N3319123R0054 Kindergarten Cahul Moldova _Attach 1 PTS (Part 3 of 5).pdf
PDF 8 MB Posted
- Solicitation number
- N3319123R0054
About this file
This document is the solicitation for contract N3319123R0054 to design-build and renovate Kindergarten No. 2 in Cahul, Moldova. The solicitation involves renovating the frame roof, installing thermal insulation on the ceiling and facades. The Navy is the contracting agency seeking proposals to replace the existing wooden roof with a new wooden truss roof and metal tile covering. The project also includes replacing windows, insulating and finishing exterior walls, and landscaping. The renovation work is scheduled for completion within six months of award.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BLOCK
i=25° i=30°
BLOCK
BLOCK
i=30° i=60°
Signal. Date.
i=60°
BLOCK A
BLOCK A
BLOCK A
BLOCK A
Mode. part no. Sheet No. doc.
i=30°
BLOCK
i=30°
SRL "PROJECT-DESIGN"
3) The existing metal escape stairs are in satisfactory condition. It is planned to restore them -cleaning, priming, painting in 2 layers.
NOTE:
1) The existing roof is of the frame type with slate sheet coverings. It is in unsatisfactory condition and does not meet the standards. It is intended for disassembly.
4) The old (wooden) windows are dismantled.
2) The existing ventilation ducts are made of brick. It is planned to dismantle them up to the existing floor. The dimensions and location of the ventilation ducts to be determined on site.
BENEFICIARY:
Cahul City Hall
11/20
11/20
FACADE IN AXES 3b-1b - EXISTING SC.1:200
FACADE IN AXES 1b-3b - EXISTING SC.1:200
FACADE IN CA AXES - EXISTING SC.1:200
FACADE IN AC AXES - EXISTING SC.1:200
Flat Phase
THAT
ON 6
A
A.ÿ.P.
3b A
Prepared Prepelita A.
1b
2. 3
Existing facades sc. 1:200
C
1b
3b boards
2b
BLOCK "B"
Limbas S.
13,000
12,500
2,700
4,000
13,000
4,000
0.700
6,050
6 100 6,400
11,140
11,140
10,100
3,300
0.000
-0.650
10,100
6,000
2,700
2,700
0.700
12,500
6,000
GSPublisherVersion 0.49.100.100
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2
"Licurici" in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086
No. 055984 from 08.09.17
License Series A MMII
The existing truss type roof with slate sheathing is being removed
6,500
The wooden windows are dismantled
4,000
6,200
6,000
2,900
The wooden drum is dismantled
The wooden windows are dismantled
11,140
-0.050
The existing truss type roof with slate sheathing is being removed
5,200
2,700
0.700
-0.600
The existing truss type roof with slate sheathing is being removed
The existing metal staircase
-0.900
The wooden windows are dismantled
0.700
The existing truss type roof with slate sheathing is being removed
4,000
The wooden drum is dismantled
2,700
The existing metal staircase
6,000
The existing truss type roof with slate sheathing is being removed
2,700
11,140
-0.050
6,000
0.000
The existing truss type roof with slate sheathing is being removed
4,655 i=12°
Existing metal railing
1,900
10-12/20 - 2 - Sat
Machine Translated by Google
4 400 two hundred
9,700
1 400 1 800 1 550 two hundred
1 000 550
2 000 1 500
1 300
3 100
2,800
12,500
2 250
3 300
13,550
3 400
9,200
7,900
1 800
5,950
2,800
9,200
2 350
3 650 3 300 two hundred
150 1 400
13 000 9 700
13,000
2,800
1 600
2 250
SRL "PROJECT-DESIGN"
±0.000
-1,600
10-12/20 - 2 - Sat
11/20
11/20
EXISTING BASEMENT PLAN (relief) elevation -1,600 SC.1:100
6,400 6 100 12,500
EXISTING GROUND PLAN (survey) elevation 0.000 SC.1:100
Group
1b
B
A
3b
B
C
A
1b 2b
C
3b2b
Limbas S.
Flat Phase
BLOCK "B"
Prepared Prepelita A.
Existing basement plan (relief) elevation -1,600. Existing ground floor plan (survey) elevation 0.000 boards
A.ÿ.P.
7ON
BLOCK "A"
2. 3
BLOCK "A"
GSPublisherVersion 0.49.100.100
Date.Mode. part no. Sheet No. doc. Signal.
License Series A MMII
No. 055984 from 08.09.17
5,900
6 100
1 950
1 800
1 800
1 7003 100
500550
2 150
3 100
BENEFICIARY:
Cahul City Hall
5,600
5,900
1 700 1 800 9,600
12,500
5,600
1 600
6,400
3 950
5,900
5,600
6,400
6,400
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2
"Licurici" in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086
BLOCK "B"
Prepared Prepelita A.
boards
A.ÿ.P.
8ON
Existing floor plan (relief) elevation +3,300.
Existing roof plan
2. 3
BLOCK "A"
Flat Phase
11/20
11/20
3 400
14,80013,000
900 7
4,850
2,800
1 300
13,000
14,800
2 250
3 300
1 800 i = 30°
9,700 i = 30°
1 800 1 550 two hundred two hundred
4 400
Limbas S.
Group
EXISTING FLOOR PLAN (survey) elevation +3,300 SC.1:100 i=30°
EXISTING ROOF PLAN SC.1:100
i=30°
1b
C
A A
3b1b3b
C
2b
B
GSPublisherVersion 0.49.100.100
Mode. part no. Sheet No. doc. Signal. Date.
1 825
14 250
14 250
No. 055984 from 08.09.17
License Series A MMII
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2
"Licurici" in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086
SRL "PROJECT-DESIGN"
NOTE:
2 150
BENEFICIARY:
Cahul City Hall
500 5,600
3 100
Wood that is in satisfactory condition will be reused for the new roof. 3) The existing roof -
6,787 m3 4) The existing roof is of the roof type with slate sheets. It is in unsatisfactory condition and does not meet the standards. It is intended for dismantling - 242.40 m2.
3 100
5,900
1 800
1 700
1) The existing floor is made of prefabricated panels. The condition of the floor is satisfactory. 2) As a result of wetting, the wooden frame partially rotted - it is dismantled.
6,400
12,500
10-12/20 - 2 - Sat
+3,300
6 100
12,500
Wooden carpentry (windows) (pcs.) 14
1 Drum (plank) (m2) 6.04
GSPublisherVersion 0.49.100.100
License Series A MMII
No. 055984 from 08.09.17
PIC. THE AMOUNT
BOARD OF DISMANTLING WORKS
items NOTES
+3,300
6 1006,400
±0.000
12,500
SRL "PROJECT-DESIGN"
11/20
11/20
GroupGroup
2b
A
3b
A
C
B
2b 3b
B
C
1b 1b
Limbas S.
3 100
1 800
1 600 2000
6 100
5,600
1 600
1 800
5,600
1 7002000
2 150
3 950
5,600
1 950
6,400
2 100
6,400
3 100 3 1001 700
12,500
5,900
5,900
3 100
5,900
2 150
Signal. Date.Mode. part no. Sheet No. doc.
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2
"Licurici" in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086
BLOCK "A"
9 2. 3ON
Prepared Prepelita A.
Ground plan (dismantling) quota 0.000. Floor plan
(dismantling) elevation +3,300
BLOCK "B"
Flat Phase
A.ÿ.P.
boards
BLOCK "A"
2 250
1 800 1 550 two hundred
9,700
3 650 3 300
1 600
2 250
3 400
2,800
1 800
5,950
1 300
1 400
13,000
7,900
2,800 two hundred
1 800 two hundred
4,850
1 300
9,200
1 800 1 550
4 400
2 250
3 100
13,000 two hundred
150 1 400
9,700 two hundred
4 400
2,800
900 7
2 350
3 400
3 300
2 000 1 500
10-12/20 - 2 - Sat
3) The old (wooden) windows are dismantled.
2) The existing metal escape stairs are in satisfactory condition. Their renovation is planned; they will be scraped, primed and painted in 2 layers.
4) During the execution of the dismantling work on the existing eaves , protection measures for the existing windows must be provided. Dismantling works to be carried out on small sectors.
BENEFICIARY:
Cahul City Hall
NOTE:
1) The existing drum is made of wood. His condition is unsatisfactory. It is planned to dismantle it.
GROUND PLAN (dismantling) elevation 0.000 SC.1:100 FLOOR PLAN (dismantling) elevation +3,300 SC.1:100
GROUND PLAN (new constructions) elevation 0.000 SC.1:100
Group
FLOOR PLAN (new constructions) elevation +3,300 SC.1:100
Group
1b
B
C
B
A
2b 3b1b 2b
A
C
3b
Mode. part no. Sheet No. doc. Date.Signal.
Limbas S.
2 250
150 1 400
F 2
3 400
F 2
1 400
1 300
7,900
2 250
F1
F 2
9,700
1 800 1 550
5,950
4 400
3 300 two hundred two hundred
13,000
1 800
3 100
2 000 1 500
2,800
U1
13,000
2 250 two hundred
1 800 1 550 two hundred
F1 two hundred
900 7 9,200
2,800
1 600
4 400
2 350
3 400
4,850
2,800
1 300
3 650 3 300
F 2
9,700
1 800
SRL "PROJECT-DESIGN"
6 100
12,500
+3,300
6,400
10-12/20 - 2 - Sat
±0.000
11/20
11/20
License Series A MMII
No. 055984 from 08.09.17
2 150
6,400
3 100 800 1 700
6,400
PIC. NOTESTHE AMOUNT
6 100
3 100 3 100
BOARD OF NEW BUILDING WORKS
5,900
1 800
2 150
12,500
5,600
800 800
5,900
1 800 items
3 100 1 700
1 600
5,600
3 950 1 950
5,900
BENEFICIARY:
Cahul City Hall
2 100
5,600
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2
"Licurici" in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086
F3
BLOCK "B"
2. 3
F1
Flat Phase11.20
A.ÿ.P.
F3 boards
PVC carpentry (windows) (pcs.)
24.00
F3 F2
Metal railing (ml) Galvanized sheet apron b=200mm (m/l)
F3
F1
Basement awnings - corrugated board (m2) 2.00
Prepared Prepelita A.
BLOCK "A"
ON
Ground plan (new construction) elevation 0.000. Floor plan
(new construction) elevation +3,300 see pl. 12
BLOCK "A"
9.80
F2
Window awnings - technonikoli (m2)
274.40 kg see pl.12
Galvanized sheet dripper b=200mm (m/l)
24.00 GSPublisherVersion 0.49.100.100
Resume
1 300
4 4304 430
2,800
2 100
Dormer L1 entrance to the attic
Existing parapet h=800mm
Resume
Resume
12,300
New belt on perimeter h=200mm
3 440
Resume
Sm2
12,300
SRL "PROJECT-DESIGN"
4 300
13,000
12,750
4 300
13,000 12,750
8,050
4 400
400 400
11/20
11/20
C
1b
A
3b
C
A
1b 3b
Limbas S.
h=150mm see "C" h=50mm Mode. part no. Sheet No. doc.
see pl. 14
Signal.
h=4.00m
Date.
see pl. 15
DESIGNED CERDAC PLAN (elevation +6,600) SC.1:100 EXISTING CERDAC PLAN elevation +6,600 SC.1:100
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2
"Licurici" in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086
10-12/20 - 2 - Sat
38,40
BLOCK "B"
Cement-plast thermal insulation (m3)
23.50
NOTES
THE AMOUNT
Metal ladder Sm2 (pc.)
Flat Phase
A.ÿ.P.
Ventilation channel (pcs.)
Existing cerdac plan. Plan cerdac designed elevation + 6,600.
Mortar screed (m2)
2. 3 boards
Reinforced concrete belt (m3)
156.80 see "C"
ON
PIC.
Prepared Prepelita A.
items
Galvanized profiles (m2)
4 Skylight L1 (pc.)
GSPublisherVersion 0.49.100.100
BENEFICIARY:
Cahul City Hall
6) Details on L1 dormers see pl. 14.
5) The dimensions and location of the ventilation ducts to be determined on site.
NOTE:
1) The existing floor is made of prefabricated panels.
The condition of the floor is satisfactory.
7) Details on the metal scale see comp. "C".
2) On the perimeter of the building to be executed, the monolithic reinforced concrete belt h=200mm (see comp. "C").
BORDEROU MATERIALS
3) It is recommended to perform thermal insulation on the entire surface of the floor: a layer of cement plaster - 150
mm. Above to execute the h-50mm mortar screed.
4) The existing ventilation ducts to be raised above the roof level, to be executed according to the project
(see compartment "C").
