Attachment 2 - Contract Surveillance Plan (CSP).docx

DOCX document 59 KB Posted

Attached to
NAWC WOLF TARCES FOLLOW-ON REQUIREMENT SOLICITATION
Solicitation number
N00421-21-R-0116
Issued by

About this file

This document contains a contract surveillance plan and related federal contract opportunity. The contract surveillance plan outlines quality assurance methods for a requirements contract supporting command, control, communications, computer, combat systems, intelligence, surveillance, and reconnaissance systems engineering. It defines roles for the contracting officer, contracting officer's representative, and government project leads in monitoring performance. Oversight will include inspection of deliverables and quarterly evaluations of quality, schedule, cost control, and other criteria. The federal contract opportunity is a follow-on requirements solicitation from the Naval Air Warfare Center Aircraft Division Webster Outlying Field Special Communications Mission Solutions Division. It seeks engineering support for C5ISR systems across various domains and customers, continuing previous efforts.

View the file

Other files

File Type Posted
Attachment P04 - BLS Chart Amend 0001.xlsx XLSX spreadsheet
N00421-21-R-0116 Amend 0001 FINAL.pdf PDF
Attachment P08 - Labor Hours Amend 0001.xlsx XLSX spreadsheet
TARCES Q and A Amend 0001.xlsx XLSX spreadsheet
Attachment 14 - SCMS Division RDTE Network SOP.pdf PDF
Attachment P02 - CPAQ.pdf PDF
Exhibit A CDRLs.docx DOCX document
Attachment P01 - Past Performance Information Form.pdf PDF
Government Responses to Industry Questions FINAL.xlsx XLSX spreadsheet
Attachment 13 - ACOR Designation Letter.docx DOCX document
Attachment 4 - Workforce Reporting Template.xlsx XLSX spreadsheet
Attachment 7 - Small Business Subcontracting Plan.docx DOCX document
Attachment 6 - Data Item Transmittal Form.docx DOCX document
Attachment P05 - Wage Rate Determination.pdf PDF
Attachment 9 - List of Approved Subcontractors.docx DOCX document
Attachment P06 - Cost Summary Spreadsheet.xlsx XLSX spreadsheet
Attachment P04 - BLS Chart.xlsx XLSX spreadsheet
Attachment 5 - Task Order Closeout.docx DOCX document
Attachment 10 - Wage Determination.docx DOCX document
Attachment P08 - Labor Hours.xlsx XLSX spreadsheet
Attachment 3 - Segregation of Costs Format.docx DOCX document
Attachment 16 - Locator Form.docx DOCX document
N00421-21-R-0116 FINAL.pdf PDF
Attachment 11 - OCI.docx DOCX document
Attachment 12 - COR Designation Letter.docx DOCX document
Attachment 15- Non-Navy IT Certification Form.docx DOCX document
Attachment 8 - List of Key Personnel.docx DOCX document
Attachment 1 - DD-254.pdf PDF
Attachment P03 - Fully Burdened Labor Rates.xlsx XLSX spreadsheet
N00421-21-R-0116 DRAFT.pdf PDF
Attachment P08 - Labor Hours.xlsx XLSX spreadsheet
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N00421-18-R-0018 Enclosure (3)

N00421-19-RFPREQ-4K0000T-2323

Enclosure (3)

CONTRACT SURVEILLANCE PLAN FOR

SPECIAL COMMUNICATION RAPID INTEGRATION FACILITY

1. Purpose

This Contract Surveillance Plan (CSP) document is a Government developed and applied document used to ensure systematic Quality Assurance (QA) methods are being used in the administration and surveillance of tasking under the Contract. The intent is to ensure the Contractor performs In Accordance With (IAW) the Statement of Work (SOW), and the Government receives the quality of services called for in each Task Order (TO) SOW.

The Naval Air Warfare Center Aircraft Division (NAWCAD) Webster Outlying Field (WOLF) Special Communications Mission Solutions (SCMS) Division supports the warfighter by providing best value, full-spectrum Command, Control, Communications, Computers, Combat systems, Intelligence, Surveillance, and Reconnaissance (C5ISR) engineering from requirements definition through sustainment within Continental United States (CONUS), and Outside Continental United States (OCONUS). The SCMS Division’s “cradle-to-grave” systems engineering approach ensures interoperability, supportability, and connectivity among fielded equipment. The SCMS Division provides rapid operations and support of C5ISR systems for small/large craft, rotary/fixed wing aircraft, commercial/militarized vehicles, transit cases, mobile communications, fixed based stations, command centers, and intelligence systems. The in-service support for C5ISR systems is funded by a broad range of customers to include the following: uniformed services such as the Navy and Marine Corps, agencies such as the National Guard Bureau and joint services such as United States Special Operations Command (USSOCOM), Central Command (CENTCOM), and European Command (EUCOM).

