26R6111 QA_0002.pdf
PDF 167 KB Posted
- Attached to
- TUGCON; OPEN-OCEAN TOW
- Solicitation number
- N3220526R6111
About this file
This document is a Questions and Answers clarification notice issued by Military Sealift Command (MSC) on 02 July 2026 for RFP N3220526R6111 regarding a tug contract opportunity. The Q&A addresses five inquiries from potential offerors and provides clarifications that do not constitute amendments to the solicitation.
The responses clarify that Parts X and XI of the RFP are reserved and not applicable, with references to these sections to be updated in the Proforma. Regarding small business requirements, MSC confirms that per FAR 52.219-14(e)(1), small business primes and similarly situated small business subcontractors must perform at least 50 percent of the service portion, with large business subcontractors acceptable for limited portions provided overall team compliance is maintained. For the limitation on subcontracting calculation, fuel must be included in the firm fixed-price lump sum and is not reimbursable, while other reimbursable items such as pass-through marine operating costs are subject to Part III(z) for Reimbursable Supplies and Services (Charters) and should not be included in the firm fixed price or demurrage. MSC notes that if no technically acceptable small business proposals are received, the Government will consider re-opening the solicitation as full and open competition.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 26R6111 A0001_RFP.pdf | ||
| 26R6111 QA_0001.pdf | ||
| 2015-0213 Rev. 40.pdf | ||
| 26R6111 RFP.pdf | ||
| 26R6111 Shipyard Data Template.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY SEALIFT COMMAND
N3220526R6111
QUESTIONS AND ANSWERS
02 July 2026
The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.
1. QUESTION: Can MSC clarify that Part(s) X & IX are both RESERVED and therefore N/A from this RFP? The Proforma listed on MSC's website for a Tug Contract does not include those sections but they are included by reference in the RFP. Please advise.
ANSWER: Parts X and XI are both RESERVED and not applicable to this RFP and TUGCON Proforma. References of Part X and XI in the RFP will be updated to the appropriate Proforma sections.
2. QUESTION: Does the Government expect the small business prime, together with any similarly situated small business subcontractors, to perform at least 50% of the service portion of the requirement?
ANSWER: Per FAR 52.219-14(e)(1): By submission of an offer and execution of a contract, the Contractor agrees that in performance of a contract assigned a North American Industry Classification System (NAICS) code for—
(1) Services (except construction), it will not pay more than 50 percent of the amount paid by the Government for contract performance to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded.
3. QUESTION: Would the use of a large business subcontractor for a limited portion of the vessel/asset support be acceptable, provided the overall team remains compliant with the limitation on subcontracting requirements?
ANSWER: Per FAR 52.219-14(e)(1): By submission of an offer and execution of a contract, the Contractor agrees that in performance of a contract assigned a North American Industry Classification System (NAICS) code for—
(1) Services (except construction), it will not pay more than 50 percent of the amount paid by the Government for contract performance to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded.
4. QUESTION: For purposes of the limitation on subcontracting calculation, how should reimbursable items such as fuel or other pass-through marine operating costs be treated?
ANSWER: Fuel must be included in the offeror’s firm fixed-price lump sum and is not reimbursable. Other reimbursable items will be subject to Part III(z) Reimbursable Supplies and Services, (Charters) and should not be included in the offeror’s firm fixed price lump sum or demurrage.
5. QUESTION: If the market does not appear to have sufficient small business sources capable of performing the primary vessel/ROV scope while remaining compliant, would the Government consider revisiting the set-aside determination or issuing additional guidance?
ANSWER: If there are no technically acceptable small businesses proposals, the Government will consider re-opening the solicitation as full and open competition.