12,500 12,500
No. 055984 from 08.09.17
License Series A MMII
+10,300
10-12/20 - 2 - Sat
12,500
+10,060
+10,400
+10,400
3 300
SRL "PROJECT-DESIGN"
Mode. part no. Sheet No. doc.
see "C"
Signal.
Existing wall
Date.
L=1000mm zinc 275gr/m2 thick.0.45mm
TECHNONICOLI
zinc metal tile 275gr/ m2 thick.0.45mm
Exterior finish insulation see pl. 19
Galvanized sheet apron
Galvanized sheet dripper
Window see pl. 15
Existing floor (at windows)
11/20
11/20 trough trough
BP1
pipe
5. The joints and junctions of the roof elements to be executed with nailed studs at a distance of 20 cm from the edge (posts, diagonals).
8. Specifying the ventilation ducts as planimetric dimensions will be established on site.
pipe pipe
The snow guard
3. Under the elements resting on the wall or slab, lay 2 layers of ruberoid on bitumen mastic on the leveled surface with 20mm mortar.
Resume
14 640
7 320
Sm2
1. For roof truss structures, the wood should be softwood (pine), the humidity of which should not exceed 20%. Type of wood - II. The dimensions of the elements must be according to GOST 8486-86.
pipe trough
6 820
BENEFICIARY:
Cahul City Hall
EXECUTION NODE
BP1
6 820 pipe
6. Roof construction works to be performed according to ÿÿÿÿ II-25-80 "ÿÿÿÿÿÿÿÿÿÿ ÿÿÿÿÿÿÿÿÿÿÿ". 7. The frame will be made of corrugated sheet metal on the wooden case.
4. After installing and aligning with nails the load-bearing elements of the frame to be reinforced later with bolts.
Resume trough pipe
L1
2. All wooden elements of the frame to be subjected to antiseptic and fireproof treatment according to CHÿÿ 2.03.11-85.
7 320
WINDOW CANOPIES
pipe
5 280
BORDEROU ROOFING MATERIALS
2 770
14,750
4 pl.
4 pl.
i = 20°
13,000 i = 20°
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2
"Licurici" in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086
BLOCK "B"
NOTES
59.00
55.00 m/l
THE AMOUNT
Flat Phase
Gutter (m/l)
A.ÿ.P.
Skylight L1 (pc.)
Corrugated board (roof eaves (m2))
2. 3
Projected roof boards
PIC.
ON
items
235.90
Prepared Prepelita A.
47.00
Metal ladder (pcs.)
Downspout (pc.)
Roof block "B" (m2)
Snow guard (pc.)
41.30
GSPublisherVersion 0.49.100.100
Limbas S.
Guard rail Bp-1 (ml)
License Series A MMII
No. 055984 from 08.09.17 floors i=25°
PROJECTED ROOF PLAN SC.1:100
Note:
floors i=25°
A
1b
C
3b
Composition I
BENEFICIARY:
Cahul City Hall
12,500
Composition IV
Metal tile (red color) Slats 100x30 pitch 250...350mm
Counterslats 50x50 on the rafters Diffuse waterproofing membrane
120g/m2 Rafters 160x50 pitch 800mm
Composition III
Cement-sand mortar leveling screed M100 - 50mm
Composition II
6 1006,400
License Series A MMII
No. 055984 from 08.09.17
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2
"Licurici" in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086
SRL "PROJECT-DESIGN"
C
pl. 16
III
N
D
pl. 17
Resume
A
pl. 16
B pl. 16
SECTION 3 - 3 DESIGN SC.1: 100
A
pl. 16
L2 yl and
1b 2b 3b
11/20
11/20
10,300
6,600
7,600
6,000
2,700
-1,600
10-12/20 - 2 - Sat
4,000
-0.450
3,300
-0.600
2,100
0.700
10,400
6,800
0.000
Limbas S.
GSPublisherVersion 0.49.100.100
2. 3 boards
Mineral wool thermal insulation - 50mm
Mesh glue
Finishing the ceiling
ON
Klinker brick cladding
Fiberglass net
Vertical linochrome waterproofing - 1 layer
Prepared Prepelita A.
Cyclopean concrete
Decorative plaster
BLOCK "A"
Vapor barrier - ruberoid on bituminous mastic
Plastic dowels for fixing polystyrene
Mesh glue
BLOCK "B"
Fiberglass net
Mesh glue
A.ÿ.P.
Mesh glue
Plastic dowels for fixing polystyrene Adhesives for fixing polystyrene Cement-based plaster
Limestone blocks M.35 on mortar M.50 Interior plaster
Existing precast concrete slab floor - 160 mm
Glue for fixing polystyrene
Interior plaster
Flat Phase
Thermal insulation with cementoplast Ø200 h=150 mm
- it is a solution for thermal insulation of the attic
Thermal insulation from extruded polystyrene - 80mm
Bitumen-based primer
Section 3-3 projected
Mode. part no. Sheet No. doc. Signal. Date.
3 300
Composition IV
Metal tile (red color) Slats 100x30 pitch 250...350mm
Counterslats 50x50 on the rafters Diffuse waterproofing membrane
120g/m2 Rafters 160x50 pitch 800mm
Composition I
BENEFICIARY:
Cahul City Hall
Composition II
Composition III
Cement-sand mortar leveling screed M100 - 50mm
No. 055984 from 08.09.17
License Series A MMII
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2
"Licurici" in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086
SRL "PROJECT-DESIGN"
yl
III
SECTION 4 - 4 DESIGN SC.1:100
ResumeL1 N and
D
pl. 17
C
pl. 16
A
pl. 16
Sm2
B C
11/20
11/20
6,600
0.000
6,800
10-12/20 - 2 - Sat
-0.600
2,100
7,600
10,30010,060
-1,600
5,400
-1,850
0.000 -0.400
3,300
Limbas S.
GSPublisherVersion 0.49.100.100
Finishing the ceiling
ON
Mesh glue
Prepared Prepelita A.
Glue for fixing polystyrene
Vapor barrier - ruberoid on bituminous mastic
Klinker brick cladding
Cyclopean concrete
Thermal insulation from extruded polystyrene - 80mm
Mesh glue
BLOCK "B"
Mesh glue
Fiberglass net
A.ÿ.P.
