ATTACHMENT M
Contract Data Requirement List (CDRL)
| CONTRACT DATA REQUIREMENT |
| INITIAL SUBMISSION |
| FINAL SUBMISSION |
| Weekly Environmental Control Report (Attachment E-3.5.3.5.1) |
| Weekly |
| Monthly Environmental Control Report (Attachment E-3.5.3.5.2) |
| Monthly |
| Installation Acceptance & General Layout Drawings (Attachment E-3.5.3.8) |
| 60 days from Contract award |
| 60 days after receipt of Government comments |
| Reports & Documentation (Attachment E-8.3) |
| During Vessel on-hire survey |
| Fuel Oil Inventory Reports (Attachment E-12.1.1) |
| Monthly |
| Fuel Consumption Reports (Attachment E-12.1.2) |
| Monthly |
| Voyage/Passage Reports (Attachment E-12.1.3) |
| At the end of each voyage/passage |
| Vessel Self-Assessment (Attachment E-15.1.2) |
| 14 calendar days prior to commencement of OCI inspection |
| Documentation (Attachment E-17.1) |
| 48 hours from Contract award |
| 30 calendar days after receipt of Government comments |
| Ship Drawings (Attachment E-17.2) |
| 48 hours from Contract award |
| 30 calendar days after receipt of Government comments |
| Cargo Handling Equipment List (Attachment E-17.3) |
| 72 hours from Contract award or 24 hours if less than 72 hours away from receiving port. |
| 72 hours from Contract award or 24 hours if less than 72 hours away from receiving port. |
| Delivery Schedule (Attachment E- 17.4) |
| 15 calendar days from Contract award |
| 15 calendar days after receipt of Government comments |
| Vessel Photograph (Attachment E- 17.5) |
| 60 calendar days from Contract award |
| 60 calendar days after receipt of Government comments |
| Insurance (Attachment E-17.6) |
| 10 calendar days from Contract award |
| 10 calendar days after receipt of Government comments |
N32205-18-R-3512
| Small Arms Inventory (Attachment E-18.2.1) |
| Annually |
| Schedule for Delivery of Vessel (Attachment E-17.1.3) |
| 15 calendar days from Contract award |
| Progress Chart (Attachment E-17.1.3) |
| Every 14 calendar days |
| Inventory of Government Property (Attachment A (a)) |
| Annually |
| Training Plan (Attachment H-3.4) |
| 60 days from Contract award |
| Drawing (Attachment I-20) |
| Upon delivery of Vessel |