N0040620R0004 Amendment 0004.pdf
PDF 200 KB Posted
- Attached to
- Telecommunication Support Service Federal contract opportunity
- Solicitation number
- N0040620R0004
About this file
This document is an amendment to a solicitation for telecommunication support services. The amendment extends the proposal due date from March 10 to March 12, 2020. It provides answers to questions from potential offerors regarding the scope of work, historical workload at each site, equipment requirements, and information assurance qualifications for personnel. Key details include that the Navy will require ISP and OSP technician support at several stations in the Naval Computer and Telecommunications Area Master Station Pacific Detachment Puget Sound area of responsibility. Offerors should include all necessary tools, vehicles, and test equipment in their fixed-price proposal as the government will only provide existing telecommunications networks, computer equipment, and replacement parts.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N0040620R0004 Amendment 0005.pdf | ||
| N0040620R0004 Amendment 00003.pdf | ||
| N0040620R0004 Amendment 00002.pdf | ||
| N0040620R0004 Amendment 00001.pdf | ||
| Revised DD 254.pdf | ||
| N0040620R0004 SOL.pdf | ||
| DD 254.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
This amendment is issued to address one question and extend the proposal due date to 12 March 2020. The point of contact for this amendment is James Wasson at james.w asson@navy.mil.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 7
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 06-Mar-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N0040620R0004
X 9B. DATED (SEE ITEM 11)
07-Feb-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
06-Mar-2020
CODE
NAVSUP FLC PUGET SOUND
467 W STREET, 2ND FLR
ATTN: JAMES WASSON
BREMERTON WA 98314
N00406 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N0040620R0004
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SECTION SF30 - CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 10-Mar-2020 02:00 PM to 12-Mar-2020 02:00 PM.
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
QUESTIONS AND ANSWERS
1. Question: Will the Navy be willing to sponsor a vendor for a Facility Clearance?
Answer: Yes, NCTAMS will sponsor a vendor for a Facility Clearance.
QUESTIONS FROM SITE VISIT
1. Can both the Prime plus the Sub submit up to three past performances?
‐ This solicitation was issued under FAR 13.5. In accordance with Section L, addendum to 52.212‐1 (Submittal Requirements), and Section M, 52.212‐2 (Evaluation), only the offeror’s past performance submittals will be evaluated for the trade‐off evaluation.
2. Will the Government please provide a plug‐in number to cover the price of tools, test equipment, and leased vehicles?
‐ This requirement is a firm‐fixed price service contract. Contractor’s are expected to already have this equipment or procure it to perform the services. These costs are generally already part of a companies Overhead.
3. How often are fiber pulls done?
‐ Everett: N/A, no fiber pulls are expected.
‐ Whidbey Island: Assist with pathway twice on previous contract ‐ Hospital: Rare, none are currently expected.
4. How many maintenance actions at Bangor?
‐ See Attachment 2. Historically, a total of 8 maintenance actions at this location.
5. What types of phones are used at each site.
‐ Everett: Avaya digital 2410, 2420 and standard 500 type analog sets ‐ Whidbey Island: Meridian M2000 Series, Meridian M3000 Series and Analog Devices ‐ Hospital: 2410, 2420, 2500, 7406, 7407, 7444, 8410
6. How many buildings at each site?
‐ Everett: 80 buildings including Marysville and Jim Creek ‐ Whidbey Island: 325 Buildings (Ault Field:300, Seaplane Base:25, Outlying Field Coopville:3) ‐ Hospital: 10 Buildings
7. How many manholes at each site?
‐ Everett: 50 manholes including Marysville and Jim Creek ‐ Whidbey Island: 180 Manholes (Ault Field:125, Seaplane Base:55) ‐ Hospital: NA
8. How many closets at each site?
‐ Everett: 100 closets in Everett including Marysville and Jim Creek ‐ Whidbey Island: 425 Closets ‐ Hospital: 25 Closets
9. How many Ring Downs at each site
‐ Everett: Zero ‐ Whidbey Island: 25 ‐ Hospital: 5
10. What type of voicemail is used at each site?
‐ Everett: Callegra Voicemail System ‐ Whidbey Island: Nortel Callpilot 703T V2.02 ‐ Hospital: Audix CMM 5.2‐9.5
11. Are there DSN trunks at each site?
‐ Everett: 2 ‐ Whidbey Island: 3 ‐ Hospital: 1
12. Is the vendor required to get an ATO for any of the products
‐ No, ATO for Avaya already in place.
13. Is there any VOIP?
‐ No VOIP currently in use.
