Q_4_Response.pdf
PDF 74 KB Posted
- Attached to
- 2015 MTA on USNS YUKON
- Solicitation number
- N32205-15-R-1000
About this file
Response to Question 4
View the file
Other files
| File | Type | Posted |
|---|---|---|
| J-10_Interport_Differential_Revised.doc | DOC document | |
| Amendment_0002_USNS_YUKON.doc | DOC document | |
| Q_1_Response.pdf | ||
| Q_3_Response.pdf | ||
| Q_2_Response.pdf | ||
| Q_5_Response.pdf | ||
| N32205-15-R-1000-0001_AMENDMENT.pdf | ||
| J-14_NON_DISCLOSRE_AGREEMENT_FOR_GOVN'T_TECHNICAL_DATA_(V1.1 _2-27-14).docx | DOCX document | |
| J-9 Disclosure of Lobbying Activities SF-LLL.doc | DOC document | |
| J-12 Past Performance Data.docx | DOCX document | |
| N104-15-R-1000_J A_Redacted.pdf | ||
| J-10 Interport Differential.doc | DOC document | |
| N32205-15-R-1000_SOLICITATION.pdf | ||
| J-3 Category B Items.xls | XLS spreadsheet | |
| J-13__PAST_PERFORMANCE_QUESTIONNAIRE.docx | DOCX document | |
| J-8 Request for Spec Clarification.doc | DOC document | |
| J-6 WI 015 CDRL.pdf | ||
| J-4 GFP - YUKON.pdf | ||
| J-7 MSC Ship Repair Facility Survey.doc | DOC document |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N32205-15-R-1000
USNS YUKON (T-AO 202)
ATTACHMENT J - 8
REQUEST FOR SPECIFICATION CLARIFICATION
11/12/14
NAME OF CONTRACTOR:
SPECIFICATION ITEM NO.: page 1 SF 33
PARAGRAPH / SECTION NO: 9
TITLE: Solicitation
QUESTION:
Please note that this solicitation was posted on Tuesday, October 28 th
. The bid due date is listed as Friday, November 28 th
. November 27 th and 28 th are Contractor’s holidays. Due to contractor’s mail room issues, contractor did not receive specifications, drawings and references until November 6 th
. Additionally, contractors on the West Coast must mail their proposals two business days before due date to ensure timely arrival.
This gives us 13 business days in which to accomplish a pre-proposal site visit on the
USNS Yukon in San Diego, review specifications and submit bidder’s questions, review amendment responses and assemble our proposal.
Contractor respectfully requests at minimum a one week extension to the request for clarification date and the submission due date.
ANSWER:
Solicitation was amended on 14 November 2014 to change submission due date as well as specification clarification question request date.