N33191-18-R-1600 Pre-Proposal Inquiry (PPI) Log
PPI #PPI QuestionGovernment Response
1Reference: 2.2 NON-PRICE EVALUATION (Non-Price/Technical Proposal), Projects submitted for the Offeror shall be completed within the past five (5) years of the date of issuance of this solicitation.
Given the economic situation that Spain has had in the past 5 years, would the government consider projects at 70% complete in lieu of having to have been complete within the past five (5) years of the date of issuance of this solicitation? Only the past two years have larger projects been awarded in Spain as the country emerges from a severe economic crisis.No. Submitted projects must be 100% complete.
2As per Factor 1.Experience page 20 of 45 from the RFP.

Project completed by the offeror in any capacity other than a prime contractor will be considered unacceptable and not evaluated. However although the prime contractor does not have selfperforming of significant features must demonstrate that it has managed projects that included these features.

Due to the specialization of this project we understand that it should be acceptable if prime contractors with experience in projects management could submit completed relevant projects but utilizing experience information of a specialized subcontractor. In this kind of project is essential to focus on a good management and coordination of especialized subcontractors in this kind of utilities.We really appreciate if prime contractors could submit experience of a specialized subcontractor provided that the prime contractor has experience in project management and hold updated the certification of classification required under the

Solicitation.Subcontractor work experience will not be considered, unless the Offeror was the prime contractor on that work/project.
327 21 10.00 40 / Drawing C501 – Detail D3 - Fiber optic in PVC conduit

What is the diameter of the PVC conduit?

Refer to the Project Drawings, General Notes on Sheets ET101, ET102, ET103, which states:

103mm (4") Schedule 80 PVC conduit with 3 cell fiber inner duct.

4 33 11 00 / 40 05 13 Drawing C601 – Restrained Length, Start and Stop

As indicated on number 4 of general notes “See sheet C601 for restrained joint placement and required restrained lengths”. The information provided in the tables are just lengths and coordinates of start and stop of the restrainers. Please provide details of construction of the restrainers.

. Refer to the Project Specifications, Section 33 11 00, Paragraph 2.2.3 Pipe Anchorage, which states:

2.2.3 Pipe Anchorage

Provide pipe anchorage designed for a minimum working pressure of 2.4 MPa and in accordance with BSI BS ISO 10804. Provide restrained joints or restraint devices with gripper wedges incorporated into a follower gland and specifically designed for the pipe material and meeting the requirements of EN 681 or metal harness for PVC pipe joints.

5 Drawings ET102 and ET103 depicts the fiber optic connection between buildings 603 and 3201. However, Note 2 in drawings ET102 and ET103 states: “Install new 103 mm2 PVC conduit with 3 cell fiber inner duct between building 3236 and building 1968. Conduit to be schedule 80.

Note 4 in drawing ET102 and ET103 states: “Install 0S2 single mode, 24 strand, fiber-optic cable and terminate at patch panels in bldg 3236 and 1968.

Please, confirm:

- The features of the conduit and the fiber optic cable to be installed between bldg 603 and bldg 3201

- Whether, in addition to the connections depicted in the drawings, any other connection has to be done between bldgs 603/3201 and bldgs 3236/1968 Conduit shall be 103, schedule 80, PVC conduit with 3 cell fiber inner duct.

Cable shall be OS2, single mode, 24 strand, fiber-optic.

Connections for fiber-optic only need to be made between bldgs. 603 and 3201 and between bldgs. 3236 and 1968. No other fiber connections are required.