BLOCK "A"
Existing precast concrete slab floor - 160 mm Flat Phase
Vertical linochrome waterproofing - 1 layer
Thermal insulation with cementoplast Ø200 h=150 mm
- it is a solution for thermal insulation of the attic
Plastic dowels for fixing polystyrene
Mineral wool thermal insulation - 50mm
Interior plaster
Section 4-4 projected
Fiberglass net
2. 3
Mesh glue
Bitumen-based primer boards
Decorative plaster
Plastic dowels for fixing polystyrene Adhesives for fixing polystyrene Cement-based plaster
Limestone blocks M.35 on mortar M.50 Interior plaster
Mode. part no. Sheet No. doc. Signal. Date.
1 100
1 100
1 560
1 100
9 0
1 700
40 45
Limbas S.
45°
Mode. part no. Sheet No. doc. Signal. Date.
License Series A MMII
No. 055984 from 08.09.17
10-12/20 - 2 - Sat
11/20
11/20
1 - 1 m3 m3
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2
"Licurici" in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086
All wood
50°
GOST 8486-86
Sash BLOCK "B"
6.65
Prepared Prepelita A.
variable
8.50
GOST 8486-86
ON
variable
Sash
2. 3
8.80
GOST 8486-86
Attic L1. Details
3 030
0.02
10.00
Sash
GOST 8486-86
0.05
Total dormer wood (L1) 1 pieces
Door
0.03
50°
Slat (garnish)
0.01
3 030 boards
A.ÿ.P.
Flat Phase
45° mm4
GSPublisherVersion 0.49.100.100 fascia
RIDGE
SCALE 1:20
WALL GLASS
mourning
BENEFICIARY:
Cahul City Hall
LOFT L1
ml VolumeName dimensions, BORDEROU SKYLIGHT (L1)
0.10
IndicationPos.
0.10
SRL "PROJECT-DESIGN"
ventilation duct
(150) variable variable
Rafter 150x50 6
-4x40 on the sealing perimeter3 step 500mm
5 6 variable
-4x40 pitch 250mm
Date.Mode. part no. Sheet No. doc. Signal.
2. 3
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2
"Licurici" in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086
Scale 1:20 Execution detail of the ventilation channel
10-12/20 - 2 - SatBENEFICIARY:
Cahul City Hall
GSPublisherVersion 0.49.100.100
Node C
6,460 variable
6,600
No. 055984 from 08.09.17
License Series A MMII
SRL "PROJECT-DESIGN"
14- Dropper
22- Thermal insulation
2- Galvanized profile
6- Diffuse membrane
25- Protective railing
2- Existing belt
12- Sort gutter
20- The new belt
NOTES:
10- Self-tapping screw
5- Galvanized sheet
8- Slat 100x30 mm
17- Mane
15- Burlan
23- Sandrama covered with corrugated sheet
3- Bituminous cardboard
3- Wooden bars 50x60mm
5- Deer
21- Vapor barrier
13- Gutter
1- Metal corner
NOTES:
19 - Existing precast concrete slab
1- Existing parapet/ Existing wall
11- The snow guard
9- Metal tile
18- Mane element
6- Mineral wool
24- Board casing
4- Galvanized metal plate
4- Grooved 150x100mm
16- Thermal insulation
7- Plywood 50x50 mm
Limbas S.
11/20
11/20
20° two hundred
Flat Phase
2. 3
Nodes A, B, C. Execution detail of the ventilation channel
BLOCK "B"
Prepared Prepelita A.
A.ÿ.P.
boards
16ON
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2
"Licurici" in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086
SRL "PROJECT-DESIGN"
h=100mm
11/20
11/20
PVC - profile 5 chambers, 2 layers of glass, with ventilation
6 36
5. It is important to determine who is responsible for protecting the installed windows against possible damage until the time of reception. It is recommended to agree with the beneficiary on taking individual measures, for example, on protection in case of removing the excess foam. When carrying out masonry repairs, the profiles must be covered.
800×800
Material
BENEFICIARY:
Cahul City Hall mark
F1 and
2. In case of installation at temperatures below 5 degrees Celsius, the specific properties of the materials used will be taken into account. Direct hits on the profile frame and on the wings will be avoided. 3. For all profiles, the protective film must be removed immediately after assembly.
1. The windows must be mounted horizontally, perpendicularly, and according to the measurements.
opening elements.
Schematic of the element yl
PVC - profile 5 chambers, 2 layers of glass, with ventilation
F2
4 36
NoteThe amount
4. Residues left on the profile will be removed immediately after the foam has hardened.
1800×2000
F3
Deviations from this request must be agreed in writing.
-1,600
Empty dimensions, LxH mm
4 11
NOTE: Details for compositions I and II see pl. 13-14.
PVC - profile 5 chambers, 2 layers of glass, with ventilation
2000×2000
6. After finishing the assembly, the functionality of everything will be checked and verified in writing
Joinery borderou (windows)
10-12/20 - 2 - Sat
General installation instructions
Limbas S.
Mode. part no. Sheet No. doc. Date.Signal.
1 800
GSPublisherVersion 0.49.100.100
ON 2. 3
BLOCK "B"
Flat Phase
Prepared Prepelita A.
boards
A.ÿ.P.
Node D. Borderou carpentry (windows) No. 055984 from 08.09.17
License Series A MMII
(fraction 20-40) existing
10 -12 /20 - 2 - SA
Limbas S.
GSPublisherVersion 0.49.100.100
BENEFICIARY:
Cahul City Hall
Flat Phase
BLOCK "B"
boards
Prepared Prepelita A.
A.ÿ.P.
18ON 2. 3
Rules for fixing windows License Series A MMII
No. 055984 from 08.09.17
Mode. part no. Sheet No. doc. Signal. Date.
SRL "PROJECT-DESIGN"
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2
"Licurici" in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086
11/20
11/20
A
B
B A
View A
View B
Limbas S.
20 30 20
Welding height h=6mm two hundred
1 200
Hole Ø10
BENEFICIARY:
Cahul City Hall
ON 2. 3
Guard rail Bp-1
Flat Phase
BLOCK "B"
Prepared Prepelita A.
A.ÿ.P.
boards
1-1
A
Signal. Date.Mode. part no. Sheet No. doc.
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2
"Licurici" in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086
Guard rail BP-1 ml ml ml
10-12/20 - 2 - Sat
GSPublisherVersion 0.49.100.100
1 1.21
Item
Ø 16 AI GOST 2590-71*
l=1370
47.00
United
Table.
