This is a pricing template for vessel charter services under RFP N3220526R0014. The attachment establishes the basic daily pricing structure that offerors must use to submit cost proposals for a Jones Act-qualified U.S.-flag host ship to be based in Pearl Harbor, Hawaii, for Naval Special Warfare operations. The template covers a base period and four option periods, with the base period and options 1-3 calculated on a 365-day year (option 4 on 335 days), requiring offerors to itemize daily costs across multiple categories: crew-related expenses (lines 1-8, including wages, training, victualling, transportation, and other crew costs totaling $0); vessel costs (lines 9-18, including maintenance, lubricants, surveys, equipment, capitalized costs, depreciation, and other vessel costs totaling $0); insurance costs (lines 19-26, including protection and indemnity, hull and machinery, and other insurance totaling $0); general and administrative expenses; and profit. The final line item calculates the daily rate by dividing total annual costs by days assumed on-hire per year, accounting for off-hire days.
The template also includes a separate fuel consumption data section requiring offerors to specify barrels per day of fuel consumption across four operational categories: fuel underway (laden), fuel underway (ballast), auxiliaries underway, and idle fuel periods, with an estimated total of 1,978 days of performance across the base period and all options. Offerors must select from three fuel types—MGO/MDO, IFO-180, or IFO-380—and consumption data must align with Special-Time boxes 68-71 and be reflective of 60 degrees Fahrenheit conditions. The government will convert barrel consumption to metric tons using specified conversion factors and apply Defense Logistics Agency-Energy (DLA-E) standard prices: MGO/MDO at $1,500.83 per metric ton, IFO-180 at $964.80 per metric ton, and IFO-380 at $956.21 per metric ton, with all pricing in U.S. dollars.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Period
| Attachment (06) | Vessel: | ||
| Basic Pricing Data | RFP: N3220526R0014 | ||
| Unless otherwise specified by the offeror, the price and profit identified below will be assumed | |||
| (a) allocable to the services of the Vessels under this Charter | |||
| (b) in US dollars | |||
| (c) based upon a 365-day year | |||
| Base Period | |||
| PRICE PER DAY | |||
| 1 | Crew wages, etc., as itemized in Attachment C | ||
| 2 | Crew Training, not separately itemized in Attachment C | ||
| 3 | Victualling, stores, and water | ||
| 4 | Crew transportation/repatriation | ||
| 5 | Other crew costs (itemize at lines 5-7) | ||
| 6 | |||
| 7 | |||
| 8 | Total crew-related expenses (lines 1-7 above) | $ - 0 | |
| 9 | Maintenance and repair | ||
| 10 | Lubricants | ||
| 11 | Survey and classification expenses | ||
| 12 | Equipment and materials | ||
| 13 | Capitalized costs (Vessel) | ||
| 14 | Depreciation (Vessel) | ||
| 15 | Other Vessel costs (itemize at lines 15-17) | ||
| 16 | |||
| 17 | |||
| 18 | Total Vessel costs (lines 9-17 above) | $ - 0 | |
| 19 | Protection and indemnity premia | ||
| 20 | Protection and indemnity deductibles paid | ||
| 21 | Hull and machinery premia | ||
| 22 | Hull and machinery deductibles paid | ||
| 23 | Other insurance costs (itemize at lines 23-25) | ||
| 24 | |||
| 25 | |||
| 26 | Total insurance costs (lines 19-25 above) | $ - 0 | |
| 27 | Other (itemize at lines 27-30) | ||
| 28 | |||
| 29 | |||
| 30 | |||
| 31 | General and administrative expenses | ||
| 32 | Profit |
33 Total daily costs from above multiplied by 365 $ - 0
34 Days assumed off-hire per year
35 Line 33 divided by the number of days assumed on-hire per year $ - 0
Option 1
| Attachment (06) | Vessel: | ||
| Basic Pricing Data | RFP: N3220526R0014 | ||
| Unless otherwise specified by the offeror, the price and profit identified below will be assumed | |||
| (a) allocable to the services of the Vessels under this Charter | |||
| (b) in US dollars | |||
| (c) based upon a 366-day year | |||
