This document is a solicitation for the Post Award Shakedown Availability (PSA) on the USNS MIGUEL KEITH (T-ESB - 5) issued by the Department of the Navy Military Sealift Command - Norfolk contracting office. Interested contractors must complete a non-disclosure agreement by August 3, 2020 in order to receive the work item package, drawings, and references for the PSA which is expected to commence on or about August 3, 2020 and last 120 calendar days. The solicitation seeks proposals/bids for Category A and B work items to prepare for and accomplish the PSA in accordance with the specifications. Pricing terms include fixed unit prices for various services under CLIN 0001 and fully burdened labor rates for additional government requirements and other direct costs under CLIN 0002.
View the file
Other files
Show 40 more
Latest 50 of 58 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N3220520R4037
Section B - Supplies or Services and Prices
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Category "A" Work Items (WIs)
FFP
Prepare for and accomplish the Post Shakedown Availability of the USNS MIGUEL KEITH (T-ESB 5) Total Category "A" WIs $_____________
Proposed unit price per KWh $_____ in accordance with (IAW) WI 011, 7.1.1.4
Proposed unit price per gallon of potable water $______ IAW WI 011, 7.1.2.2
Proposed unit price per gallon of distilled water $______ IAW WI 011, 7.1.3.2
Proposed unit price per gallon of bilge water removal $______ IAW WI 011, 7.1.20.3
Proposed unit price per crane usage $______ IAW WI 11, 7.9.1
Proposed Hazardous Waste handling fee rate IAW WI 023, 7.5.1 ______%
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0001AA
Category "A" Work Items (WIs)
USNS MIGUEL KEITH (T-ESB-5) MSC AND PMS 385 GENERAL REQUIREMENTS FUNDED CAT A WIs CAT A WORK ITEMS 010, 011, 012, 013, 014, 015, 016, 017, 018, 019, 020, 021, 022, 023
FOB: Destination J999
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0001AB
MSC Category "A" Work Items (WIs)
USNS MIGUEL KEITH (T-ESB-5) PSA MSC GENERAL REQUIREMENTS FUNDED CAT A WIs CAT A WORK ITEMS 101, 102, 103, 104, 105, 201, 301, 302, 303, 304, 401, 402, 403, 404, 405, 408, 409, 501, 502, 503, 504, 505, 506, 507, 508, 509, 510, 511, 512, 513, 514, 518, 522, 523, 524, 525, 601, 602, 603, 604, 605, 606, 607, 609, 610, 801, 802
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0001AC
PMS-385 Category "A" Work Items (WIs)
USNS MIGUEL KEITH (T-ESB-5) PSA PMS-385 NEW CONSTRUCTION FUNDED CAT A WIs CAT A WORK ITEMS 305, 306, 406, 407, 515, 516, 517, 519, 520, 521, 608, 611, 612, 613, 614, 615
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0001AD
PMS-385 Category "A" Work Items (WIs)
USNS MIGUEL KEITH (T-ESB-5) PSA PMS-385 POST DELIVERY FUNDED CAT A WIs
CAT A WORK ITEMS 144, 320, 528, 597, 820, 821
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0001AE
PMS-385 Category "A" Work Items (WIs)
USNS MIGUEL KEITH (T-ESB-5) PSA OPN FUNDED CAT A WIs
CAT A WORK ITEMS 434
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
AGR AND ODC
USNS MIGUEL KEITH (T-ESB-5) PSA MSC FUNDED ADDITIONAL GOVERNMENT REQUIREMENTS (AGR) AND OTHER DIRECT COSTS
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0002AA
MSC AGR AND ODC
MSC AGR
(21,502) man-hours @ $________ per man-hour = $_____________
ODC
Base $693,480.00_____________
Proposed G&A Rate _______________% Subtotal: $_____________
Proposed Profit Rate _______________% Subtotal: $____
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0002AB
PMS 385 NC AGR AND ODC
PMS 385 NEW CONSTRUCTION AGR
(19,487) man-hours @ $________ per man-hour = $_____________
ODC
Base $1,060,955.00_____________
Proposed G&A Rate _______________% Subtotal: $_____________
Proposed Profit Rate _______________% Subtotal: $
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0002AC
PMS 385 PD AGR AND ODC
PMS 385 POST DELIVERY AGR
(3,820) man-hours @ $________ per man-hour = $_____________
ODC
Base $167,000.00_____________
Proposed G&A Rate _______________% Subtotal: $_____________
Proposed Profit Rate _______________% Subtotal: $
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
0002AD
PMS 385 SEA GIRAFFE AGR AND ODC
PMS 385 SEA GIRAFFE AGR
(140) man-hours @ $________ per man-hour = $_____________
ODC
Base $2,000.00_____________
Proposed G&A Rate _______________% Subtotal: $_____________
Proposed Profit Rate _______________% Subtotal: $
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| OPTION |
| Category "B" WI 0025 |
FFP
WI 0025 - Physical Security at Private Contractor's Facility in FPCON Charlie - Delta
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| OPTION |
| Category "B" WI 0030 |
FFP
WI 0030 - Continuation of Services
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| OPTION |
| Category "B" WI 0370 |
FFP
WI 0370 - SOF LAN Drops (TALT TESB 19-050)
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| OPTION |
| Category "B" WI 0410 |
FFP
WI 0410 - ECDIS Install in Master's Dayroom (TALT TESB 15-009)
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| OPTION |
| Category "B" WI 0616 |
FFP
WI 0616 - Galley Shelving Install (T-ALT T-ESB 17-002)
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| OPTION |
| Category "B" WI 0617 |
FFP
WI 0617 - MILCREW Space Conversion for Barber Shop (T-ALT T-ESB 18-011)
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| OPTION |
| Category "B" WI 0618 |
FFP
WI 0618 - Enlisted Messdecks (A4-90-0) Table/Seating Modifications (TALT TESB 19-043)
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| OPTION |
| Category "B" WI 0619 |
FFP
WI 0619 - CPO/SNCO Mess (A4-90-3) Table/Seating Modifications (TALT TESB 19-044)
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| OPTION |
| Category "B" WI 0620 |
FFP
WI 0620 - Officer’s Mess/Wardroom (A4-90-1) Table/Seating Modifications (TALT TESB 19-045)
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| OPTION |
| Category "B" WI 0632 |
FFP
WI 0632 - Repair Non-Skid Coatings
Category B WIs are optional WIs and not required to be accomplished as part of this contract as awarded. The KO may require the contractor to perform the requirements of the optional Category B WIs by exercising the option via written notice to the contractor.
