This document contains a pre-solicitation notice for facilities support services contract N40080-20-R-0001 to be awarded by the Naval Facilities Engineering Command. The single-award IDIQ contract will have a one year base period and four one-year option periods, not to exceed 66 months total. Services include custodial, pest control, grounds maintenance, landscaping, pavement clearance, transportation, and material handling. The solicitation will utilize FAR Part 15 procedures and require experience, technical approach, management approach, safety, and past performance submissions with price. Award will be made using a tradeoff process considering best value. The NAICS code is 561720 and size standard is $19.5M. The draft RFP is attached with the final RFP on January 30th and proposals due February 20th. The incumbent is Diversified Service Contracting, Inc. under contract N40080-11-D-3020 valued at $71M. This procurement will be an 8(a) small business set-aside.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT "A"
CONTRACTOR CRANE OPERATING CHECKLIST FOR CRITICAL LIFTS YES NO
1 Does the operator know the weight of the load to be lifted?
Is the load to be lifted within the crane manufacturer's rated capacity in its present configuration?
3 Is the crane level and on firm ground?
4 Are outriggers required?
5 If so, are outriggers fully extended and down, and the load off the wheels?
6 If blocking is required, is the entire surface of the outrigger pad supported, and is the blocking material of sufficient strength to safely support the loaded outrigger pad?
If outriggers are not used, is the crane rated for on-rubber lifts by the manufacturer's load chart?
Is the swing radius of the crane counterweight clear of people and obstructions and accessible areas within the swing area barricaded to prevent injury, damage and unplanned encroachment?
Has the hook been centered over the load in such a manner to prevent swing (deflection, side loading, load-moment)?
Is the load well secured and balanced in the sling or lifting device before it is lifted (free and clear) more than a few inches?
11 Is the lift swing path clear of obstructions?
12 If rotation of the load being lifted is hazardous, is tag line or restraint line being used?
13 Are personnel prevented from standing or passing under a suspended load?
14 Are personnel prevented from entering the load fall zone?
15 Is the crane operator's attention diverted?
16 Are proper signals being used at all times?
17 If radio communications are used is the frequency isolated to the crane team?
18 Do the operations ensure that side and tip loading is prohibited?
Are start and stop motions in a smooth fluid motion (no sudden acceleration or deceleration)?
If operating near electric power lines, are the rules and guidelines understood and adhered to as specified in NAVFAC P-307?
21 Is the lift a critical lift?
If so, are critical lift regulations understood, check-off sheets initialed and signed off, and was there an interactive brief conducted with associated personnel?
23 Is Attachment "A" current, filled out completely, and posted in the crane?
Contractor Name (Print Legibly):
Contractor Name (Signature):
Location: Date: