RFC_016_response.pdf

PDF 258 KB Posted

Attached to
USNS HENRY J. KAISER T-AO 187 MID-TERM AVAILABILITY
Solicitation number
N3220518R4008
Issued by

About this file

RFC 016 RESPONSE

View the file

Other files

File Type Posted
N3220518R4008-0012.docx DOCX document
N3220518R4008-0011.docx DOCX document
RFC_023_J-2_CAT_A_Revised_2.xlsx XLSX spreadsheet
RFC_022_RESPONSE.doc DOC document
RFC_024_RESPONSE.pdf PDF
N3220518R4008-0010.docx DOCX document
RFC_020_RESPONSE.doc DOC document
RFC_021_RESPONSE.doc DOC document
RFC_023_RESPONSE.pdf PDF
J-2_CAT_A_Revised.xlsx XLSX spreadsheet
N3220518R4008-0009.docx DOCX document
KAISER_MTA-19_-_Work_Item_Index_amend_a.docx DOCX document
J-2_Category_A_Items_REV_a.xlsx XLSX spreadsheet
N3220518R4008-0008.docx DOCX document
RFC_018_response.pdf PDF
RFC_019_response.pdf PDF
N3220518R4008-0007.docx DOCX document
RFC_013_response.pdf PDF
RFC_017_response.pdf PDF
N3220518R4008-0006.docx DOCX document
RFC_015_response.pdf PDF
RFC_001_RESPONSE.pdf PDF
RFC_011_response.pdf PDF
N3220518R4008-0005.pdf PDF
J-3_Category_B_Items.xlsx XLSX spreadsheet
N3220518R4008-0004.pdf PDF
RFC_2_response.pdf PDF
RFC_9_response.pdf PDF
RFC_6_response.pdf PDF
RFC_4_response.pdf PDF
RFC_5_response.pdf PDF
RFC_10_response.pdf PDF
RFC_7_response.pdf PDF
RFC_012_response.pdf PDF
RFC_8_response.doc DOC document
N3220518R4008-0003.docx DOCX document
RFC_-_3_response.pdf PDF
KAISER_MTA-19_-_Work_Item_Index_rev_1_AMEND_0004.docx DOCX document
N3220518R4008-U00002.docx DOCX document
18R4008-U00001_MOD.docx DOCX document
J-10_Interport_Differential_rev_1.doc DOC document
J-10_Interport_Differential_rev_1.doc DOC document
N3220518R4008-U00002.docx DOCX document
18R4008-U00001_CONF.docx DOCX document
CDRL,_WI-0012.pdf PDF
J-8_RFC.doc DOC document
J-12_Past_Performance_Data.docx DOCX document
CDRL,_WI-0015.pdf PDF
CDRL,_WI-0011.pdf PDF
J-13_PAST_PERFORMANCE_QUESTIONNAIRE.docx DOCX document
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N3220518R4008

USNS HENRY J. KAISER (T-AO 187)

ATTACHMENT J - 8

REQUEST FOR SPECIFICATION CLARIFICATION

RFC 016

NAME OF CONTRACTOR: Mare Island Dry Dock, LLC

SPECIFICATION ITEM NO.: 107

PARAGRAPH / SECTION NO: 1.1, 2.1.1, 6.1, 7.1.1, 7.1.2 a, b, c, f

TITLE: AFFF SPRINKLER PIPING REPLACEMENT

QUESTION:

1.1 This item describes replacing all existing main deck carbon steel AFFF piping and fittings (2 ½” and below) and internal cleaning of piping above 2 ½” (frame 31-51).

* We recently received 2.1.1 MSC Drawing # 555-6580704 Foam System Diagram and noted the material in this Diagram is CUNI and not carbon steel as stated in 1.1.

Is there an actual DWG for this item with a material list that shows the sprinkler connections also?

Is it the Government’s intent to replace steel with Code 6 CUNI?

6.1 Install all piping in accordance with 2.1 and the applicable rules and regulations of the USCG and ABS?

7.1.1 Mechanically disconnect, remove and clean to bright metal all sprinkler heads affected by this work item using Reference 2.1 sheets 3 and 4 as guidance.

Sprinkler heads shall not be blasted in the cleaning process. Retain the sprinkler heads for reinstallation in 7.3.2.b below.

* There is no 7.3.2 in this specification.

7.1.2 a. Install new AFFF piping (2 ½” and below), valves and associated fittings templating from the existing configuration and locations, using Reference 2.1 as guidance.

* 2.1 is CUNI and existing is carbon steel

Is it the Government’s intent to replace steel with Code 6 CUNI?

N3220518R4008

USNS HENRY J. KAISER (T-AO 187)

ATTACHMENT J - 8

7.1.2 b. Install sprinkler heads removed in 7.3.1.a above, using Reference 2.1 sheets 3 and 4 as guidance. Connect sprinkler head to the system using ½” couplings retained from original installation.

There is no 7.3.1 above 7.1.2. The Diagram shows Code 6 CUNI and existing material is carbon steel. Spec states to reuse couplings retained from original installation.

Are the original couplings steel and put into a CUNI system?

7.1.2 c. Replace with new orifices FF-OR002 and FF-OR003 in 2.1, one each with the following openings: 3 ¾” and 3 7/8”.

Pipe replacement in this item is 2 ½ ‘and below. Are these orifices’ correct?

7.1.2 f. New piping returned to the ship shall be blasted and primed prior to installation.

Does the Government want the CUNI Piping blasted and primed prior to installation?

ANSWER:

henry.robson Typewritten Text MSC does not intent to replace CUNI piping, item has been revised to reflect.

henry.robson

7.3.2 removed from Para 7.1.1.a

7.1.2 Para revised to reinstall AFFF removed.

All AFFF material is CUNI, if piping has to be cut contractor will need to use CUNI coupling to rejoin piping.

All orifices are correct, for orifices removed.

All piping remove shall be blasted and painted, as per item.

See Revised Item henry.robson Typewritten Text