NET AMT
CLAUSES INCORPORATED BY FULL TEXT
TOTAL PROPOSED PRICE FOR CLINS 0001 THROUGH 0012 $______________
The contractor shall enter the total proposed price of all CLINs.
PART I - THE SCHEDULE
Section B, Price Schedule, detailed information
CLIN 0001 –Attachment J-2 – Category “A” WIs provides a WI breakdown of CLIN 0001 pricing.
CLIN 0002: This CLIN contains the FBLR (e.g., G&A, overhead, profit, supervision, consumables, and/or support functions, etc.) and the ODC profit and G&A rate. These rates are used for pricing changes negotiated under the H-3 Clause - AGR and H-4 Clause ODC, for the duration of the contract. Changes are inherent to vessel repair contracts and should be expected by the Contractors. Additionally, this CLIN includes G&A and profit rates for ODC to be used for negotiating changes. These rates shall prevail even when the contract is extended/modified. The number of AGR man-hours and the ODC base amount are estimates that were generated for evaluation purposes. The actual amounts of man-hours and ODC may be used interchangeably under the contract which could result in a distribution and amount of man-hours and ODC that is either higher or lower than that stated in CLIN 0002. Any additional AGR or ODC required beyond the CLIN 0002 estimated amount shall be added through contract modification using the same AGR and ODC rates agreed upon at contract award. Any unused AGR or ODC will be de-obligated from the contract at the same AGR and ODC rates agreed upon at contract award. The contractor agrees that the number of man-hours included in its proposed price for such AGR shall include only direct production man-hours. For these purposes, direct production man-hours are for skilled labor at the Journeyman level expended in direct production as exemplified by the following functions:
| Abrasive cleaning/blasting | Tank cleaning | ||
| Welding | Machinists (inside and outside) | ||
| Burning | Brazing | ||
| Carpentry | Electrical work | ||
| Electronic work | Shipfitting | ||
| Lagging | Painting | ||
| Boilermaking | Pipefitting | ||
| Sheetmetal work | Engineering | ||
| Rigging | Staging/scaffolding | ||
| General labor | Fire Watch |
Direct production man-hours will not include those functions (whether charged directly or indirectly by the contractor’s accounting system) which are defined herein as support for production functions. Necessary support functions shall be considered to be included in the offeror's FBLR for direct production man-hours. Examples of support functions include:
| Testing | Quality Assurance | ||
| Planning | Cleaning (except tank cleaning) | ||
| Material handling & warehousing | Security | ||
| Surveying | Administration | ||
| Transportation | Purchasing staff | ||
| Lofting | Other indirect support | ||
| Supervision |
Consumable materials are goods used in the ordinary course of work performance such as office supplies, paper, rags, vehicle or equipment fuel costs, cleaning chemicals, disposable tools, welding rods, paint buckets, paint brushes, protective clothing, etc. that do not become an integral part of the repaired vessel. Consumable material shall be included in the contractor's FBLR and not separately priced.
The rates for profit and G&A on CLIN 0002 above shall be the same rates used by the contractor in its responses to the Request for CCO Proposals issued under this contract. The KO will apply these rates to the ODCs for each CCO when it is negotiated and settled.
The base cost, stated in this CLIN does not include the profit or G&A rates.
NOTE: This does not include any material cost for Category “A” WIs. The material cost for Category “A” WIs has been included under CLIN 0001.
CLINs 0003 through 0012 –Attachment J-3 – Category “B” WIs provides a WI breakdown of CLIN 0003 through 0012 pricing.
Section C - Descriptions and Specifications
ACRONYM TABLE
| ABIH |
| American Board of Industrial Hygiene |
| ABR |
| Agreement for Boat Repair |
| ABS |
| American Bureau of Shipping |
| ACO |
| Administrative Contracting Officer |
| AGR |
| Additional Government Requirements |
| AIHA |
| American Industrial Hygiene Association |
| ALT |
| Alternate |
| AMT |
| Amount |
| BLDG |
| Building |
| CCO |
| Contract Change Order |
| CD |
| Compact Disc |
| CDRL |
| Contract Data Requirements List |
| CD-ROM |
| Compact Disc Read-Only Memory |
| CFM |
| Contractor Furnished Material |
| CFP |
| Contractor Furnished Property |
| CFR |
| Condition Found Report |
| CHENG |
| Chief Engineer |
| CFR |
| Code of Federal Regulations |
| CIH |
| Certified Industrial Hygienist |
| CLIN |
| Contract Line Item Number |
CONUS
CPARS
Contiguous United States Contractor Performance Assessment Reporting System
| DBIDS |
| Defense Biometric Identification Systems |
| DFARS |
| Defense Federal Acquisition Regulation Supplement |
| DOD |
| Department of Defense |
| DOD SAFE |
| Department of Defense Secure Access File Exchange |
| DON |
| Department of the Navy |
| Electronic Mail |
| ESRS |
| Electronic Subcontract Report System |
| FAPIIS |
| Federal Awardee Performance and Integrity Information System |
| FAR |
| Federal Acquisition Regulation |
| FBLR |
| Fully-Burdened Labor Rate |
| FBO |
| Federal Business Opportunities (FebBizOpps) |
| F/CC |
| Fibers Per Cubic Centimeter |
| FPCON |
| Force Protection Condition |
| FTR |
| Federal Travel Regulations |
| G&A |
| General and Administrative |
| GFI-TD |
| Government Furnished Information – Technical Data |
| GFM |
| Government Furnished Material |
| GFP |
| Government Furnished Property |
| IAW |
| In Accordance With |
| ID |
| Identification |
| ISO |
| International Organization for Standardization |
| JTR |
| Joint Travel Regulations |
| KO |
| Contracting Officer |
| KWh |
| Kilowatt Hour |
| LLTM |
| Long Lead Time Material |
| LPTA |
| Lowest Price Technically Acceptable |
| M&IE |
| Meals and Incidental Expenses |
| MSC |
| Military Sealift Command |
| MSCREP |
| Military Sealift Command Representative |
| MM |
| Millimeter |
| MSRA |
| Master Ship Repair Agreement |
| MTA |
| Mid-Term Availability |
| N/A |
| Not Applicable |
| NCACS |
| Navy Commercial Access Control System |
| NDA |
| Non-Disclosure Agreement |
| NO |
| Number |
| NSP |
| Not Separately Priced |
| ODC |
| Other Direct Costs |
| PAT |
| Proficiency in Analytical Testing |
PII
Portable Document Format Personally Identifiable Information
| PM |
| Program Manager |
| PPE |
| Principal Port Engineer |
| PRIME |
| Prime Contractor |
PSA
QA
Post Shakedown Availability Quality Assurance
| QC |
| Quality Control |
| REV |
| Revision |
| RFC |
| Request for Specification Clarification |
| RFP |
| Request for Proposal |
| ROH/DD |
| Regular Overhaul/Dry-Docking |
| SECNAV |
| Secretary of the Navy |
| SF |
| Standard Form |
| SUB |
| Subcontractor |
| TPSN |
| Time Phased Sequencing Network |
| TWA |
| Time-Weighted Average |
| USC |
| United States Code |
| USCG |
| United States Coast Guard |
| USNS |
| United States Naval Ship |
| VR |
| Voyage Repair |
| WAWF |
| Wide Area Workflow |
| WI |
| Work Item |
C-1 GENERAL
1. The contractor shall prepare for and accomplish the VR, overhaul, or alterations of the USNS MIGUEL KEITH (T-ESB 5) as specified herein and IAW the WI package as provided in Attachment J-1 – WI Package (Specifications). Unless otherwise specified, all work shall be performed at the contractor’s shipyard.
