N3319121R9001 Amend 0001 Jinja.pdf
PDF 203 KB Posted
- Attached to
- D-B Construct Storage Facility, Jinja, Uganda
- Solicitation number
- N3319121R9001
About this file
This document is an amendment to a solicitation for the construction of a storage facility in Jinja, Uganda. The Navy is seeking to construct an open bay storage building with environmental controls to maintain temperatures between 15-30 degrees Celsius and relative humidity of 15-95%. The amendment provides responses to contractor questions, clarifying that experience of teaming partners may be used to meet requirements, wooden or plastic pallets can be accommodated, and fire detection and suppression systems are to meet specifications outlined in the Performance Technical Specification. Additionally, payment clauses have been added specifying the use of WAWF for electronic submission of payment requests and receiving reports in accordance with DFARS 252.232-7003 and 252.232-7006.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N3319121R9001 Amend 0002.pdf | ||
| N3319121R9001 Jinja Attach 5 - 252.229-7001.docx | DOCX document | |
| N3319121R9001 Jinjaa Attach 6 - Data Sheet.docx | DOCX document | |
| N3319121R9001 Jinjaa Attach 7 - Safety Checklist.docx | DOCX document | |
| N3319121R9001 Jinja RFP.pdf | ||
| N3319121R9001 Jinja Attach 1 - PTS.pdf | ||
| N3319121R9001 Jinja Attach 8 - PPQ.docx | DOCX document | |
| N3319121R9001 Jinja Attach 2 - PPI.docx | DOCX document | |
| N3319121R9001 Jinja Attach 4 - 52.204-26.docx | DOCX document | |
| N3319121R9001 Jinja Attach 3 - Price Schedule.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
N3319121R9001 D-B Construct Storage Facility, Jinja, Uganda
See Page 2 for description of amendment.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 9
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 10-Dec-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N3319121R9001
X 9B. DATED (SEE ITEM 11)
23-Nov-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
10-Dec-2020
CODE
NAVFAC EUROPE AFRICA CENTRAL
VIALE PORTO CAPODICHINO
NAPOLI 80144
N33191 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N3319121R9001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
The purpose of this amendment to the solicitation is to respond to the Pre-Proposal Inquiries and add payment clauses.
PRE-PROPOSAL INQUIRY 001
Section 00100 - Bidding Schedule/Instructions to Bidders Pg 7 : I. (5) (2) (i) # 3
As a U.S Prime that has a teaming agreement with a local Ugandan Subcontractor (that has extensive construction experience in Uganda), can the experience of our local teaming subcontractor be used to meet the requirements “Performed in the country of Uganda within the last 10 years of the date this RFP was issued”?
PRE-PROPOSAL RESPONSE 001
Yes.
Refer to Page 8, “The offeror may utilize experience of a subcontractor that will perform major or critical aspects of the requirement to demonstrate construction experience under this evaluation factor. The Offeror must provide a letter of commitment and an explanation of the subcontractor’s role in the performance of this contract.”
PRE-PROPOSAL INQUIRY 002
Section 00100 - Bidding Schedule/Instructions to Bidders Pg 7 : I. (5) (2) (i) # 4
Can a U.S Prime that has a teaming agreement with a local Subcontractor use the experience of the local subcontractor to the meet the past performance requirement: “Similar in magnitude with a value of at least $500,000” ?
PRE-PROPOSAL RESPONSE 002
Yes.
Refer to Page 8, “The offeror may utilize experience of a subcontractor that will perform major or critical aspects of the requirement to demonstrate construction experience under this evaluation factor. The Offeror must provide a letter of commitment and an explanation of the subcontractor’s role in the performance of this contract.”
PRE-PROPOSAL INQUIRY 003
The RFP states that the Past Performance citations MUST be for work done in Uganda. We are currently doing significant construction in Togo, Benin, and Guinea under our prime contract with GPOI. We also have done water purification systems installation under the APRRP. We were made award of this opportunity by the GPOI program office. Our construction has remained on schedule throughout the Covid lockdowns and we have complete confidence we can execute your project without issue even with Covid issues.
Will the government consider allowing Past Performance from other African countries in the region in lieu of only Uganda construction past performance?
PRE-PROPOSAL RESPONSE 003
No, the requirement remains unchanged.
