Q&A_Set__2.docx
DOCX document 19 KB Posted
- Attached to
- Sources Sought EVERS Federal contract opportunity
- Solicitation number
- N32205-19-R-6010
About this file
Q&A Set 2.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| T-AKE_CLASS_NOTICE_15_-_MAIN_DIESEL_GENERATOR_COUPLINGS.pdf | ||
| DOKU1G531W0013E_0_0_VULKAN_COUPLING.pdf | ||
| J_-_2_Category_A_Items_M.EVERS.xls | XLS spreadsheet | |
| 0208_A_VULKAN_COUPLINGS_LINK_STABILIZER_INSTALL.pdf | ||
| USNS_MEDGAR_EVERS_AMEND_0004.docx | DOCX document | |
| MEDGAR_EVERS_MOD_0003.docx | DOCX document | |
| Question_Set__2_Question__4_Reference.pdf | ||
| Q&A_Set2_Question__3_Reference.pdf | ||
| MEDGAR_EVERS_ROH_DD_QUESTIONS_AND_ANSWERS.doc | DOC document | |
| USNS_MEDGAR_EVERS_AMEND_0002.docx | DOCX document | |
| USNS_MEDGAR_EVERS_ROH_DD_AMEND_0001.docx | DOCX document | |
| J-ATTACHMENTS_FBO.zip | ZIP file | |
| J-ATTACHMENT_6_FBO.zip | ZIP file | |
| N3220519R6010_USNS_MEDGAR_ROHDD_FINAL.docx | DOCX document | |
| J_-_14_Technical_Data_Non-Disclosure.docx | DOCX document | |
| SYNOPSIS_N3220519R6010_USNS_MEDGAR_EVERS.docx | DOCX document | |
| MEDGAR_EVERS_ROH_SOURCES_SOUGHT_2019.docx | DOCX document |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Friday, July 19, 2019
QUESTION #1:
Paragraph 1.3 has a table that identifies the pricing format for the work item with four (4) boxes to fill in on pricing, which is in keeping with all recent bid specifications. The J-3 provided has two (2) sections to fill in on pricing as follows. Please clarify.
ANSWER
-------KTR shall price the J-3 accordingly for CAT B Item 025; Price per day and Total for FP Charlie and Delta in accordance with WI 0025 paragraph 1.3; $ cost to establish and $ cost per day to maintain.
QUESTION #2: On the J-3 the item 7.6 is described as “Delivery, Care and Redelivery of the Vessel” which is not covered in the Work Item 030. Please clarify.
ANSWER
-------See attached revised J-3 for WI 030, bid for Continuation of Services for WI 0018 is not required and has been removed. WI 018 is a CAT A item though and shall be bid accordingly per the J-2.
QUESTION #3. Work Item 014 – Weight Report – Trim and Stability Book were not included in the references provided. Please provide.
ANSWER:
Reference was provided for WI 0901. See attached reference
QUESTION #. 4
Specification Item Number: 0360, Paragraph / Section NO: 2.1,Title: OP 4 STOREROOMS LIGHTING UPGRADE Paragraph 2.1 identifies the version of the reference drawing as REV J. The version of the reference drawing provided is REV L. Please confirm that the version REV L provided is the correct version to be used.
ANSWER:
Drawing 331-7488807 REV L is most current version of drawing and is what was provided in references. WI has been red-lined accordingly; see attached REV A of work item reflecting change.
image1.emf
File details come from the government source that posted it.