2. In performing the WIs specified, the contractor shall be responsible for all of the following related work (in case of a discrepancy, the terms and conditions stated in the WIs take precedence over the following terms and conditions):
(a) Providing the necessary management, procurement, production, testing, technical capability and resources, and quality assurance services.
(b) Ensuring the timely procurement of CFM/CFP and the timely reporting, receipt, storage, installation, and accountability of GFM/GFP IAW FAR Clause 52.245-1 and DFARs Clauses 252.211-7007, 252.245-7001, 252.245-7002, 252.245-7003, and 252.245-7004.
(c) Using progress measurement systems to determine the physical progress of completed work for each of the elements in the scheduling plan, including material and manpower control, engineering, production, tests and trials IAW the CDRL and the contractor's own Technical Proposal, and the WI package. The progressing system shall permit a direct comparison of the physical progress of completed work to the planned performance measurement baseline for each of the elements in the scheduling plan.
(d) Using management procedures and systems to identify behind schedule conditions and unfavorable schedule variances based on the TPSN submitted with the contractor’s proposal. The applied procedures and systems shall provide timely identification of scheduling problem areas to permit prompt management action to correct unsatisfactory conditions.
(e) Developing a performance milestone schedule/critical path chart to measure scheduled performance. Deviations from the milestone schedule/critical path chart dates in WI 013 must be submitted to and approved by the KO. A performance milestone schedule and critical path chart shall be developed and submitted in accordance with the WI Package. The performance milestone schedule shall include and clearly identify primary and parallel critical paths. The resource loaded performance milestone schedule shall include, at a minimum, those milestones identified in WI 013.
(f) Using approved quality control procedures as required by this contract and the WI package to ensure procured material and performed production work conforms to the required quality standards.
(g) Ensuring the ship's equipment and systems remain configured to existing baselines with regard to procured material, production work, and software.
(h) Applying stringent configuration control procedures to ensure that configuration baselines are maintained for procured material and production work.
(i) Providing for staging and storing of material (both Government-furnished and contractor-furnished) and LLTM for use in the availabilities from the date of award.
(j) Managing all subcontractors’ performance during the availability. Ensure subcontractor work is to the same quality and standards as expected from the prime contractor. Develop and maintain a subcontractor management plan. The plan shall ensure that all communication and control of subcontractors is maintained by the prime contractor.
(k) Employing good judgment and sound engineering practice and principles, particularly when WIs do not describe all details of accomplishing the work. The contractor shall be expected to have, either organically or through subcontractors, access to competent engineers who have a history of working solutions in a maritime environment.
3. Contract work shall be performed by an eligible contractor as defined below.
(a) The contractor shall be capable of performing the full scope of the requirement stated herein within its own facilities, utilizing its own shop(s) and work force, or be capable of subcontracting for these elements beyond its managerial, technical, or physical capability or capacity. The contractor shall assume full responsibility for the integrated scheduling, cost, and quality of subcontractor performance.
(b) The contractor shall be a company recognized as engaged in ship repair work and possess an organization capable of the full scope of planning, engineering, quality control, shipboard/offship production and component/system testing and trials. The contractor shall provide industry certifications such as: MSRA, ABR, or ISO Certification that would further emphasize the contractor's ability to perform the work. To be determined responsible, the contractor shall submit acceptable evidence to demonstrate its ability to accomplish the work. This will include a conclusive demonstration of having the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and/or subcontractors) at the time of award. The contractor’s proposal shall provide a documented and positive demonstration of established organizational elements as set forth below. These characteristics will be evaluated to determine a firm's eligibility for contract award:
a. Administration/Management Control. Established organization geared toward ship repair at all levels of size, value, and complexity, and toward technology innovation and process improvement. Clear lines of authority. Delegation of responsibility. Mid-level managerial positions in place. Competent and experienced employees with ship repair experience. Capability to develop and integrate planning, estimating, and scheduling functions. Defined managerial responsibilities for production, quality assurance, material procurement/control, and subcontractor control.
b. Financial Control. Segregation of accounting costs. Adequate accounting system. Favorable cash flow-ratios. Availability of a line of credit or other source of financial income to support the work effort. Prompt payment of subcontractors and suppliers.
c. Production Control. A production organization. On board (or ability to obtain) trade mix/skills to perform ship repair work. Control of production efforts. Integration of other key functions with production. Use of scheduling techniques. Methods of progressing. Training available to trades employees.
d. Production Technical Support. Engineering and design support capabilities (in-house or subcontracted) with sufficient capability to diagnose and evaluate technical problems and issues and to make competent technical recommendations to MSC when necessary and appropriate. The offeror shall be fully cognizant of ABS rules and USCG regulations and how they apply and impact this specification package.
e. Material/Procurement Control. A material purchasing department with staff. Procedures for control of material (purchasing, monitoring, receipt, inspection, segregation, issuance, nonconformance, and disposal). An inventory system – ordering, tagging warehousing. CFM/GFM storage, control and protection. Existing environmentally-controlled warehouse space. Material handling equipment. Familiarity with the Navy logistics support system.
f. Subcontractor Control. Procedures for selecting, scheduling, managing, monitoring and controlling subcontractors.
g. Quality Control/Test and Trials. A quality control organization/department/staff. Quality assurance procedures/manual. Calibration and metrology system availability. Test memo writing capability. Nondestructive Testing capabilities. Welding procedures and welders’ qualifications. Ability to perform trend analysis. Quality control system shall be certified or equivalent to ISO 9001:2001 standards.