PRE-PROPOSAL INQUIRY 004
Do you consider wooden pallets or plastic pallets?
PRE-PROPOSAL RESPONSE 004
This project construction and scope shall be designed for use for both wooden pallets and plastic pallets.
PRE-PROPOSAL INQUIRY 005
Do you require firefighting systems such as fire extinguishers, fire hydrants, fire hose reels?
PRE-PROPOSAL RESPONSE 005
The fire fighting systems are noted in the PTS:
PTS Part 5 Room Minimum Requirements indicated smoke detectors as well as break glass unit fire alarm notification for each of the rooms listed in that section.
PTS Part 7 Engineering System Requirements Section D40 Fire Protection provides the fire system requirements: Provide integrated fire alarm system capable of notifying building occupants of any fire that may start inside the facility. Provide wall mounted multi-purpose fire-extinguishers throughout the facility.
D4010 Fire Alarm and Detection System Provide a complete, electrically supervised, manual, and automatic, annunciated fire alarm and detection system throughout the facility. Provide integrated systems capable of notifying building occupants by means of tone and strobes. The fire reporting portion of the system must be consistent with the existing UPDF base fire reporting system.
Provide a complete and useable fire alarm system including manual stations, system smoke detectors, audio/visual alarms, and fire alarm radio transmitter back to the UPDF primary base.
Provide surface mounted manual pull stations.
PRE-PROPOSAL INQUIRY 006
What are the dimension and the weights of the pallets? Please provide the dimensions A, B, C, D, E (as showed below) and on which side will the pallet be handled by forklift.
PRE-PROPOSAL RESPONSE 006
Storage shelves shall be designed for material on shipping pallets. Pallet dimensions are estimated at:
A - 40 inches / 1.016 m / 1016 mm Depth B - 48 inches / 1.219 m / 1219 mm Width C - 40 inches / 1.016 m / 1016 mm Height D - 40 inches / 1.016 m / 1016 mm Depth E - 48 inches / 1.219 m / 1219 mm Width
Either side A or B shall be handled by forklift.
The max weight to be handled by any single pallet is 238.5 KG
PRE-PROPOSAL INQUIRY 007
Do you require any special storing conditions (salt storage, Chemical storage, special food requirements)?
PRE-PROPOSAL RESPONSE 007
No special storage conditions are required other than stated in the Performance Technical Specification
(PTS).
Per PTS Part 1 Project Description Section 1.2 Scope of Project Open Bay Storage Environmental HVAC controls to maintain the space at temperature range between 15 – 30 degrees Celsius and Relative Humidity of 15-95%.
PRE-PROPOSAL INQUIRY 008
For electrical source of the building, do we have to connect only to the existing network, or we must provide alternate source such as generator or solar system.
PRE-PROPOSAL RESPONSE 008
The electrical source of the building shall be only to the existing network. No new alternative source such as a generator or solar power system is required.
Connection to existing electrical network shall be per proper local Ugandan utility codes and requirements.
SECTION 00700 - CONTRACT CLAUSES
The following have been added by full text:
252.232-7003 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS AND RECEIVING REPORTS (DEC 2018)
(a) Definitions. As used in this clause--
Contract financing payment means an authorized Government disbursement of monies to a contractor prior to acceptance of supplies or services by the Government.
(1) Contract financing payments include--
(i) Advance payments;
(ii) Performance-based payments;
(iii) Commercial advance and interim payments;
(iv) Progress payments based on cost under the clause at Federal Acquisition Regulation (FAR) 52.232-16, Progress Payments;
(v) Progress payments based on a percentage or stage of completion (see FAR 32.102(e)), except those made under the clause at FAR 52.232-5, Payments Under Fixed-Price Construction Contracts, or the clause at FAR 52.232-10, Payments Under Fixed-Price Architect-Engineer Contracts; and
(vi) Interim payments under a cost reimbursement contract, except for a cost reimbursement contract for services when Alternate I of the clause at FAR 52.232-25, Prompt Payment, is used.
(2) Contract financing payments do not include--
(i) Invoice payments;
(ii) Payments for partial deliveries; or
(iii) Lease and rental payments.
Electronic form means any automated system that transmits information electronically from the initiating system to affected systems.
