Q AND A Responses 1.pdf

PDF 120 KB Posted

Attached to
USNS PUERTO RICO (T-EPF 11) POST SHAKEDOWN AVAILABILITY/DRYDOCK
Solicitation number
N3220520R4088
Issued by

About this file

This document contains questions and answers regarding solicitation number N3220520R4088 for the USNS PUERTO RICO (T-EPF 11) Post Shakedown Availability/Drydock opportunity with the Department of the Navy Military Sealift Command. Key details include clarification that work item 114 is for replacement of a grease interceptor rather than installation of BERPs as originally specified. For work item 108, offerors should assume up to 400 square feet of minor pitting to fill and up to 10,000 linear feet of structure requiring grinding. For work item 120, the OEM will provide materials and tooling per paragraph 3.0 but the contractor may coordinate with the OEM for commonly available items. Non-OEM representatives require proof of authorization for work on Kelvion equipment under work item 201. Replacement hoses under work item 512 are to be CFM rather than GFM. A reference error is corrected for work item 903. And an amendment will be issued regarding changes to work item 090 for daily COVID prevention.

View the file

Other files

File Type Posted
USNS PUERTO RICO N3220520R4088 solicitation(updated).pdf PDF
USNS PUERTO RICO N3220520R4088 Solicitation(updated).pdf PDF
Q AND A Responses 6.pdf PDF
N3220520R4088 Amendment 0006.pdf PDF
J - 2 CAT A ITEMS USNS PUERTO RICO 20R4088.xlsx XLSX spreadsheet
J - 1 Work Item Index USNS PUERTO RICO 20R4088.docx DOCX document
N3220520R4088 Amendment 0005.pdf PDF
Q AND A Responses 5.pdf PDF
N3220520R4088 Amendment 0004.pdf PDF
Q AND A Responses 4.docx DOCX document
N3220520R4088 Amendment 0003.pdf PDF
N3220520R4088 Amendment 0002.pdf PDF
Q AND A Responses 3.docx DOCX document
N3220520R4088 Amendment 0001.pdf PDF
Q AND A Responses 2.pdf PDF
J - 7 MSC Ship Repair Facility Survey - PUERTO RICO 20R4088.docx DOCX document
J - 12 Past Performance Data - PUERTO RICO 20R4088.doc DOC document
J - 11 Dry Dock Evaluation Form - PUERTO RICO 20R4088.docx DOCX document
J - 14 Technical Data Non-Disclosure - PUERTO RICO 20R4088.docx DOCX document
J - 1 Work Item Index USNS PUERTO RICO 20R4088.docx DOCX document
J - 9 Disclosure of Lobbying Activities - PUERTO RICO 20R4088.doc DOC document
J - 8 Request for Spec Clarification - PUERTO RICO 20R4088.doc DOC document
J - 6 CDRLs USNS PUERTO RICO PSA.zip ZIP file
J - 2 CAT A ITEMS USNS PUERTO RICO 20R4088.xlsx XLSX spreadsheet
J - 3 CAT B ITEMS USNS PUERTO RICO 20R4088.xls XLS spreadsheet
USNS PUERTO RICO PSADD N3220520R4088 Solicitation.pdf PDF
J - 10 Interport Differential - PUERTO RICO 20R4088.doc DOC document
J - 4 GFP Listing.xlsx XLSX spreadsheet
J - 13 Past Performance Questionnaire - PUERTO RICO 20R4088.docx DOCX document
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MILITARY SEALIFT COMMAND

N3220520R4088

QUESTIONS AND ANSWERS 1

The following are answers to questions received from potential offerors. The answers provide clarification only and DO

NOT constitute an amendment to the solicitation.

QUESTION #1:

SPECIFICATION ITEM NO.: 114

PARAGRAPH / SECTION NO: N/A

TITLE: Title Incorrect

Title of work item is for Grease Interceptor, but the item is installation of new BERPs. Please clarify if item is correct.

ANSWER:

Incorrect work item provided. WI 114 revised for replacement of Grease Interceptor.

QUESTION #2:

SPECIFICATION ITEM NO.: 108

PARAGRAPH / SECTION NO: Multiple

TITLE: Bilge Coating

7.1.7.1: How much pitting is anticipated to need filling?

7.2.1: How many linear feet of grinding is to be priced?

7.1.7.1: For bidding purposes, assume up to 400 sqft of minor pitting to be filled using Belzona 1111.

7.2.1: For bidding purposes, assume up to 10,000 linear feet of structure will require grinding.

QUESTION #3:

SPECIFICATION ITEM NO.: 120

PARAGRAPH / SECTION NO: 3.3

TITLE: HMS

Is the contractor to perform this part of the install or is it being performed by the manufacturer?

The OEM is to provide all materials and tooling listed in para 3.0. However, the contractor may choose to coordinate with the

OEM to provide commonly available materials and tooling.

QUESTION #4:

SPECIFICATION ITEM NO.: 201

TITLE: Heat Exchangers

Will non-OEM equivalents be accepted to perform this work?

Non-OEM authorized representatives may be used in lieu of OEM Kelvion. However, proof of OEM authorization to perform maintenance on Kelvion equipment must be provided as part of the proposal for subcontractor evaluation and approval.

QUESTION #5:

SPECIFICATION ITEM NO.: 512

PARAGRAPH / SECTION NO: 4.2

TITLE: Stern Ramp Hose Renewal

Paragraph 4.2 states that hoses are to be GFM, but paragraph 7.2 refers to the hoses as CFM.

Replacement stern ramp hoses to be provided as CFM.

QUESTION #6:

SPECIFICATION ITEM NO.: 903

PARAGRAPH / SECTION NO: 3.2.1

TITLE: Reference missing

Paragraph references 2.7, but the item only has references 2.1-2.6. Please clarify if reference is missing.

Paragraph 3.2.1 should read “Painting systems are described in reference 2.6.”

QUESTION #7:

SPECIFICATION ITEM NO.: 090

TITLE: Daily COVID Prevention

Item delivered on 7/22/20 is significantly different from the original item provided with the solicitation. To properly incorporate this new version of the item, we are required by the contract documents, to have an amendment directing to do

so. Please provide an amendment directing us which version of this item to use.

Yes, that is correct. An amendment to the solicitation will be provided to update the changed work item and it will be posted publicly to beta.sam.gov.