| Option Period One | |||
| PRICE PER DAY | |||
| 1 | Crew wages, etc., as itemized in Attachment C | ||
| 2 | Crew Training, not separately itemized in Attachment C | ||
| 3 | Victualling, stores, and water | ||
| 4 | Crew transportation/repatriation | ||
| 5 | Other crew costs (itemize at lines 5-7) | ||
| 6 | |||
| 7 | |||
| 8 | Total crew-related expenses (lines 1-7 above) | $ - 0 | |
| 9 | Maintenance and repair | ||
| 10 | Lubricants | ||
| 11 | Survey and classification expenses | ||
| 12 | Equipment and materials | ||
| 13 | Capitalized costs (Vessel) | ||
| 14 | Depreciation (Vessel) | ||
| 15 | Other Vessel costs (itemize at lines 15-17) | ||
| 16 | |||
| 17 | |||
| 18 | Total Vessel costs (lines 9-17 above) | $ - 0 | |
| 19 | Protection and indemnity premia | ||
| 20 | Protection and indemnity deductibles paid | ||
| 21 | Hull and machinery premia | ||
| 22 | Hull and machinery deductibles paid | ||
| 23 | Other insurance costs (itemize at lines 23-25) | ||
| 24 | |||
| 25 | |||
| 26 | Total insurance costs (lines 19-25 above) | $ - 0 | |
| 27 | Other (itemize at lines 27-30) | ||
| 28 | |||
| 29 | |||
| 30 | |||
| 31 | General and administrative expenses | ||
| 32 | Profit |
33 Total daily costs from above multiplied by 366 $ - 0
34 Days assumed off-hire per year
35 Line 33 divided by the number of days assumed on-hire per year $ - 0
Option 2
| Attachment (06) | Vessel: | ||
| Basic Pricing Data | RFP: N3220526R0014 | ||
| Unless otherwise specified by the offeror, the price and profit identified below will be assumed | |||
| (a) allocable to the services of the Vessels under this Charter | |||
| (b) in US dollars | |||
| (c) based upon a 365-day year | |||
| Option Period Two | |||
| PRICE PER DAY | |||
| 1 | Crew wages, etc., as itemized in Attachment C | ||
| 2 | Crew Training, not separately itemized in Attachment C | ||
| 3 | Victualling, stores, and water | ||
| 4 | Crew transportation/repatriation | ||
| 5 | Other crew costs (itemize at lines 5-7) | ||
| 6 | |||
| 7 | |||
| 8 | Total crew-related expenses (lines 1-7 above) | $ - 0 | |
| 9 | Maintenance and repair | ||
| 10 | Lubricants | ||
| 11 | Survey and classification expenses | ||
| 12 | Equipment and materials | ||
| 13 | Capitalized costs (Vessel) | ||
| 14 | Depreciation (Vessel) | ||
| 15 | Other Vessel costs (itemize at lines 15-17) | ||
| 16 | |||
| 17 | |||
| 18 | Total Vessel costs (lines 9-17 above) | $ - 0 | |
| 19 | Protection and indemnity premia | ||
| 20 | Protection and indemnity deductibles paid | ||
| 21 | Hull and machinery premia | ||
| 22 | Hull and machinery deductibles paid | ||
| 23 | Other insurance costs (itemize at lines 23-25) | ||
| 24 | |||
| 25 | |||
| 26 | Total insurance costs (lines 19-25 above) | $ - 0 | |
| 27 | Other (itemize at lines 27-30) | ||
| 28 | |||
| 29 | |||
| 30 | |||
| 31 | General and administrative expenses | ||
| 32 | Profit |
33 Total daily costs from above multiplied by 365 $ - 0
34 Days assumed off-hire per year
35 Line 33 divided by the number of days assumed on-hire per year $ - 0
Option 3
| Attachment (06) | Vessel: | ||
| Basic Pricing Data | RFP: N3220526R0014 | ||
| Unless otherwise specified by the offeror, the price and profit identified below will be assumed | |||
| (a) allocable to the services of the Vessels under this Charter | |||
| (b) in US dollars | |||
| (c) based upon a 365-day year | |||
| Option Period Three | |||
| PRICE PER DAY | |||
| 1 | Crew wages, etc., as itemized in Attachment C | ||
| 2 | Crew Training, not separately itemized in Attachment C | ||
| 3 | Victualling, stores, and water | ||
| 4 | Crew transportation/repatriation | ||
| 5 | Other crew costs (itemize at lines 5-7) | ||
| 6 | |||
| 7 | |||
| 8 | Total crew-related expenses (lines 1-7 above) | $ - 0 | |
| 9 | Maintenance and repair | ||
| 10 | Lubricants | ||
| 11 | Survey and classification expenses | ||
| 12 | Equipment and materials | ||
| 13 | Capitalized costs (Vessel) | ||
| 14 | Depreciation (Vessel) | ||
| 15 | Other Vessel costs (itemize at lines 15-17) | ||