Invoice payment means a Government disbursement of monies to a contractor under a contract or other authorization for supplies or services accepted by the Government.
(1) Invoice payments include--
(i) Payments for partial deliveries that have been accepted by the Government;
(ii) Final cost or fee payments where amounts owed have been settled between the Government and the contractor;
(iii) For purposes of subpart 32.9 only, all payments made under the clause at 52.232-5, Payments Under Fixed- Price Construction Contracts, and the clause at 52.232-10, Payments Under Fixed-Price
Architect-Engineer Contracts; and
(iv) Interim payments under a cost-reimbursement contract for services when Alternate I of the clause at 52.232-25, Prompt Payment, is used.
(2) Invoice payments do not include contract financing payments.
Payment request means any request for contract financing payment or invoice payment submitted by the Contractor under this contract or task or delivery order.
Receiving report means the data prepared in the manner and to the extent required by Appendix F, Material Inspection and Receiving Report, of the Defense Federal Acquisition Regulation Supplement.
(b) Except as provided in paragraph (d) of this clause, the Contractor shall submit payment requests and receiving reports in electronic form using Wide Area WorkFlow (WAWF). The Contractor shall prepare and furnish to the Government a receiving report at the time of each delivery of supplies or services under this contract or task or delivery order.
(c) Submit payment requests and receiving reports to WAWF in one of the following electronic formats:
(1) Electronic Data Interchange.
(2) Secure File Transfer Protocol.
(3) Direct input through the WAWF website.
(d) The Contractor may submit a payment request and receiving report using methods other than WAWF only when-
(1) The Contractor has requested permission in writing to do so, and the Contracting Officer has provided instructions for a temporary alternative method of submission of payment requests and receiving reports in the contract administration data section of this contract or task or delivery order;
(2) DoD makes payment for commercial transportation services provided under a Government rate tender or a contract for transportation services using a DoD-approved electronic third party payment system or other exempted vendor payment/invoicing system (e.g., PowerTrack, Transportation Financial Management System, and Cargo and Billing System);
(3) DoD makes payment on a contract or task or delivery order for rendered health care services using the TRICARE Encounter Data System; or
(4) The Governmentwide commercial purchase card is used as the method of payment, in which case submission of only the receiving report in WAWF is required.
(e) Information regarding WAWF is available at https://wawf.eb.mil/.
(f) In addition to the requirements of this clause, the Contractor shall meet the requirements of the appropriate payment clauses in this contract when submitting payment requests.
(End of clause)
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (DEC 2018)
(a) Definitions. As used in this clause—
“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.
“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.
“Payment request” and “receiving report” are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232- 7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall—
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:
(1) Document type. The Contractor shall submit payment requests using the following document type(s):
(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.
(ii) For fixed price line items—
(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.
(Contracting Officer: Insert applicable invoice and receiving report document type(s) for fixed price line items that require shipment of a deliverable.)
(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.
(Contracting Officer: Insert either “Invoice 2in1” or the applicable invoice and receiving report document type(s) for fixed price line items for services.)
(iii) For customary progress payments based on costs incurred, submit a progress payment request.
(iv) For performance based payments, submit a performance based payment request.
(v) For commercial item financing, submit a commercial item financing request.
(2) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.
[Note: The Contractor may use a WAWF “combo” document type to create some combinations of invoice and receiving report in one step.]
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table*
Field Name in WAWF Data to be entered in WAWF
Pay Official DoDAAC ____
Issue By DoDAAC ____
Admin DoDAAC** ____
Inspect By DoDAAC ____
Ship To Code ____
Ship From Code ____
Mark For Code ____
Service Approver (DoDAAC) ____
Service Acceptor (DoDAAC) ____
Accept at Other DoDAAC ____
LPO DoDAAC ____
DCAA Auditor DoDAAC ____
Other DoDAAC(s) ____
(*Contracting Officer: Insert applicable DoDAAC information. If multiple ship to/acceptance locations apply, insert “See Schedule” or “Not applicable.”)
(**Contracting Officer: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42.302(a)(13).)
(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.
(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.
(g) WAWF point of contact.
(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity’s WAWF point of contact.
(Contracting Officer: Insert applicable information or “Not applicable.”)
(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.
(End of clause)
(End of Summary of Changes)