. Refrigerant is/was R220004
98/4/23---B24193 – Please provide the chiller tag data and what are the issues you been having?Chiller data available in schedule of drawings. Electrical related failures are reported pertaining to the chiller.0004
108/4/23---B3255 – What are the reported heating/cooling issues you have been having?Issues within the AHU'S and associated DDC.0004
118/4/23---B2074 – Please provide the chiller tag data for this chiller?Equipment schedule available in drawings.0004
128/4/23---B3314 – What is the make of the existing BAS systemControls are Carrier brand.0004
138/4/23---B3098 – Please providee the McQuay MAU Tag data. How many Heat Pumps are on the system?Unavailable. 1- Make-up air handler w/ hot water heating and DX coil & 1- DX- Condenser with 2 stages of cooling.0004
148/4/23---Do we include repairs in our proposal, or would that be a change?Include.0004
---
---
---
---

SOLICITATION NO. &"-,Bold"N4008017R0006&"-,Regular" PROJECT TITLE/LOCATION: Repair HVAC and Replace Roof, Davis Center, Building 3300, Marine Corps Base Quantico, VA 22134

Attachment B: Pre-Bid/Proposal Inquiry Form
&"-,Italic"&KFF0000

July 2016

Sheet2

Sheet3