This document contains a request for submission (RFS) for environmental science and engineering services to support the Naval Facilities Engineering and Expeditionary Warfare Center (NAVFAC EXWC). Firms are invited to submit a completed Standard Form 330 by June 2021 for consideration of a single-award, indefinite delivery indefinite quantity contract with a maximum value of $100 million over a 60-month base period and 6-month extension period. Services required include site investigation, remediation, and technology support for environmental restoration and compliance projects worldwide on a range of contaminants. Evaluation criteria prioritize experience in emerging contaminants like PFAS, radiological compounds, bioremediation, and munitions response. The small business participation goal is 20% across prime and subcontracts.

View the file

Other files

File Type Posted
N3943021R2201 RFI 0004.pdf PDF
N3943021R2201 RFI 0003.pdf PDF
N3943021R2201 RFI 0002.pdf PDF
Attachment B - SB Participation and Commitment Strategy.docx DOCX document
SAES for ESEC Contract 30 Sep 2020.docx DOCX document
Attachment A - PPQ.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

No. Reference Question Answer

1 Selection Criteria (2) Specialized Experience and Technical Competence

The selection criteria (2) states, “Firms shall submit no more than two (2) page per project (size 12 Calibri with a minimum of 1” margins on the top, bottom, and sides).” Are these font and margin restrictions applicable to the entire submittal?

Yes.

2 Selection Criteria (2) Specialized Experience and Technical Competence

Is smaller font (9 or 10 point) again acceptable for tables and figures, including the organizational chart?

It is acceptable to use a smaller font size for tables and figures, including the organizational chart.

3 Selection Criteria (2) Specialized Experience and Technical Competence

The selection criteria (2) states, “In Section H, also indicate the estimated percentage of involvement in each project of each firm on the proposed team." Please confirm it is ok to provide additional supporting information in Section H to address 1. Professional Qualifications and 2. Specialized Experience.

Not confirmed. The only additional information allowed in Section H is for criteria (2) is “the estimated percentage of involvement in each project of each firm on the proposed team.”

4 Selection Criteria (2) Specialized Experience and Technical Competence

Please confirm that an IDIQ with multiple task orders can be used as a project in Section F.

Depends. The synopsis states “a project can also be defined as multiple task orders supporting one installation or customer”, that is generally in the context that there may be multiple contractors supporting a single project (i.e.

a contractor to perform investigation, another contractor to perform remediation). However, if the single project required the issuance of multiple task orders to the same firm (i.e. one task order for an investigation and a subsequent task order for oversight/quality assurance), then in those cases multiple task orders would be acceptable as one project.

5 Selection Criteria (2) Specialized Experience and Technical Competence

If Question #4 is confirmed, is it acceptable for Section F project write-ups to include all completed work for an ongoing IDIQ contract?

Bearing in mind the response to Question 4, we will not consider task orders under IDIQs that supported multiple projects as just a single project.

6 Selection Criteria (2) Specialized Experience and Technical Competence

In Section F, when a project write-up includes multiple TOs supporting an installation, facility, or customer, is it acceptable for project write-ups to include all completed work for Ongoing TOs?

We emphasize the key word is “project” as in a single undertaking with a series of tasks that must be completed in order to achieve a specific outcome. A “completed” project would not have on-going task orders.

7 Selection Criteria (2) Specialized Experience and Technical Competence

An organizational chart shall be provided and be no larger than 8.5” x 11.” Please confirm the organizational chart is provided in Section D.

Yes, the organizational chart shall be presented as an attachment to Section D of the

SF330.