Ø 14 AI GOST 2590-71*
The amount
2.16
Remarks
Guard rail
The element's name
SRL "PROJECT-DESIGN"
License Series A MMII
No. 055984 from 08.09.17
Border of protective railing elements
11/20
11/20
-0.600
6,000
5. Details of L1 attic see pl.15.
10,060
0.700
2,700
10,400
2,700
3. Mealic scales Sm1 are existing and restored.
10,300
1. Details on ventilation ducts see pl. 16.
1,900
4,000
10,300 10,400
5,200
6,000 6,100 5,676
9,825
2. Brand new PVC windows.
4. Details of metal ladders Sm2 and Sm3 see compartment "C".
0.700
2,700
10,060 i=20°
BENEFICIARY:
Cahul City Hall
10,400
4,000
6,000
SRL "PROJECT-DESIGN"
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2
"Licurici" in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086
11/20
11/20
F2
F3
Resume
BP1
F2
L2
BLOCK
i=25°
F3
BP1
Sm2
F1
FACADE IN AC AXES - DESIGNED SC.1: 100
Sm1
F2
BP1
F1
F3
U1
Resume
Resume
L1 trough
F2
F3 pipe
BLOCK
F2
Sm 1
Note:
Sm2
L1
F2
FACADE IN AXES 1b-3b - DESIGN SC.1: 100
A 3b1b
C
Limbas S.
10-12/20 - 2 - Sat
12,500
13,000
GSPublisherVersion 0.49.100.100
BLOCK "B"
2. 320
Flat Phase
Facades between axes 1b-3b; CA designed
A.ÿ.P.
ON
boards
Prepared Prepelita A.
No. 055984 from 08.09.17
License Series A MMII
1 600
Date.Mode. part no. Sheet No. doc. Signal.
10,060
4,000
13,000
10,300
4,000
0.700
3,300
10-12/20 - 2 - Sat
6,050
2,700
6 100
10,400
6,400
10,40010,300
2,700
6,000
10,400
6,000
2,700
0.700
12,500
0.000
-0.650
6,100
No. 055984 from 08.09.17
License Series A MMII
Date.Mode. part no. Sheet No. doc. Signal.
SRL "PROJECT-DESIGN"
F1 i=20°
BLOCK
Note:
i=25°
BLOCK
BP1
Resume
FACADE IN AC AXES - DESIGNED SC.1: 100
trough
BLOCK A
pipe
FACADE IN AXES 3b-1b - DESIGN SC.1: 100
F1
BP1
BP1
Sm1
BLOCK A
Resume
L1 Resume
Sm2
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2
"Licurici" in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086
11/20
11/20
THAT
1b
A 2b3b
Limbas S.
GSPublisherVersion 0.49.100.100
3. Mealic scales Sm1 are existing and restored.
1. Details on ventilation ducts see pl. 16.
0.000
2,900
BENEFICIARY:
Cahul City Hall
2. Brand new PVC windows.
4. Details of metal ladders Sm2 and Sm3 see compartment "C".
-0.900
6,200
5. Details of L1 attic see pl.15.
boards
2. 3
Facades between AC axes; 3b-1b designed
Flat Phase
ON
A.ÿ.P.
Prepared Prepelita A.
BLOCK "B"
- Plywood from tiles and tiles.
10-12/20 - 2 - Sat
Preparatory operations:
- Cement mortar plasters
- Smoothed plasters:
GSPublisherVersion 0.49.100.100
Flat Phase
ON
A.ÿ.P.
General instructions for finishing work - start boards
Prepared Prepelita A.
BLOCK "B"
2. 3
License Series A MMII
No. 055984 from 08.09.17
General instructions for finishing works
Date.Mode. part no. Sheet No. doc. Signal.
SRL "PROJECT-DESIGN"
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2
"Licurici" in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086
11/20
11/20
The application of the smoothing trowel will be done with trowel trowel, in layers of 1 mm thickness or using and those with the following irregularities:
that the plating is performed to be protected from the action of atmospheric precipitation;
them under pressure.
The flatness of the surface of the blade will be checked, using the metal ruler.
The installation of the plywood will be done with tiles or tiles with adhesive paste as specified
The materials can only be introduced into the work if it has been verified in advance by the site management that they were delivered with certificates of conformity, which confirm that they comply with the respective norms.
The work will not start until the works already executed (the floor) are satisfactorily protected.
Before starting the tiling works, a surface inspection will be made of what is to be tiled. Work will not begin until any irregularities found have been rectified (vertical and horizontal deviations, as well as possible defects or apparent degradation).
paint available for walls and ceilings).
the other finishing works as follows:
Before starting the cladding works, the following operations will be performed: -removal of possible mortar remains, dust, grease stains, etc. - the masonry joints
(horizontal and vertical) must be thoroughly cleaned to a depth of about 1 cm, BENEFICIARY:
Cahul City Hall
*Large dents (up to max. 3 mm) and deep scratches formed during chipping, on the coating layer.
The tiles will have the following physical-chemical characteristics: - water absorption coefficient: max. 18% for tiles and max. 2.5% for tiles. - when testing resistance to fine cracking, the samples will not show any such cracking; - during the chemical resistance test, the finish (glaze) will remain undamaged.
- Plastering of ceilings and non-cladding surfaces, in the rooms where cladding will be done.
- Execution of cold floors (cast mosaic, mosaic tiles, tiles, marble, etc.).
Any existing cracks in the masonry will be injected with cement milk to restore continuity.
Any local irregularities will not exceed 10 mm (bumps or depressions).
The smoothing will be done manually, with a trowel (the trowel steel).
aspect can be checked at any time, after the completion of the entire object.
- The specified execution technology was not respected, which led to damage to the works.
- It does not comply with the indications provided in the project regarding the thickness, layout, coverage, flatness, non-formity (as processing), the connecting edges of the walls with the ceiling, the jambs, the edges of the door or window openings, spalls.
the producer (designer).
- Installation of window frames and door frames and linings, except for window sills
The obtained surface must be perfectly smooth to the touch, any asperities will be cleaned and smoothed with fine glass paper. For the surfaces of the walls made of bca blocks, with thin joints of 2-3 mm, apply the smoothing putty based on sand and fine sand with a composition of 1:2:0.5 (sand sand DP 25; fine sand 0.2 mm; water) in volumes.
Installation of dowels or devices for fixing sanitary objects, any holes the manual or electric painting device, or the plastering gun.
The thickness of the screed layer of 1-3 mm is obtained through two or three successive applications and leveling.
The screed layer will be executed by spreading and smoothing the paste with the screed steel, on surfaces of max.