h. Safety/Security. Safety Organization/Manager or Engineer. Safety manual/procedures. Safety training. First-aid capabilities or medical services. Fire protection/procedures. Physical yard security/security procedures.
i. Hazardous Material/Waste Control. Proper procedures and facilities to meet the legal requirements for removal, storage, and disposal of hazardous waste. Segregated storage. Documentation of licensed subcontractors responsible for control of hazardous waste removal, storage, and disposal. Appropriate state/federal agency-issued hazardous waste generator number. Disposal records which indicate type of material, date, and place of disposal.
j. Facilities. Although facility requirements may vary with the work authorized for a specific ship, the contractor must be a ship repair company that possesses or has available the following facilities:
· Pier, with services in place, accessible to the CLASS size ship for birthing
· Structural Shop
· Machine Shop
· Pipe Shop
· Electrical/Electronic Shop
· Carpentry Shop
· Rigging Equipment
· Dry-dock – when required for docking of vessel in performance of the specification
k. Agreements. To be determined responsible, a prospective contractor must possess an MSRA, ABR or submit acceptable evidence in lieu of the aforementioned to effectively communicate and demonstrate its ability to obtain required resources.
(c) The government reserves the right to perform a site survey(s) for verification of policies, procedures, capabilities and facilities prior to award.
This award consummates the contract which consists of the following documents: (a) the Government’s solicitation and your final proposal revision submitted on 03/16/2020 inclusive of all discussion and clarifications responses and (b) this award/contract.
C – 2 List of Standard WIs included for this solicitation:
| NOT SEPARATELY PRICED (NSP) REQUIREMENTS | Category | ||
| 001 | SCOPE, GENERAL CONDITIONS AND DEFINITIONS | NSP | |
| 002 | TECHNICAL AND MANUFACTURER’S REPRESENTATIVES | NSP | |
| 003 | APPROACH, BERTH, AND MOORING REQUIREMENTS | NSP | |
| 004 | TESTING AND QUALITY ASSURANCE | NSP | |
| 005 | ELECTRICAL SAFETY PROCEDURE REQUIREMENTS | NSP | |
| 006 | HEAVY WEATHER PLAN | NSP | |
| 007 | COLD WEATHER PLAN | NSP | |
| 024 | PHYSICAL SECURITY AT PRIVATE CONTRACTOR’S FACILITY (NSP) | NSP |
CATEGORY “A” WORK ITEMS
| 010 | FURNISH OFFICE FOR OVERHAUL MANAGEMENT TEAM (OMT) | A COMBINED |
| 011 | FURNISH GENERAL SERVICES | A COMBINED |
| 012 | INFORMATION TECHNOLOGY SERVICES | A COMBINED |
| 013 | PROJECT PLANNING AND PRODUCTION STATUS MONITORING REPORTS | A COMBINED |
| 014 | PREPARATION OF WEIGHT AND MOVEMENT REPORT | A COMBINED |
| 015 | INTEGRATED LOGISTICS AND GFM SUPPORT REQUIREMENTS | A COMBINED |
| 016 | FIRE PROTECTION AND SHIP’S SAFETY PROGRAM | A COMBINED |
| 017 | HANDLING SHIP’S STORES | A COMBINED |
| 018 | DELIVERY AND REDELIVERY OF THE VESSEL | A COMBINED |
| 019 | SHIPBOARD ACCESS AND SECURITY | A COMBINED |
| 020 | GAS FREE CERTIFICATES | A COMBINED |
| 021 | CLEAN AND GAS FREE TANKS, VOIDS, AND COFFERDAMS & SPACES | A COMBINED |
| 022 | MACHINERY SPACE TURN-OVER, DOCK TRIALS AND SEA TRIALS | A COMBINED |
| 023 | HAZARDOUS WASTE DISPOSAL AT A CONTRACTOR’S FACILITY | A COMBINED |
CATEGORY “B” WORK ITEMS
| 025 | PHYSICAL SECURITY AT PRIVATE CONTRACTOR’S FACILITY | B COMBINED |
| 030 | CONTINUATION OF SERVICE | B COMBINED |
SECTION 100 HULL STRUCTURE Category
CATEGORY “A” WORK ITEMS
| 101 | ABS ANNUAL TANK INSPECTION | A | |
| 102 | MACNINERY ROOM TO PUMP ROOM WTD (T-ALT T-ESB 15-002) | A | |
| 103 | MACHINERY SPACE DECK UTILIZATION PLAN (T-ALT T-ESB 15-057) | A | |
| 104 | INSTALL MISSION DECK MOORING FITTINGS (T-ALT T-ESB 17-021) | A | |
| 105 | EXHAUST STACK ACCESS LADDER MOD (T-ALT T-ESB 15-012) | A |
SECTION 200 MACHINERY, PROPULSION
201 PROPULSION MOTOR AND COOLER CLEANING, INSPECTION AND MAINTENANCE A
| SECTION 300 | ELECTRICAL | |
| CATEGORY “A” WORK ITEMS | Category | |
| 301 | HV AND MV SWITCHBOARD ANNUAL INSPECTION AND CLEANING | A |
| 302 | MOTOR CONTROL CENTER INSPECTION AND CLEANING | A |
| 303 | GENERATOR INSPECTION AND CLEANING | A |
| 304 | MSC LAN EXPANSION (T-ALT T-ESB 16-017) | A |
| 305 | HULL PERIMETER LIGHTING (T-ALT T-ESB 15-005) | A |
| 306 | 480 VOLT SUBMERSIBILE PUMP OUTLETS (T-ALT T-ESB 15-003) | A |
SECTION 400 COMMUNICATION AND NAVIGATIONAL AIDS Category
CATEGORY “A” WORK ITEMS
| 401 ANNUAL RADIO COMM EQUIP RECERTIFICATION | A | |
| 402 ANNUAL VDR CERTIFICATION | A | |
| 403 ANNUAL ECDIS SERVICE | A | |
| 404 ANNUAL GYRO COMPASS SERVICE | A | |
| 405 ANNUAL RADAR SERVICE (ABS) | A | |
| 406 EXPAND SHORE TELEPHONE CONNECTION CAPABILITY (T-ALT T-ESB 15-033) | A |
407 MACHINERY SPACE CCTV MONITORING SYSTEM & BOW CAMERA INSTALL
| (T-ALT T-ESB 15-018 & 15-048) | A |