This Contract will have Cost-Plus-Fixed-Fee (CPFF) Term Contract Line Item Numbers (CLINs) for labor and corresponding cost reimbursable CLINs for Other Direct Costs (ODCs). The Contract will have a five-year ordering period beginning a contract award. A properly executed CSP will assist the Government in achieving the objectives of this procurement.

2. Authority

Authority for issuance of this CSP is provided under Contract Section E – Inspection and Acceptance, which provides for inspections and acceptance of the services, products, and documentation called for in the Contract executed by the Contracting Officer (KO) or a duly authorized representative.

3. Scope

To fully understand the roles and responsibilities of the parties, it is important to first define the distinction in terminology between Quality Control Plan (QCP) and the CSP. The Contractor, and not the Government, is responsible for the QCP, which defines the management and quality control actions necessary to meet the quality standards set forth in the Contract and resultant TOs.

The CSP provides Government surveillance oversight of the Contractor’s efforts to assure they are timely, effective, and delivering the results specified in the Contract and each TO.

4. Government Resources

The following definitions for Government resources are applicable to this plan:

KO: A person duly appointed with the authority to enter into a contract (Procuring Contracting Officer (PCO)), or a person with the authority to administer contracts (Administrative Contracting Officer (ACO)) and make related determinations and findings on behalf of the Government. The DPCO for this Contract is May Dimitrov. The ACO will be designated in the resulting Contract. KOs are designated via a written warrant that sets forth limitations of authority.

Contracting Officer’s Representative (COR): An individual appointed in writing by the PCO to act as their authorized representative to assist in administering the Contract. The COR will be appointed in the resulting Contract. The limitations of authority are contained in the letter of appointment.

Alternate Contracting Officer’s Representative (ACOR): An individual appointed in writing by the PCO to act as their authorized representative, in the absence of the COR, to assist in administering the Contract. The ACOR will be appointed in the resulting Contract. The limitations of authority are contained in a written letter of appointment.

Government Project Lead (GPL): The COR designates individual GPLs to assist in administering of specific efforts under the Contract.

5. Responsibilities

The following Government resources will have responsibility for the implementation of this CSP:

KO: The KO (PCO or ACO) ensures performance of all necessary actions for effective contracting, ensures compliance with the terms of the Contract, and safeguards the interests of the United States in the contractual relationship. The KO that assures the Contractor receives impartial, fair, and equitable treatment under the Contract. The KO is ultimately responsible for the final determination of the adequacy of the Contractor’s performance.

COR: The COR is responsible for technical administration of the Contract and assures proper Government surveillance of the Contractor’s performance. The COR is not empowered to make any contractual commitments or to authorize any changes on the Government’s behalf. Any changes that the Contractor deems may affect the Contract price, terms or conditions shall be referred to the KO for action.

ACOR: The ACOR assists the COR for technical administration of the Contract and assures proper Government surveillance of the Contractor’s performance. The ACOR is not empowered to make any contractual commitments or to authorize any changes on the Government’s behalf. Any changes that the Contractor deems may affect the Contract price, terms, or conditions shall be referred to the KO for action.

GPL: The GPL is responsible for assisting in administering specific efforts under the Contract. A GPL cannot, in any manner, alter the scope of the Contract, make commitments or authorize any changes on the Government’s behalf.

6. Methods of QA Surveillance

a. Contractor Performance Assessment Reporting System (CPARS): The marketplace for providing rapid integration for C5ISR systems on board small and large craft, commercial and militarized vehicles, transit cases, mobile communications, fixed base stations, command centers, and intelligence systems is very competitive. As such, the successful Offeror has a vested interest in the Government generated CPARS under this Contract. Additionally, an evaluation using the CPARS format will be performed at the end of each ordering year. This evaluation will be one (1) determinant in the award of future TOs. The Government will address the quality of product or service, schedule, cost control, business relations, management, utilization of Small Business (SB), and other important areas for this procurement. Some of the monitoring methods to be used will be Government observation, review of reports, customer feedback and review of Contract Data Requirements Lists (CDRLs). As this information may affect future source selections throughout the Department of Defense (DoD), as well as the continuation of this tasking, the annual Government assessment will be used appropriately as an additional performance oversight and communication tool within the policies of this CSP.

b. CSP: This document will be used by the COR, ACOR, and GPLs in the technical administration of this Contract. In addition to the below instructions, the form to be used for documentation of QA surveillance is the Surveillance Activity Checklist (SAC).