| 16 | |||
| 17 | |||
| 18 | Total Vessel costs (lines 9-17 above) | $ - 0 | |
| 19 | Protection and indemnity premia | ||
| 20 | Protection and indemnity deductibles paid | ||
| 21 | Hull and machinery premia | ||
| 22 | Hull and machinery deductibles paid | ||
| 23 | Other insurance costs (itemize at lines 23-25) | ||
| 24 | |||
| 25 | |||
| 26 | Total insurance costs (lines 19-25 above) | $ - 0 | |
| 27 | Other (itemize at lines 27-30) | ||
| 28 | |||
| 29 | |||
| 30 | |||
| 31 | General and administrative expenses | ||
| 32 | Profit |
33 Total daily costs from above multiplied by 365 $ - 0
34 Days assumed off-hire per year
35 Line 33 divided by the number of days assumed on-hire per year $ - 0
Option 4
| Attachment (06) | Vessel: | ||
| Basic Pricing Data | RFP: N3220526R0014 | ||
| Unless otherwise specified by the offeror, the price and profit identified below will be assumed | |||
| (a) allocable to the services of the Vessels under this Charter | |||
| (b) in US dollars | |||
| (c) based upon a 335-day year | |||
| Option Period Four | |||
| PRICE PER DAY | |||
| 1 | Crew wages, etc., as itemized in Attachment C | ||
| 2 | Crew Training, not separately itemized in Attachment C | ||
| 3 | Victualling, stores, and water | ||
| 4 | Crew transportation/repatriation | ||
| 5 | Other crew costs (itemize at lines 5-7) | ||
| 6 | |||
| 7 | |||
| 8 | Total crew-related expenses (lines 1-7 above) | $ - 0 | |
| 9 | Maintenance and repair | ||
| 10 | Lubricants | ||
| 11 | Survey and classification expenses | ||
| 12 | Equipment and materials | ||
| 13 | Capitalized costs (Vessel) | ||
| 14 | Depreciation (Vessel) | ||
| 15 | Other Vessel costs (itemize at lines 15-17) | ||
| 16 | |||
| 17 | |||
| 18 | Total Vessel costs (lines 9-17 above) | $ - 0 | |
| 19 | Protection and indemnity premia | ||
| 20 | Protection and indemnity deductibles paid | ||
| 21 | Hull and machinery premia | ||
| 22 | Hull and machinery deductibles paid | ||
| 23 | Other insurance costs (itemize at lines 23-25) | ||
| 24 | |||
| 25 | |||
| 26 | Total insurance costs (lines 19-25 above) | $ - 0 | |
| 27 | Other (itemize at lines 27-30) | ||
| 28 | |||
| 29 | |||
| 30 | |||
| 31 | General and administrative expenses | ||
| 32 | Profit |
33 Total daily costs from above multiplied by 335 $ - 0
34 Days assumed off-hire per year
35 Line 33 divided by the number of days assumed on-hire per year $ - 0
Fuel Consumption Data
| Attachment (06) | Vessel: |
| Fuel Consumption Data | RFP: N3220526R0014 |
| Offeror Instructions: Fill in the "barrels/day" used by the vessel proposed, as applicable. Offerors are required to select a fuel type from the below DLA-E fuel table below. Consumption in barrels shall match the Boxes 68-71 of the Special-Time and be reflective of 60 Degrees Farenheit. |
| Special-Time Box # | Special-Time Box Description | Consumption of Barrels/Day | Fuel Type | # Days of Performance |
| 68 | Fuel Underway (laden) | 593 | ||
| 69 | Fuel Underway (ballast) | |||
| 70 | Auxiliaries underway | |||
| 71 | Idle Fuel Period | 1385 |
| Notes: | |
| The total number of days include the base period and all options to include the FAR 52.217-8 Option to Extend Services. | |
| The number of days in the box above are considered estimates and shall not form the basis of a future claim. | |
| The Government's fuel consumption calculations will be made using metric tons as the unit of measure. The below table will be used to convert barrels to metric tons. | |
| Conversion Factors for Barrels to Metric Tons | |
| MGO/MDO: | 7.507 barrels per metric ton |
| IFO-180: | 6.526 barrels per metric ton |
| IFO-380: | 6.468 barrels per metric ton |
| The price per metric ton will be based on the following Defense Logisitics Agency - Energy (DLA-E) Standard Prices as indicated in the below table. | ||
| Defense Logistics Agency - Energy (DLA-E) Standard Prices | ||
| MGO/MDO: | per metric ton | $ 1,500.83 |
| IFO-180: | per metric ton | $ 964.80 |
| IFO-380: | per metric ton | $ 956.21 |