1 m in order to be able to achieve the smoothing before the paste hardens.
so that the fixing mortar adheres as well as possible to these surfaces.
- The envelope of the building, with the execution of the leaks in the solution will be defined, so that the surfaces on
During the work, it is necessary to check if the execution technology is respected, the use of the type and composition of the mortar, as well as the application of successive layers without exceeding the maximum thicknesses.
Measures will be taken against too fast drying (wind, sunshine), washing by rain or frost.
The tiles will not have dark spots with an area larger than max. 1.5 mm2 at max. 2% of the sample, cracks in the glaze, thickening of the glaze or insufficiently glazed areas, "ice cream" or crystalline appearance and rough areas.
Before starting any tiling operations with tiles or tiles, they will be executed
The grout will be provided as a support layer for the realization of superior quality finishes (ex.: paints with
- Installation of sanitary, electrical and heating pipes buried under plywood and testing
- The execution of warm floors (parquet, PVC, etc.) that degrade at high humidity, will be done only after installing the tile.
Works that do not comply with the provisions of these specifications will be classified as defective, such as
If these deviations are exceeded, the surface will be straightened by completing with
Defects that do not allow the following defects:
*Swellings, dents, pinches (lime shots), stains, efflorescence, cracks, cracks, missing window frames, window sills, plinths, technical-sanitary objects.
Considering that the plasters are works intended to remain visible, their quality from the point of view of
The verification of the quality of the support on which the plaster is applied is done during the verification of the execution of this support. It is absolutely forbidden to apply the plaster over a support that has not been received according to the specific instructions. Before the execution of the plasters, it is necessary to check whether all the works designed to protect them or works that, through subsequent execution, would cause damage to the plasters have been received: coverings, floors, balconies, installations, carpentry on the frame, etc. It will be checked if all the parts necessary for each carpentry or installations have been installed once the supports have been executed.
It is absolutely necessary to reduce the general humidity of the building, which negatively influences its structure.
they will mount after the execution of the plywood.
subsequent ones to be given only with the drill.
The application of tiles or sandstone will be done only on dry surfaces, prepared in advance and which fall within deviations from flatness between 3 mm/ m vertically and 2 mm/ m horizontally.
mortar or putty. The thickness of the mortar layer should not exceed 1-2 cm.
- It does not respect the verticality and horizontality of the surface and edges, the flatness of the plastered surface.
- Painters and painters.
Painters and painters being works intended to remain visible, their quality from the point of view of appearance can be checked at any time, even after the completion of the entire objective, and consequently it is not necessary to conclude minutes of hidden works.
10-12/20 - 2 - Sat
SRL "PROJECT-DESIGN"
Mode. part no. Sheet No. doc. Signal. Date.
11/20
11/20
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2
"Licurici" in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086
GSPublisherVersion 0.49.100.100
Limbas S.
- The plywood must have a uniform color over the entire surface; tone differences are not allowed between the mounted panels, nor within the same panel; dirt stains, visible places with defective enamel, etc. are not allowed.
- After finishing the drawing operations, you can proceed to the execution of the plywood application in the next one
The site manager must check all materials before they are introduced into the work.
through rain or frost.
- The installation of the boards will be done by applying the mortar or adhesive paste with a trowel on the back of the board, as the case may be, and applying the boards by pressing them on the support layer.
During the execution of the works, it is necessary to check the execution technology, provided in the technical prescriptions, the use of the recipes and the composition of the indicated mixtures, as well as the application of successive layers in the order and at the prescribed time intervals.
- The surface of the plywood will be checked with a 1.20 m ruler, and at most one wave with an arrow will be allowed
It is forbidden to start the execution of any painting, painting or wallpapering work, before the support has been carefully checked by the site managers, regarding the fulfillment of the quality conditions of the support layer.
* Failure to respect the continuity and dimensions of the joints in the two directions.
- The following will be considered defects that must be repaired locally or completely: *Non-compliance with these specifications.
The marking will be done with a wooden straightedge of a maximum length of 2 m and with the help of repenes made of pieces of tiles or sandstone provisionally fixed with plaster mortar on the respective surface of the plaster, in the immediate vicinity of the surface to be tiled. The lead wire, left in front of the markers, must represent the line of the plywood surface to be executed.
After this operation, the joints will be filled with white cement paste, if not specified otherwise, at a time interval of 6-8 hours after finishing the execution of the plywood on the entire surface of the respective room.
- Placing the boards will start from the floor level, taking care to match the joints of the floor with those of the plywood if not specified otherwise and correlating the plywood (perfectly adjusted horizontally) with the floor whose level can be tilted.
At the preliminary reception, the same checks are carried out directly by the commission, but with a frequency of at least 1/5 of the previous frequency.
- It is checked every time with the right hand.
- During the warm season, the surfaces exposed to the sun will be covered with sackcloth sheets in strips or sheets that will be permanently moistened for 2 days.
BENEFICIARY:
Cahul City Hall
- Allowed deviations for the finished surfaces will be +/- 2 mm below the 1.20 m long rectangle.
Checking the quality of the paints and varnishes is done only after their complete drying and has the main purpose of detecting defects that exceed the permissible deviations in order to carry out repairs and eliminate the possibility that these defects will be repeated in the future.
cracks in the plates, separation of the plates from the support layer, stains, etc.
glazed, or corner profiles.
sequence of operations.
The materials must be delivered with a certificate of conformity to confirm that they are
The following measures will be taken to protect the plywood works: - The spaces in which the tile or sandstone veneers were executed will be closed and kept like this until the work is completely dry.
- The rows of boards must be regular, with continuous or alternate rectilinear joints, wide
The application of protective measures against sudden drying (wind, sunlight), washing will be followed of maximum 2 mm.
*Applying to the edges of the walls or pillars some normal boards and not the special boards with the edge
The execution of cladding works will be carried out in compliance with the following requirements:
After placing each row of tiles, the excess mortar will be cleaned and poured into the remaining voids
The verification of the quality of the support on which the paints and varnishes are applied is done within the verification of the execution of this support (plasters, masonry, concrete, grouts, carpentry elements, installations).
Before starting painting works, it is necessary for painters to check whether all works intended to protect them (students) or whose subsequent execution could cause their damage (installation pipes, carpentry) have been executed and received, as well as whether they have been all auxiliary parts installed: (dowels, brackets, supports for sanitary objects or heating elements).
corresponding to the respective norms.
The receipt verification of the works is carried out as follows:
*Faulty positioning of the boards with deviations from the vertical and horizontal.