7. Surveillance

Enclosure (2) sets forth the performance standards, incentives, and surveillance methods for the Contractor, the COR/ACOR, and GPLs while Enclosures (1) and (3) provide the checklist and means for the COR to document the results of the surveillance and will be provided to the KO.

8. Documentation

In addition to providing reports to the KO, the COR will maintain a complete QA file. The file will contain copies of all reports, evaluations, recommendations, and any actions related to the Government’s performance of the QA function, including the originals of the QA Checklists. All such records will be maintained for the life of the Contract. The COR shall forward these records to the KO at termination or completion of the Contract.

9. Enclosures

Enclosure (1): Surveillance Activity Checklist (SAC) Enclosure (2): Quarterly Evaluation by CDRL Enclosure (3): Annual Surveillance Summary N00421-16-R-0059 N00421-21-R-0116 Attachment 2

Source Selection Information 4 UNCLASSIFIED//FOR OFFICIAL USE ONLY See FAR 2.101 and 3.104

ENCLOSURE (1): SURVEILLANCE ACTIVITY CHECKLIST (SAC)

Quarterly Surveillance:

The COR will perform a quarterly assessment of quality, schedule, cost control, business relations, management, utilization of SB, and other areas as applicable utilizing the CPARS evaluation rating definitions listed in Enclosure (3).

QUARTERLY EVALUATION BY SOW PARAGRAPH

Description
Surveillance Method/Measure
Dates
Quality Assessment
Schedule Assessment
Cost Control Assessment
Business Relations Assessment
Management Assessment
Utilization of SB Assessment
Other Areas Assessment
Provide planning and production engineering support IAW paragraph 3.3.1
100% Inspection by COR/ACOR and/or GPLs
Provide assimilation/kitting, integration, and verification support IAW paragraph 3.3.2
100% Inspection by COR/ACOR and/or GPLs
Provide logistics and in-service support IAW paragraph 3.3.3.
100% Inspection by COR/ACOR and/or GPLs
Provide technical and project management support IAW paragraph 3.3.4
100% Inspection by COR/ACOR and/or GPLs

Enclosure (1)

N00421-19-RFPREQ-4K0000T-2323

Enclosure (1)

Source Selection Information 7 UNCLASSIFIED//FOR OFFICIAL USE ONLY See FAR 2.101 and 3.104

ENCLOSURE (2): QUARTERLY EVALUATION BY CDRL

Description
Surveillance Method/Measure
Dates Due
Dates Completed
No. Submittals
No. of Req’d Rework
Percentage On Time
Comments
A001 – Contracting Officer’s Representative (COR) Management Report for Technical (TDLs)
100% Inspection by COR/ACOR and/or GPLs.
A002 - Contractor’s Progress and Status Report - Financial Progress Report
100% Inspection by COR/ACOR and/or GPLs.
A003 - Contractor’s Progress and Status Report - Contractor’s Personnel Roster/Workforce Report
100% Inspection by COR/ACOR and/or GPLs.
A004 - Report, Record of Meeting/Minutes - Trip/Meeting Report
100% Inspection by COR/ACOR and/or GPLs.
A005 – Government Property (GP) Inventory Report
100% Inspection by COR/ACOR and/or GPLs.
A006 - Phase-Out Transition Plan
100% Inspection by COR/ACOR and/or GPLs.
A007 - Accident Incident Report
100% Inspection by COR/ACOR and/or GPLs.
A008 – NAVAIR Operations Security (OPSEC) Plan
100% Inspection by COR/ACOR and/or GPLs.
A011 - Conceptual Design Drawings/Models - Systems Concepts Documentation
100% Inspection by COR/ACOR and/or GPLs.
A012 - Product Engineering Design Data and Associated Lists
100% Inspection by COR/ACOR and/or GPLs.
A014 - Technical Report – Study Services – Technical Manuals and Materials
100% Inspection by COR/ACOR and/or GPLs.
A015 – Job Manual – Operations and Maintenance Manuals and Materials
100% Inspection by COR/ACOR and/or GPLs.
A016 – Training Materials – Operator Training Manuals and Materials and Course Curriculum
100% Inspection by COR/ACOR and/or GPLs.
A017 - Test Plan
100% Inspection by COR/ACOR and/or GPLs.
A018 – Test Procedure
100% Inspection by COR/ACOR and/or GPLs.
A019 - Test/Inspection Report
100% Inspection by COR/ACOR and/or GPLs.
A020 - Integrated Logistics Support (ILS) Plan
100% Inspection by COR/ACOR and/or GPLs.
A021 - Supplier’s Configuration Management Plan
100% Inspection by COR/ACOR and/or GPLs.
A022 - Engineering Change Proposal (ECP)
100% Inspection by COR/ACOR and/or GPLs.
A023 - Program Management Plan - Project Requirements
100% Inspection by COR/ACOR and/or GPLs.
A024 - Configuration Audit Plan
100% Inspection by COR/ACOR and/or GPLs.
A025 - Production Report
100% Inspection by COR/ACOR and/or GPLs.
A026 - System/Subsystem Specifications (SSS) - Design Engineering Report
100% Inspection by COR/ACOR and/or GPLs.