| 408 NAVMEDIA TV DTS SYSTEM INSTALL (TALT T-ESB 15-059) | A |
| 409 SITE 300 INSTALLATION INDUSTRIAL ASSISTANCE | A |
CATEGORY “B” WORK ITEMS
410 ECDIS INSTALL IN MASTER’S DAYROOM (TALT T-ESB 15-009) B
SECTION 500 MACHINERY, AUXILIARY SYSTEMS Category
CATEGORY “A” WORK ITEMS
| 501 | FIXED CO2 FIREFIGHTING SYSTEM ANNUAL INSPECTION | A |
| 502 | FIXED FOAM FIREFIGHTING SYSTEM ANNUAL INSPECTION | A |
| 503 | LOCAL WATER BASED MIST FIRE EXT SYSTEM ANNUAL INSPECTION | A |
| 504 | FIRE AND SMOKE DETECTION ANNUAL INSPECTION | A |
| 505 | FRYER GRILL AND RANGE HOOD EXT ANNUAL INSPECTION | A |
| 506 | PORTABLE EXTINGUISHERS ANNUAL INSPECTION | A |
| 507 | FIRE HOSE ANNUAL INSPECTION | A |
| 508 | FIRE AND SMOKE DAMPER ANNUAL INSPECTION | A |
| 509 | FIRE DOORS & SHUTTERS (1 YR) | A |
| 510 | SCBA ANNUAL INSPECTION | A |
| 511 | ANNUAL PROVISION CRANES AND PEDESTAL (P & S) INSPECTION | A |
| 512 | ANNUAL APPLETON SUPPORT CRANE INSPECTION | A |
| 513 | ANNUAL ENGINE ROOM BRIDGE CRANE (P & S) INSPECTIONS | A |
| 514 | ANNUAL HANGAR BRIDGE CRANE INSPECTION | A |
| 515 | INSTALL DUMBWAITER FROM UPPER DECK TO A DECK (T-ALT T-ESB 15-006) | A |
| 516 | INSTALL 3RD AC PLANT IN FWD HOUSE (T-ALT T-ESB 15-021) | A |
| 517 | SEGREGATE GREY & BLACK WATER TRANSFER LINE (T-ALT T-ESB 15-022) | A |
| 518 | AFT HOUSE GREY WATER SYSTEM ISOLATION (T-ALT T-ESB 15-036/37) | A |
| 519 | MISSION DECK BOAT REFUELING STATION ENHANCEMENTS (T-ALT T-ESB 15-052) | A |
| 520 | INSTALL FIXED FIREFIGHTING JP-5 PUMP ROOM (T-ALT T-ESB 16-002) | A |
| 521 | FORWARD MAIN FIRE LOOP INSTALLATION (T-ALT T-ESB 15-055) | A |
| 522 | RO FEED WATER CYCLONE SEPARATOR INSTALL (T-ALT T-ESB 17-028) | A |
| 523 | REPLACE RO UNIT SEA WATER FEED PUMP (T-ALT T-ESB 18-031) | A |
| 524 | GAUGE CALIBRATION | A |
| 525 | FWD AC PLANT 1 AND 2 OPEN AND INSPECT | A |
SECTION 600 OUTFIT, FURNISHINGS AND HABITABILITY Category
CATEGORY “A” WORK ITEMS
| 601 | LIFEBOAT & DAVIT ANNUAL INSPECTION (ABS) | A | ||||||
| 602 | RESCUE BOAT & DAVIT ANNUAL INSPECTION (ABS) | A | ||||||
| 603 | LIFERAFT & DAVIT ANNUAL CERTIFICATION (ABS) | A | ||||||
| 604 | ACCOMMODATION LADDER INSPECTION (1 YR) | A | ||||||
| 605 | DEEP FAT FRYER INSPECTION | A | ||||||
| 606 | AFT HOUSE HABITABILITY MODS (T-ALT T-ESB 15-013/17-023/15-046) | A | ||||||
| 607 | ECR1 DECK HEAD INSTALL (T-ALT T-ESB 15-040) | A | ||||||
| 608 | BRIDGE WING SHELTERS (T-ALT T-ESB 15-004) | A | ||||||
| 609 | INSTALL LIFESAVING APPLIANCES FOR BERTHING ADDITIONAL CIVMARS IN | |||||||
| FWD HOUSE (T-ALT T-ESB 18-056) | A | |||||||
| 610 | CBRD CAGE AND CABINETS & ASSOC SYSTEMS (T-ALT T-ESB 17-005 | A | ||||||
| 611 | INSTALL LIFE SAVING APPLIANCES TO SUPPORT BERTHING CONTAINERS | |||||||
| (T-ALT T-ESB 17-029) | A | |||||||
| 612 | PA/GA, FIRE DETECTION AND IDS INTERFACE FOR MISSION DECK FOOD | |||||||
| STORAGE AND LAUNDRY TEUS (T-ALT T-ESB 19-002) | A | |||||||
| 613 | RECONFIGURE A2 MEZZANINE DECK SOCKETS (T-ALT T-ESB 19-003) | A | ||||||
| 614 | A2 A3 LEVEL 25 RACK PERMANENT BERTHING MODIFICATIONS | |||||||
| (T-ALT T-ESB 19-004 and 19-005) ) | A | |||||||
| 615 | ESB MILCREW A2 LEVEL SANITARY SPACES HVAC MODIFICATIONS | |||||||
| (T-ALT T-ESB 19-004) | A |
CATEGORY “B” WORK ITEMS
| 616 | GALLEY SHELVING INSTALL (T-ALT T-ESB 17-002) | B | ||||
| 617 | MILCREW SPACE CONVERSION FOR BARBER SHOP (T-ALT T-ESB 18-011) | B | ||||
| 618 | ENLISTED MESSDECKS (A4-90-0) TABLE/SEATING MODIFICATIONS | |||||
| (TALT T-ESB 19-043) | B | |||||
| 619 | CPO/SNCO MESS (A4-90-3) TABLE/SEATING MODIFICATIONS (TALT T-ESB 19-044) | B | ||||
| 620 | OFFICER MESS/WARDROOM (A4-90-1) TABLE/SEATING MODIFICATIONS (TALT | |||||
| T-ESB 19-045) | B |
SECTION 700 SPONSOR EQUIPMENT Category
CATEGORY “A” WORK ITEMS
| 144 | INSTALL REMOVABLE COAMING ON MISSION DECK AT FRAMES 73 - 76 | ||
| (T-ALT T-ESB 15-034) | A | ||
| 320 MILCREW LAN DROPS (T-ALT T-ESB 19-007) | A | ||
| 434 | SEA GIRAFFE INDUSTRIAL SUPPORT (T-ALT T-ESB 18-034) | A | |
| 528 | FWD OVERBOARD BLACK/GREY WATER DISCHARE AND SHORE CONNECTION | ||
| (T-ALT T-ESB 16-043) ) | A | ||
| 597 | AFT CRANE RESOLUTION OF VIBRATION ISSUE A | ||
| 820 | A5 LEVEL AVIATION SUPPORT SPACES HVAC UPGRADE (PHASE I) | ||
| (T-ALT T-ESB 18-013) | A | ||
| 821 | FWD HOUSE HVAC SYSTEM UPGRADE (PHASE II) (T-ALT T-ESB 18-036) | A |
CATEGORY “B” WORK ITEMS
| 370 SOF LAN DROPS (T-ALT T-ESB 19-050) | B | |
| 632 | REPAIR NON-SKID COATINGS | B |
SECTION 800 HEATING, VENTILATION AND CONDITIONING Category
CATEGORY “A” WORK ITEMS
| 801 | GALLEY VENTILATION AND GAYLORD HOOD ANNUAL CLEANING | A |
| 802 | LAUNDRY VENT ANNUAL CLEANING | A |
Section D - Packaging and Marking
WOOD PACKAGING MATERIAL (WPM) - ADDITIONAL DELIVERY INSTRUCTIONS