The checks that are carried out during the verification of a work phase are done at least one for each room and at least one for every 100 square meters.
The drawing of the surfaces to be tiled will be done both horizontally and vertically.
- Wet tiles will not be used for cladding.
After approx. 5-6 hours after finishing the plywood, the joints between the boards will be cleaned by rubbing.
*Damage to the plywood resulting from inadequate protection of the works until reception:
- Tiles or sandstone tiles will be cleaned of dust and impurities, they will be kept in water for 10-15 minutes before the start of tiling and then they will be drained from the water for 5-10 minutes.
behind the boards, cement milk.
- The plywood will be protected from damage until the work is received.
uniform and well filled with white cement milk.
License Series A MMII
No. 055984 from 08.09.17
ON
A.ÿ.P.
BLOCK "B"
boards
Prepared Prepelita A.
General instructions for finishing work - end
2. 3 2. 3
Flat Phase
SRL,,PROJECT-DESIGN''
Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Kindergarten /Nursery No. 2 "Licurie" Municipality of
License series A MMII
No. subject: 10-12/20
Beneficiary: Cahul City Hall
No. 055984 of 08.09.17
Chisinau 2020
Department: Organization of construction works - OLC
Website - Proiectmd.com.
Address: Chisinau municipality, 49 Alexandru cel Bun str.
Email: proiectmd001@mail.md, Tel. 067677606.
GSPublisherVersion 0.49.100.100
Execution project
In cases of road crossings by temporary pipes or cables, they will be
Free access will be ensured to all buildings under construction and those under construction, including temporary ones. The construction of the road and the access to the building under construction must be completed before the foundation works start.
The following documents were used to develop the "OLC" construction work organization project norms:
1. Norms and rules in construction "Organization of production in construction" СНиП 3.01-85;
2. The designer's guide "Organization of construction works";
3. СНиП III-4-80* "Work safety in construction". The administration of the construction unit is obliged to provide the workers with overalls and shoes of appropriate sizes, as well as with means of individual protection, corresponding to the specifics of the workplace.
About the performance of repair works, or about the temporary closure of roads, a
ORGANIZATION OF CONSTRUCTION WORKS
No. 098/1 of 04.12.2020 ISP: Para V. Certificate series 2019-P no. 0264 of 26.06.2019
BENEFICIARY:
Cahul City Hall
General data They served as initial data for the development of the construction site organization project
Placards with inscriptions and warnings will be installed in all construction sectors, on machinery and equipment, on access roads and in any other place where this is required.
The total term of the execution works will be carried out within 6 months.
Builders are obliged to strictly comply with fire safety requirements at all stages of construction, starting with preparatory work, in accordance with the "Rules of fire safety when carrying out construction-assembly works".
LIST OF EXECUTION DRAWINGS IN THE COMPARTMENT
the location of the fire hydrant.
LABOR PROTECTION
FIRE SAFETY
Characterization of the designed construction:
The construction land is located in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086.
On that lot, capital repair of the frame-type roof with thermal insulation is expected the ceiling, thermal insulation and finishing of the facades of the Crèche - Kindergarten No. 2 "Licurici" building.
The designed object constitutes a combined construction:
- Constructive scheme: Frame filled with bearing masonry;
- Foundations - continuous from FS prefabricated blocks with t=400mm;
- Longitudinal and transversal load-bearing walls made of small M35 limestone blocks on M50 cement mortar;
- Partition walls - Small M35 limestone blocks on M50 mortar with t=200mm and brick with t=120mm in sanitary groups;
- Plansee - from prefabricated boards with holes with t=220mm;
- The existing roof - wooden Sarpanta type with slate sheets.
- The new roof - wooden Sarpanta type with metal tile covering.
Basing the methods of carrying out the main works
1. Site preparation works
- installation of the temporary protective fence (during construction);
- demolition of existing buildings;
- installation of temporary drinking and technological water supply pipes (fire protection);
2. Concreting works
3. The concrete will be brought to the construction site with special concrete mixers and will be unloaded within the reach of a concrete pump. For the compaction of freshly poured concrete, the compaction vibrator a concrete IV-47.
- All heavy work, for formwork and reinforcement casings, will be carried out with the help of truck cranes.
- All constructions made of concrete and reinforced concrete will be carried out in accordance with the requirements of NCM F.02-2006 and related technology books.
4. Construction-assembly works
- The construction-assembly work and lifting to other levels will be carried out with the help of the car crane and with the help of special machinery and equipment.
5. Peculiarities of carrying out works in winter conditions.
- Construction-assembly work at the average daily temperature below +5°C and at the average temperature on day below 0° C, to be carried out in accordance with "Instructions for carrying out work during the winter" (ВСН-150-179).
The rules for storing and keeping easily flammable and explosive materials will be followed.
and free for access and entry to them and illuminated at night.
Urban certificate
During the construction, manufacture and operation of temporary electrical installations and the site electrical network, the requirements indicated in the "Rules for the manufacture of electrical devices" and in the "Rules of safety techniques for the operation of electrical devices in industrial enterprises" must be observed.
Design task project Project documentation Expert report 155/19.09.2020 executed by Technical Expert: Dohmilÿ Iurii certificate no. 035 of 22.06.2020.
For the needs of the construction works, the existing water and sewage networks on the territory of the construction site will be used.
Blocking accesses, passages, entrances and exits from the building, as well as access paths to the inventory
Safety in terms of labor protection includes measures taken to ensure the safety technique, the sanitary-epidemiological situation and the fire-fighting situation. In order to prevent accidents, construction-assembly works must be carried out in strict accordance with ÿÿÿÿ III-4-80* "Work safety in construction". The organization of work with the necessary equipment is elaborated in the technological books and falls under the competence of the project of execution of the works, according to ÿÿÿÿ 3.01.03-85.
On the construction site, a fire-fighting board will be installed with the necessary inventory and an indicator of and fire fighting equipment, hydrant and means of communication are prohibited.
crossings or access roads must be urgently notified to the Local Authorities.
All accesses, roads, fire hydrants must be in good working order protected with decks or temporary bypass.
The execution works will be carried out in stages (roof, facade, landscaping).
ASP: Limbas S. Certificate series 2019-P no. 0195 of 11.04.2019
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2 "Licurici" in the municipality of Cahul, str. Ion Luca Caragiale
no. 12, no. cadastral 1701114.086 Capital repair of the frame roof and facades of Kindergarten No. 2 "Licurici"
GSPublisherVersion 0.49.100.100
Prepared Prepelita A.
boards
I.ÿ.P. Para V.