Metric Summary:

Current Period

Cumulative

Total Number of Deliverables Submitted:

Total Number of Deliverables Submitted Late:

Total Number of Deliverables Requiring Revision:

Percentage of Deliverables Submitted Late:

Percentage of Deliverables Requiring Revision:

Enclosure (2)

N00421-19-RFPREQ-4K0000T-2323

Enclosure (2)

ENCLOSURE (3): ANNUAL SURVEILLANCE SUMMARY

The COR will perform an assessment of overall contract performance utilizing the CPARS evaluation rating definitions listed in Enclosure (3). This assessment will be completed annually covering the previous twelve (12) months.

Description
Surveillance Method/Measure
Date Planned
Date Completed
Summary Rating/Results
Quality of Product or Service
Review of Quarterly Ratings
Schedule
Review of Quarterly Ratings
Cost Control
Review of Quarterly Ratings
Business Relations
Review of Quarterly Ratings
Management
Review of Quarterly Ratings
Utilization of SB
Review of Quarterly Ratings
Other Areas
Review of Quarterly Ratings

Annual Surveillance Completed By: _______________________

Date Completed: ________________

All SOW and CDRL tasks, including sub-tasks, will be assessed focusing on the following.

Quality of product or service: Assess the Contractor’s effort to transform operational needs and requirements into an integrated solution. Areas of focus may include the planning and management of program tasks, the quality of support provided throughout all phases of contract execution, the integration of program management specialties, management of interfaces and the management of a totally integrated effort of all program management concerns to meet cost, performance and schedule objectives. Assess how successfully the Contractor meets program quality.

Schedule: Assess the Contractor’s adherence to the required delivery schedule by assessing the Contractor’s efforts during the assessment period that contribute to or effect the schedule variance. Also address significance of scheduled events (i.e., design reviews), discuss causes, and assess the effectiveness of Contractor corrective actions.

Cost control: Assess the Contractor’s effectiveness in forecasting, managing and controlling contract cost. Is the Contractor experiencing cost growth or under-run? If so, discuss the causes and Contractor proposed solutions for the cost overruns. For contracts where task or contract sizing is based upon Contractor provided person hour estimates, the relationship of these estimates to ultimate cost should be assessed. In addition, the extent to which the Contractor demonstrates a sense of cost responsibility, through the efficient use of resources in each work effort should be assessed.

Business relations: Assess the timeliness, completeness, and quality of problem identification, corrective action plans, proposal submittals, the Contractor’s reasonable and cooperative behavior, effective business relations, and customer satisfaction.

Management: Assess the Contractor’s success with timely award and management of subcontracts, including whether the Contractor met small/small disadvantage and women-owned business participation goals. Discuss the extent to which the Contractor discharges its responsibility for integration and coordination of all activity needed to execute the Contract; identifies and applies resources required to meet schedule requirements; assigns responsibility for tasks/actions required by contract; communicates appropriate information to affected program elements in a timely manner. Assess the Contractor’s risk mitigation plans.

Utilization of SB: The Request for Proposal (RFP) and FAR Subpart 19.7 and 15 U.S.C. 637 contains statutory requirements for complying with the SB Subcontracting Program. Assess whether the Contractor provided maximum practicable opportunity for SB (including Alaska Native Corporations (ANCs) and Indian Tribes) (including Small Disadvantaged Businesses (which also includes ANCs and Indian Tribes), Women Owned SBs (WOSBs), HUBZone, Veteran Owned SBs (VOSBs), Service Disabled Veteran Owned SB (SDVOSB), and ANCs and Indian Tribes that are not Small Disadvantaged Businesses (SDBs) or SBs to participate in contract performance consistent with efficient performance of the Contract. Evaluation will focus on the metrics of actual SB utilization as compared to the Contract required targets and the Contractor’s submitted SB plan.

Other areas: Assess additional evaluation areas unique to the Contract or that cannot be captured elsewhere.

The evaluation ratings are as follows:

Exceptional Performance: Performance meets contractual requirements and exceeds many to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.

Very Good Performance: Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

Satisfactory Performance: Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

Marginal Performance: Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being evaluated reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.

Unsatisfactory Performance: Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.