In accordance with the requirements of International Standards for Phytosanitary Measures (ISPM) 15, the following commercial heat treatment process has been approved by the American Lumber Standards Committee (ALSC) and is required for all Wood Packaging Material (WPM). WPM is defined as wood pallets, skids, load boards, pallet collars, wooden boxes, reels, dunnage, crates, frames, and cleats. Packaging materials exempt from the requirements are materials that have undergone a manufacturing process such as corrugated fiberboard, plywood, particleboard, veneer and oriented strand board. All WPM shall be constructed from Heat Treated (HT to 56 degrees Centigrade for 30 minutes) lumber and certified by an accredited agency recognized by the ALSC in accordance with Wood Packaging Material Policy and Wood Packaging Material Enforcement Regulations (see URL: http://www.alsc.org). All materials must include certification markings in accordance with ALSC standards and be placed in an unobstructed area that will be readily visible to inspectors. Pallet markings shall be applied to the stringer or block on diagonally opposite sides and ends of the pallet and be contrasting and clearly visible. All dunnage used in configuring and/or securing the load shall also comply with ISPM 15 and be marked with an ALSC approved "DUNNAGE" stamp. Failure to comply with the requirements of this restriction may result in refusal, destruction, or treatment of materials at the point of entry.
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
| CLIN |
| INSPECT AT |
| INSPECT BY |
| ACCEPT AT |
| ACCEPT BY |
| 0001 |
| N/A |
| N/A |
| N/A |
| N/A |
| 0001AA |
| Origin |
| Government |
| Origin |
| Government |
| 0001AB |
| Origin |
| Government |
| Origin |
| Government |
| 0001AC |
| Origin |
| Government |
| Origin |
| Government |
| 0001AD |
| Origin |
| Government |
| Origin |
| Government |
| 0001AE |
| Origin |
| Government |
| Origin |
| Government |
| 0002 |
| N/A |
| N/A |
| N/A |
| N/A |
| 0002AA |
| Origin |
| Government |
| Origin |
| Government |
| 0002AB |
| Origin |
| Government |
| Origin |
| Government |
| 0002AC |
| Origin |
| Government |
| Origin |
| Government |
| 0002AD |
| Origin |
| Government |
| Origin |
| Government |
| 0003 |
| Origin |
| Government |
| Origin |
| Government |
| 0004 |
| Origin |
| Government |
| Origin |
| Government |
| 0005 |
| Origin |
| Government |
| Origin |
| Government |
| 0006 |
| Origin |
| Government |
| Origin |
| Government |
| 0007 |
| Origin |
| Government |
| Origin |
| Government |
| 0008 |
| Origin |
| Government |
| Origin |
| Government |
| 0009 |
| Origin |
| Government |
| Origin |
| Government |
| 0010 |
| Origin |
| Government |
| Origin |
| Government |
| 0011 |
| Origin |
| Government |
| Origin |
| Government |
| 0012 |
| Origin |
| Government |
| Origin |
| Government |
CLAUSES INCORPORATED BY REFERENCE
| 252.217-7005 |
| Inspection and Manner of Doing Work |
| JUL 2009 |
| 252.217-7006 |
| Title |
| DEC 1991 |
| 252.217-7013 |
| Guarantees |
| DEC 1991 |
Section F - Delivery and Performance
DELIVERY INFORMATION
| CLIN |
| DELIVERY DATE |
| QUANTITY |
| SHIP TO ADDRESS |
| DODAAC / CAGE |
| 0001 |
| N/A |
| N/A |
| N/A |
| N/A |
| 0001AA |
| POP 03-AUG-2020 TO |
01-DEC-2020
| N/A |
| N/A |
| 0001AB |
| POP 03-AUG-2020 TO |
01-DEC-2020
| N/A |
| N/A |
| 0001AC |
| POP 03-AUG-2020 TO |
01-DEC-2020
| N/A |
| N/A |
| 0001AD |
| POP 03-AUG-2020 TO |
01-DEC-2020
| N/A |
| N/A |
| 0001AE |
| POP 03-AUG-2020 TO |
01-DEC-2020
| N/A |
| N/A |
| 0002 |
| N/A |
| N/A |
| N/A |
| N/A |
| 0002AA |
| POP 03-AUG-2020 TO |
01-DEC-2020
| N/A |
| N/A |
| 0002AB |
| POP 03-AUG-2020 TO |
01-DEC-2020
| N/A |
| N/A |
| 0002AC |
| POP 03-AUG-2020 TO |
01-DEC-2020
| N/A |
| N/A |
| 0002AD |
| POP 03-AUG-2020 TO |
01-DEC-2020
| N/A |
| N/A |
| 0003 |
| POP 03-AUG-2020 TO |
01-DEC-2020
| N/A |
| N/A |
| 0004 |
| POP 03-AUG-2020 TO |
01-DEC-2020
| N/A |
| N/A |
| 0005 |
| POP 03-AUG-2020 TO |
01-DEC-2020
| N/A |
| N/A |
| 0006 |
| POP 03-AUG-2020 TO |
01-DEC-2020
| N/A |
| N/A |
| 0007 |
| POP 03-AUG-2020 TO |
01-DEC-2020
| N/A |
| N/A |
| 0008 |
| POP 03-AUG-2020 TO |
01-DEC-2020
| N/A |
| N/A |
| 0009 |
| POP 03-AUG-2020 TO |
01-DEC-2020
| N/A |
| N/A |
| 0010 |
| POP 03-AUG-2020 TO |
01-DEC-2020
| N/A |
| N/A |
| 0011 |
| POP 03-AUG-2020 TO |
01-DEC-2020
| N/A |
| N/A |
| 0012 |
| POP 03-AUG-2020 TO |
01-DEC-2020
| N/A |
| N/A |
| 52.242-15 |
| Stop-Work Order |
| AUG 1989 |
| 52.242-17 |
| Government Delay Of Work |
| APR 1984 |
| 52.247-55 |
| F.O.B. Point For Delivery Of Government-Furnished Property |
| JUN 2003 |
F-1 SHIP AVAILABILITY PERIOD
It is anticipated the ship will arrive at contractor’s yard on or about 03 August, 2020. All work shall be completed in no more than 120 calendar days from actual start date designated by the Government at time of contract award.
F-2 PLACE OF PERFORMANCE
The place of performance for this contract shall be the contractor’s facility.
Section G - Contract Administration data
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (DEC 2018)
(a) Definitions. As used in this clause—
“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.
“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.
“Payment request” and “receiving report” are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall—
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:
(1) Document type. The Contractor shall submit payment requests using the following document type(s):
(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.
(ii) For fixed price line items—
(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.
_INVOICE____________________________________________________
(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.
_NOT APPLICABLE________________________________________________________
(iii) For customary progress payments based on costs incurred, submit a progress payment request.
(iv) For performance based payments, submit a performance based payment request.
(v) For commercial item financing, submit a commercial item financing request.
(2) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.
[Note: The Contractor may use a WAWF “combo” document type to create some combinations of invoice and receiving report in one step.]
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table*
| Field Name in WAWF |
| Data to be entered in WAWF |
| Pay Official DoDAAC |
| _N32205___ |
| Issue By DoDAAC |
| ____ |
| Admin DoDAAC** |
| ____ |
| Inspect By DoDAAC |
| ____ |
| Ship To Code |
| _N62387___ |
| Ship From Code |
| ____ |
| Mark For Code |
| ____ |
| Service Approver (DoDAAC) |
| ____ |
| Service Acceptor (DoDAAC) |
| ____ |
| Accept at Other DoDAAC |
| ____ |
| LPO DoDAAC |
| ____ |
| DCAA Auditor DoDAAC |
| ____ |
| Other DoDAAC(s) |
| ____ |
(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.
(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.
(g) WAWF point of contact.
(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity’s WAWF point of contact.
__NOT APPLICABLE______________________________________________________
(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.
(End of clause)
ADDENDUM TO 252.232-7006
The following information, at a minimum, must be attached into Wide Area Work Flow (WAWF) and submitted with each and every invoice showing certification with the Onsite Management Team prior to submission:
| CLIN # |
| Contract Price Through Mod P0000x |
| % Complete |
| Contract Completed ($) |
| Less Retainage ($) |
| Less Prev Payments ($) |
| Amount due this Invoice ($) |
| Total Invoiced to Date ($) |
| 004 |
| Option |
| 005 |
| Option |
| 00X |
| Option |
Military Sealift Command
Administrative Contracting Officer
Military Sealift Command
Ship Yard Representative
Port Engineer
(End of instructions)
MSC SPECIFIC WIDE AREA WORKFLOW (WAWF) INSTRUCTIONS (AUG 2012)
The information contained in this instruction is supplemental to DFARS 252.232-7006.
The information contained in the table in DFARS 252.232-7006 is for WAWF purposes only. Information included in DFARS 252.232-7006 and this WAWF instruction apply only to WAWF Invoicing and WAWF Receiving Reports. Contradictory information elsewhere in this contract, e.g. Ship to DoDAAC, shall be followed per the terms and conditions of the contract.
When entering the invoice into WAWF, the Contractor shall fill in the DoDAAC fields or DoDAAC extensions exactly as shown in the table in DFARS 252.232-7006. Fields that should not be filled in when entering the invoice into WAWF will be indicated with the direction, “Leave Blank.”
In some situations the WAWF system will pre-populate the “Pay DoDAAC,” “Admin By DoDAAC” and “Issue By DoDAAC.” The Contractor shall verify that those DoDAACs automatically entered by the WAWF system match the information in the table in DFARS 252.232-7006. If these DoDAACs do not match, then the Contractor shall correct the field(s).
If Receiving Reports are required, ensure that the “Inspection” and “Acceptance” defaults of “destination” for both fields are not changed in the WAWF online interface.
The CLINs on the WAWF invoice shall be entered exactly as set forth in the contract document including CLIN number (e.g. 0001), Quantity (may be adjusted for actual quantity or dollar value delivered and invoiced), and Unit Price (e.g. $1.00). The dollar amounts on each CLIN or SubCLIN on the WAWF invoice shall reflect final performance values, but in no instance can the dollar amount for each CLIN or SubCLIN exceed what is specified in the contract document. The Contractor shall bill to the lowest level, e.g., the SubCLIN level. The Quantity and Unit of Measure fields must be filled out exactly as indicated in the CLINs and SubCLINs to reduce the possibility of the invoice being delayed or rejected during processing.
Before closing out of an invoice session in WAWF, but after submitting the document or documents, the Contractor will be given the option to send additional email notifications by clicking on the “Send More Email Notifications” link that appears on the page. The Contractor shall click on this link and add the Technical Point of Contact’s (TPOC) or Contracting Officer’s Representative’s (COR) email address in the first email address block and add any other additional email addresses desired in the following blocks. This additional notification to the Government is important to ensure the acceptor/receiver is aware that the invoice documents have been submitted into the WAWF system.
(End of instructions)
Section H - Special Contract Requirements
| 252.225-7048 |
| Export-Controlled Items |
| JUN 2013 |
SECTION H CLAUSES
H-1 OPTION FOR INCREASED QUANTITIES
The Government may require delivery of the numbered line items identified in Section B as option items in any amount up to the unit quantities and at the unit prices stated in the contractor’s J-3, “Contractor Price Breakdown – Category B Items.” The KO may exercise the options by giving the contractor written notification or via issuance of standard modification (SF 30). Delivery of option items shall be within the performance period identified in Section F unless the parties otherwise agree.
H-2 PREVENTION OF THE DISCHARGE OF OIL AND HAZARDOUS SUBSTANCES
(a) Policy. In compliance with Executive Order Number 11752 (38 F.R. 34793), the policy of the DON is to conform to the provisions of the Federal Water Pollution Control Act, as amended (Title 33 U.S.C. 1251 et seq), and the Oil Pollution Act of 1990, as amended (Title 33 U.S.C. 2701 et seq.), insofar as these Acts prohibit the discharge of oil, oily mixtures, and hazardous substances, and regardless of whether or not these Acts pertain specifically to the Naval vessel and shore activities. The prescribed clause is intended to implement that policy with respect to the ship(s) being constructed or undergoing repair and overhaul under this contract.
(b) Definitions. For the purpose of this clause, the terms "oil," "oily mixtures," "hazardous substance," and "discharge" shall have the meanings as defined in the Acts referred to in paragraph (a) of this clause and other environmental statutes.
(c) Trials. Prior to commencement of any dock or sea trials hereunder, the contractor shall assure the Ship’s Master and CHENG as well as the PPE by demonstrations, completed test memoranda, or other means reasonably acceptable to the Ship’s Master and CHENG, as well as the PPE, that all equipment, the function of which is to prevent the accidental discharge of oil, oily mixtures, or hazardous substances from the ship, that the contractor shall be required by the specifications to install, is fully operable.
(d) Reports. The contractor shall, as soon as it has knowledge of any discharge of oil, oily substance, or hazardous substance from the ship, immediately notify the Ship’s Master and CHENG, as well as the Principle Port Engineer, thereof and shall immediately take all reasonable steps to prevent further discharge. Within 24-hours thereafter, the contractor shall file with the Ship’s Master and CHENG, as well as the PPE, the "Oil or Hazardous Substance Discharge Report.”
(e) Liability. The contractor shall be liable to the Government for all such costs of removal of such oil, oily mixture, or hazardous substance where such discharge was the result of willful negligence or willful misconduct within the privity and knowledge of the contractor. All documentation related to such waste shall bear the contractor’s generator number in accordance with WI 0023 HAZARDOUS WASTE DISPOSAL AT A CONTRACTOR'S FACILITY. The contractor shall not be liable for the costs incurred by the Government for the removal of such oil, oily mixture, or hazardous substance when initiated by the Government.
H-3 AGR CONTRACT LINE ITEM NUMBER (CLIN 0002)
(a) The Government may utilize CLIN 0002 for and not limited to, man-hours generated from a discrepancy found between WIs and the current conditions or a needed repair found during the open and inspect phase of the WI. This work may consist of supplemental, emergent, or new work. AGR does not include work performed pursuant to DFARS Clause 252.217-7005 - Inspection and Manner of Doing Work, 252.217-7013 - Guarantees, or other contract clauses relating to the correction of defects. The contractor agrees that CLIN 0002 AGR man-hours, if ordered, shall be performed concurrently with CLIN 0001 and any or all Category “B” WIs exercised, during the contract’s performance period, without impacting, accelerating, or causing delay or disruption to the work required by the aforementioned WIs, to any other Government contract, or to any other work in progress for the Government. Work under this CLIN may coincide with ODC, and therefore will be performed concurrently with H-4 (ODC).
(b) As a result of a discrepancy found between the WI and the current conditions or a needed repair found during the open and inspect phase of the WI, the contractor may submit a CFR to the ACO and the PPE. As a result of this report submission, the ACO may request a proposal from the contractor. Whenever the Government orders AGR pursuant to this clause, the contractor shall submit a price proposal for such work. This proposal shall be submitted within three (3) days of the receipt of the Government's request for a proposal, or within such additional time provided in writing by the KO. The contractor's failure to submit its proposal within the three (3) day period, or such extended period of time, may be considered a failure of the parties to negotiate a fair and reasonable price for the AGR and will permit the KO to take any of the three (3) options set forth in subparagraph (d) below. AGR proposals shall be priced using the FBLR set forth in Section B, CLIN 0002. The rate established in CLIN 0002 will be used in evaluating the contractor's proposal and will also be used for negotiating changes as required by this clause. As part of the contractor’s proposal submission for AGR, the following shall be included:
| - FBLR |
| - Proposed Labor Mix/Categories |
| - Proposed Man Hours |
| - Total Proposed AGR |
(c) Considering FBLRs have been pre-approved in CLIN 0002, proposal evaluation may be limited to: (1) evaluating the mix of labor categories and associated man-hours to ensure that they are reasonable to meet the Government’s minimum requirements in addressing these discrepancies or repairs found; and (2) as a result of the mix of labor categories and man-hours, the subsequent AGR price is fair and reasonable IAW FAR 15.404-1(b) – Price analysis for commercial and non-commercial items. In the event that a fair and reasonable price cannot be negotiated, the KO reserves the right to procure these ODCs utilizing alternative means described in subparagraph (d), below.
(d) Upon receipt of the contractor's price proposal for the AGR the contractor and the KO shall negotiate the scope of the effort. If a fair and reasonable price cannot be negotiated between the contractor and the KO, the KO reserves the right to:
(1) Have the work performed by the Government;
(2) Issue a unilateral modification;
(3) Cancel the requirement.
(e) The contractor knowingly and voluntarily waives all claims against the Government and/or other third-party contractors for delay, disruption, loss of efficiency, or other impact arising out of or based upon the presence of Government or other contractor employees performing the AGR at the contractor's facility. Furthermore, in cases described in sub-paragraphs (d)(1) and (2) above, the contractor waives any right to claims of interference under the DFARS Clause 252.217-7011 - Access to Vessels.
(f) The contractor warrants and hereby certifies that its price for the firm fixed portion of this contract (CLIN 0001) does not include any amount for AGR (CLIN 0002). Settlement of AGR (CLIN 0002) will be for the purpose of providing funding. In the event the Government requires additional work, authorization to proceed shall be made only by the KO. The Contractor is to perform and invoice against CLIN 0002 ONLY for work that has been AUTHORIZED through a settled CCO and incorporated into the contract through a contract modification. All funding remaining on CLINs 0001 through 0012 at contract completion shall be de-obligated.
H – 4 OTHER DIRECT COSTS (CLIN 0002)
(a) The Government may utilize CLIN 0002 for and not limited to, material and equipment generated from a discrepancy found between WIs and the current conditions or a needed repair found during the open and inspect phase of the WI. This work may consist of supplemental, emergent, or new work.
This is the start of the file's text. The full file is on GovTribe.