ONA.ÿ.P. Limbas S.
Flat Phase
General data
11/20
11/20
11/20
10-12/20 - OLC
Date.Signal.Mode. part no. Sheet No. doc.
SRL "PROJECT-DESIGN"
General data
Exhibit
Construction work organization plan. Construction site temporary fencing scheme. List of materials for temporary constructions.
General indications
Instructions for the execution of works on the site (end)
Notes
Instructions for the execution of works on the site (start)
The name
License Series A MMII
No. 055984 from 08.09.17
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2 "Licurici" in the municipality of Cahul, str. Ion Luca Caragiale
no. 12, no. cadastral 1701114.086 Capital repair of the frame roof and facades of Kindergarten No. 2 "Licurici"
2A.ÿ.P. ON
Construction work organization plan
Para V.
Flat Phase
Prepared Prepelita A.
Limbas S.
boards
I.ÿ.P.
10-12/20 - OLC
CONSTRUCTION WORK ORGANIZATION PLAN SC.1:500
Ion Luca Caragiale str 1
Fire panel
Information panel
A - resistance and stability;
Well for concrete
Senior Construction Specialist:
CONVENTIONAL SIGNS
C - fire safety;
Site illuminator
Para V.
No. 098/1 of 04.12.2020
E - thermal insulation, water repellency and energy saving;
Give way indicator
Temporary fencing
Principal specialist architect:
ISP: Para V. Certificate series 2019-P no. 0264 of 26.06.2019
Existing fence
BENEFICIARY:
Cahul City Hall
Concrete
Limbas S.
The project is developed in compliance with the documents in force and ensures the level of quality corresponding to the essential requirements:
Transformer
NOTES
B - operational safety;
ASP: Limbas S. Certificate series 2019-P no. 0195 of 11.04.2019
Urban certificate
D - hygiene and people's health;
F - protection against noise;
p p
11/20
11/20
11/20
REPRESENTED
Date.Mode. part no. Sheet No. doc. Signal.
License Series A MMII
No. 055984 from 08.09.17
SRL "PROJECT-DESIGN"
No.
NOTESEXPLANATION
BORDERO OF TEMPORARY BUILDINGS AND CONSTRUCTIONS
Completed construction
Room for site supervisors and workers Room for tools and equipment Fire panel
Organic toilet Storage of limestone and sand blocks Well for concrete
Place wheel wash
Site entrance
Scheme of temporary construction site fencing. List of materials for temporary constructions.
Major repair of the frame roof with thermal insulation of the ceiling, thermal insulation and finishing of the facades of the Creÿei building - Kindergarten No. 2 "Licurici" in the municipality of Cahul, str. Ion Luca Caragiale no. 12, no. cadastral 1701114.086 Capital repair of the frame roof and facades of Kindergarten No. 2 "Licurici" boards
ON
Flat Phase
THE POSITION
Prepared Prepelita A.
A.ÿ.P.
NOTES
Para V.
EXPLANATION
I.ÿ.P.
Scheme of temporary construction site fencing. List of materials for temporary constructions.
HA
FIRE HYDRANT SCHEME
4. The indicator is installed on the temporary fence of the construction site or on the pole
Steel pipe (Ø 200 mm)
Metal profile fence h=2000 mm
Letters according to GOST 10807-78. The hydrant number inscription is applied in orange or dark pink with fluorescent enamel AC-564 (TU6-10-722-74);
unity
8 Sandbox
Sand
Flame extinguisher
Fire hydrant
NOTES
1. The fire hydrant indicator (IHA) is made of 1.5 mm thick metal sheet; 2. The surface of the sheet is painted with nitro enamel 3 times; 3. The inscription is applied on the painted surface of the sheet with in color 3 times.
Gate in 2 wings ml ml
Axe
EXPLANATION OF THE FIRE PROTECTION PANEL
Row
THE NAME
Ø 50
THE AMOUNT
8.00
Pole Ø 150 mm unity temporary temporary temporaryFire panel
DIAGRAM OF THE FIRE PROTECTION PANEL
Canga with curling iron
Crowbar
No.
8.00
LIST OF MATERIALS FOR TEMPORARY CONSTRUCTION
2 ... 2.5 m high;
6 temporary temporary
Gate (opening 4000 mm)
BENEFICIARY:
Cahul City Hall
Asbestos pee
9 Container with water (min 200 L) crushed stone
Boiler
10-12/20 - OLC
p
UNIT
TO MEASURE
Signal.Mode. part no. Sheet No. doc. Date.
11/20
11/20
11/20
0.9
2.46
SRL "PROJECT-DESIGN"
units m3 m3
1.8
1.44
No. 055984 from 08.09.17
License Series A MMII
Kindergarten No. 2 "Licurici" in the municipality of Cahul, str. Ion Luca Caragiale
no. 12, no. cadastral 1701114.086 Capital repair of the frame roof and facades of Kindergarten No. 2 "Licurici"
SRL "PROJECT-DESIGN"
10-12/20 - OLC
11/20
11/20
11/20
In all production, administrative, storage and auxiliary rooms, in visible places
The fuel supply of the roof units must be carried out in a special place,
- the ventilation of the room where the heat-producing installations are installed must ensure a triple exchange of air.
1 m, fenced on both sides with railings, with a height of at least 1.1 m, with a continuous lining below the brush with a height of 0.15 m from the platform and with an additional fencing strip at a height of 0.5 m.
their organization, in order to prevent work accidents and occupational diseases. When performing work at height in the lower part, below the workplace, it is necessary to mark the dangerous areas.
These deformations must be rectified daily.
It is not allowed to store fuel for fueling aggregates and packaging on the roof.
in rolls must not exceed what is needed for a single work shift.
All types of paints and varnishes prepared and diluted in separate rooms next to the wall
Installation work of building elements with combustible thermal insulation or use
New means of mechanization, leased or after capital repair, are admitted for operation only after the technical review and verification by the responsible person.
technical specifications issued by the manufacturing plant; - the burners must work stably without the flame breaking out and without their bursting into site preparation and organization work, necessary to ensure the security of the construction process, including:
The access roads, the sidewalks of the production territories, as well as the work areas, the places of
At the entrance to the construction site, plans must be installed (displayed), in which the buildings and installations under construction, the entrances, the access ways, the location of the water sources, the…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .