J-8_RFC_013_-_Item_109_-_Answer.doc

DOC document 39 KB Posted

Attached to
Mid Term Availabilty USNS JOHN LENTHALL Federal contract opportunity
Solicitation number
N32205-16-R-4006
Issued by
Department of the Navy Military Sealift Command

About this file

J-8_RFC 013 - Item 109 - Answer

View the file

Other files for this federal contract opportunity

Other files attached to Mid Term Availabilty USNS JOHN LENTHALL, newest first.
File Type Posted
REDACTED _JnA-RevB _16-C-4006-P00007.PDF PDF
REDACTED-JnA _16-C-4006-P00005 _LENTHALL.PDF PDF
SOLICITATION _16-R-4006-0006 _J.LENTHALL-_Released.doc DOC document
SOLICITATION _16-R-4006-0005 _J.LENTHALL-_Released.doc DOC document
SOLICITATION _16-R-4006-0004 _USNS_JOHN_LENTHALL-_Released.doc DOC document
J-8_RFC_012_-_all_items_Answered.doc DOC document
J-8_RFC__9_-_item_512-Answer.doc DOC document
J-8_RFC__11_-_item_603_-_Answer.doc DOC document
J-8_RFC__10_-_item_511_-_Answer.doc DOC document
J-8_RFC__7_W-I_202_-_Answered.doc DOC document
J-8_RFC__6_W-I_102_-Answered.doc DOC document
J-8_RFC__4_W-I_507_Answer.doc DOC document
J-8_RFC__5 _W-I_1009 _Answered.doc DOC document
J-8_RFC__8_-_Answer _Revision_of_WI_109.doc DOC document
SOLICITATION _16-R-4006-0003 _USNS_JOHN_LENTHALL-_Released.doc DOC document
N32205-16-R-4006-0002.doc DOC document
J-8_RFC__3_-_Answer.doc DOC document
16-R-4006 _Ammendment_1 _JOHN_LENTHALL-_Released.doc DOC document
J-8_RFC__2_-_Answer.doc DOC document
J-8_RFC__1_-_Answer.doc DOC document
JnA_16-R-4006 _FedBizOps_Redacted.pdf PDF
DD_Form_1423-1_SWI-013 6.pdf PDF
DD_Form_1423-1_SWI-016.9.pdf PDF
DD_Form_1423-1_SWI-021 14.pdf PDF
DD_Form_1423-1_SWI-014 7.pdf PDF
SOLICITATION _16-R-4006 _USNS_JOHN_LENTHALL-_Released.doc DOC document
DD_Form_1423-1_SWI-015 8.pdf PDF
DD_Form_1423-1_SWI-010 4.pdf PDF
DD_Form_1423-1_SWI-022 15.pdf PDF
J-14_NON_Discl_Agreement Govnt_Tech-Data.docx DOCX document
DD_Form_1423-1_SWI-018 11.pdf PDF
DD_Form_1423-1_SWI-019 12.pdf PDF
J-7 _MSC-Ship-Rpr-Facility-Surv.pdf PDF
DD_Form_1423-1_SWI-006 3.pdf PDF
DD_Form_1423-1_SWI-001 1.pdf PDF
J-10 _Interport_Differentials _16-4006 .xls XLS spreadsheet
DD_Form_1423-1_SWI-017 10.pdf PDF
J-4 _GFP _16-R-4006.xls XLS spreadsheet
J-13__Past_Perf_Questionaire.docx DOCX document
J-12_Past_Perf_Data.docx DOCX document
DD_Form_1423-1_SWI-023 16.pdf PDF
J-3 _CAT_B.xlsx XLSX spreadsheet
J-9 _Disclsr_Lobbying_Activities_SF-LLL.doc DOC document
J-8_RFC.doc DOC document
DD_Form_1423-1_SWI-004 2.pdf PDF
DD_Form_1423-1_SWI-24 _17.pdf PDF
DD_Form_1423-1_SWI-020 13.pdf PDF
J-1_Item_Index-16-4006.doc DOC document
DD_Form_1423-1_SWI-012 5.pdf PDF
J-2 _CAT_A.xlsx XLSX spreadsheet
Show all 50

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N32205-16-C-4006

USNS JOHN LENTHALL (TAO-189)

REQUEST FOR SPECIFICATION CLARIFICATION

NAME OF CONTRACTOR:

SPECIFICATION ITEM NO.:

PARAGRAPH / SECTION NO:

entire item

TITLE: MAIN DECK STEEL REPLACEMENT

QUESTION:

1.

Despite the reduction in scope in amendment 3 we still do not believe this work can be accomplished in the 43 days allotted for this project. Although the steel work has been reduced, there is still an enormous amount of interference, wrapping and protecting to deal with. In addition, work item 415, added by amendment, involves work on the steering gear which will be inaccessible under protective cover during most of the steel and insulation work. This has the effect of increasing the overall timeline because the two items cannot be accomplished at the same time. We have attached a revised schedule indicating the time we believe will be required, even working on an expedited basis.

2.

We hereby request that the government reconsider the performance period for this availability.

ANSWER:

MSC Thanks you for your request for clarification and the information that you have provide.

MSC is issuing Item 109 REV. C which is reducing the scope of work and placing the steel repair over the Bosn Store Room and the Nixie Room this will reduce the amount of cover up that will need to be accomplished and not interfere with Item 415. MSC can not extend the performance period for the vessel during the MTA.

MSC believe that with the location change that this item should be able to be accomplished in the allowed time period.

ATTACHMENT J - 8