14. What software release is used at each site
‐ Everett: CM4 software version R014x.00.2.732.1 ‐ Whidbey Island: Release 25 ‐ Hospital: CM4 software version R014x.00.2.732.1
15. Will there be access to Cut Sheets and Data Sheets
‐ Records are available in CAIRS telephone records system
16. How many PRI’s are there at each site ‐ Everett: 8 ‐ Whidbey Island: 18 ‐ Hospital: 11
17. How many 110 blocks vs 66 blocks are there
‐ Everett: 40 ‐50 blocks, most are 66 blocks others are on patch panels ‐ Whidbey Island: Fifty percent 110 block, older buildings are 66 and newer buildings are 110.
‐ Hospital: Closets are mostly 66, demark and new installs have 110. 75% 66 block.
18. Is there required training for entrance of man hole covers/ who provides?
‐ Yes, the contractor is responsible for all confined space training to its employees.
19. How is scheduled maintenance tracked?
‐ Maintenance is logged in the Master Station Log (MSL).
20. Who coordinates any required pumping of the man hole covers?
‐ Base Communications Officer (BCO) office
21. How many users at each site?
‐ Everett: 2,070 (approximately 1,370 digital and 700 analog) ‐ Whidbey Island: 5,300 (approximately 2,300 digital and 3000 analog) o Ault Field: 2033 digital, 2540 analog o Seaplane: 70 digital, 137 analog o Ault Hospital: 231 digital, 309 analog o Outlying Field Coopeville: 6 commercial
‐ Hospital: 1,600 (approximately 1,000 digital and 600 analog)
22. Are all the phone lines at each site on the same prefix?
‐ Everett: Yes, prefix 425‐304 ‐ Whidbey Island: Yes, prefix 257 ‐ Hospital: Yes prefix 475, but there are 10 lines on prefix 813 for testing.
23. What are the requirements for personnel and vehicle flight line access?
‐ Free 3 hour flight line driving class is required to be able to drive/park on flight line.
24. Are all the buildings easy to access? Do any require special requests prior to entry?
‐ Everett: A common key is required for all telephone rooms, other facilities require request for entry.
‐ Whidbey Island: No, some buildings are more secured than others or have limited access hours.
Tenant provides escort if needed.
‐ Hospital: Easy access, no special requirements
25. About how many tickets are submitted each month
‐ Everett: Approximately 30 ‐40/month tickets both trouble and work orders ‐ Whidbey Island: Average of 175 ‐ Hospital: Approximately 30 ‐40/month
26. Who is responsible for the purchases of phones.
‐ The government tenant command at each location is responsible for purchasing phones.
27. How often are the cut sheets updated on CAIRS?
‐ Daily
28. What type rack manufacture are used at the sites.
‐ Everett: Standard network systems rack suitable for space and design.
‐ Whidbey Island: CPI Chatsworth & Panduit ‐ Hospital: CPI server rack, 5 Definity cabinets
29. Who is responsible for the up keep, producing and storage of all base communication drawings (AutoCAD)
‐ Naval Facilities Command (NAVFAC)
30. IRT the solicitation who is responsible for IA(system updates, patches, virus protection, and entering results in VRAM) for the Avaya CM4?
‐ NCTAMS Command Security Manager is responsible for security updates to PBX terminals.
31. Will the contractor be required to dispose of any data retention equipment or media?
No, NCTAMS Command Security is responsible.
32. Are any drawings available for the sites.
‐ Yes. Drawings are available for Everett and Whidbey Island. These are for official use only and can be requested by email to James.wasson@navy.mil.
QUESTIONS 04 March 2020
1. Additional clarification concerning “Telecommunications Equipment” (PWS 3.2.2) vs “Test Equipment” (Q&A #2 – Amend 0002). PWS 3.3.2 states, Telecommunications Equipment: The Government will furnish the telecommunications equipment for use by the Contractor. All Contractor-provided equipment, associated software, and documentation shall become Government property upon termination of this contract. All property is tracked by Government inventory.
- The government has consumable telecommunication equipment and replacement parts that will be inventoried and made available to the contractor for maintenance and service of the telecommunication systems under this PWS. CLIN 0002 is provided for a not to exceed amount of $115,000.00 to purchase hardware, replacement/repair parts or consumables that become part of the telecommunications system. Telecommunication equipment purchased under CLIN 0002 is expected to be government property.
2. Are we to understand this to mean that “Telecommunications Equipment” refers to hardware and software, while “Test Equipment” are tools used to test the Telecommunications Equipment?
- Confirmed.
3. As such, the contractor is expected to include the costs for ALL Vehicles, Tools and Test equipment, including items such as: Trimble GPS Systems, Tuggers, Cat 6 Testers and Fiber Probes, Fusion Splicers, Cable Trailers, Cable Locators, Manhole Retrieval Systems and Gas Testers, Duct Routers, Splicing Tools, Fiber Splice Kits, Trench Compactors, Generators, Cable Splicing Tools and Tents, Blowers, Submersible Pumps, TDRs, etc, and whatever else is needed in its Firm Fixed Price CLIN x001 price and not to separately change the Government for such costs/expenses?
- Yes. Tools, test equipment, and vehicles should be part of the overhead. Any trenching will be done by
Naval Facilities and there are environmental and superfund sites to be considered. Equipment that is not for routine use (i.e. submersible pump, generator, blower, tent, etc.) can be approved for rental under CLIN 0002 by the BCO (COR) or other Navy assets may be available to the BCO such as NAVFAC for pumping flooded manholes.
4. Can the Government please confirm where the data in Attachment 2 “Historical Level of Effort” was derived from?
- The data was derived from the government historical work orders.
5. The data only appears to be a partial record of hours associated with services performed and must not account for all hours of personnel necessary. Are these estimated historical hours per year “only” referring to “actual touch time” or “productive or tool turning time” used during corrective actions? If using an average man-year of 2080 hours, this would result in only 3.5 FTEs per year.
- Yes, these only account for estimated time to complete the work orders.
6. It appears these hours must not account for “non-productive time”, such 1 FTE associated with the Site
Manager in PWS 1.2.6 “The Contractor shall designate one individual with primary duties as the Site Manager”, or ISP and OSP Technician’s administrative time processing paperwork/task orders, driving to locations, coordinating service calls with customers, ordering/receiving/inventory/returning parts/materials, holiday, vacations, sick leave, etc. which would yield a considerable higher FTE count than that which is referenced in Attachment 2. Would the Government please confirm if this understanding is correct? The historical FTE requirements for this effort are considerably higher than would otherwise be contrived from the Attachment 2 data.
- Confirmed; administrative time and any travel time is not accounted for in the historical level of effort.
Note: 1.1.4 An ISP technician is required at three locations.
7. Our Avaya distribution channel is telling us that the sold to numbers for the Avaya systems at Bremerton and Everett are at CM4 so SA does not qualify. Page 18 task Q of the solicitation states, “Contractor must procure AVAYA SUPPORT ADVANTAGE coverage”. Please provide clarification. Upon further review of the amendment 0002 did not see any Q&A related to Avaya SA coverage.
- The PWS is updated to remove Q. It is confirmed that the CM4 is no longer covered under Avaya
Support Advantage and cannot be purchased for these systems. The requirement for the contractor to be an Avaya Partner remains.
8. Can the Government please confirm the incumbent contract requires all personnel to meet 8570 requirements, per 2.2.2 Information Assurance Work Force (IAWF)?
- Current PWS states for all personnel to meet the requirements of 8570.01-M
6. Can the Government please confirm/clarify whether Attachment 1 is describing the requirements for all personnel on contract for their respective labor category, or is Attachment 1 outlining minimum requirements for Key Personnel?
- Attachment 1 references 8570.01-M IAT Level II; baseline certifications one of which is Security+ which is preferred
7. Can the Government please confirm whether all personnel (multiple FTEs per Labor Category) are considered “Key Personnel?”
- Yes, all proposed personnel will fall under Key Personnel
8. Per 3.2.1 and 3.2.2 of the PWS, all Terminal and Telecommunications equipment is to be Government-Furnished Equipment. Per the response to answer #2 in Amendment 2, can the Government please clarify what equipment the Government expects Contractors to have and utilize in performance of this contract? For example, can the Government please provide the List of Equipment it will provide to the Contractor under 3.2.1 and 3.2.2 so offerors can better understand the delineation point of the Government’s definition of “All Telecommunications Equipment,” to help mitigate risk for offerors under the terms of this Fixed Price contract?
- The government will provide a computer and NMCI seat for access to email and CAIRS, office space, existing telecommunications network, and consumables (such as; extra copper/fiber line, spare replacement parts for existing equipment) which will be inventoried during the phase in period.. The contractor should have all tools, test equipment to perform testing on copper/fiber, and vehicles to go from base to base when necessary to do jobs. (PWS 1.1.1)
9. What is the anticipated impact of the coronavirus outbreak in nearby King County on the performance of this contract, and what are escalation points the Navy will assess in terms of contractor-related impacts (base closures, telecommuting policies, etc.).
- We currently do not have any areas we perform services in King County. We will follow what the Region dictates regarding the Corona Virus and how it will affect us.
QUESTIONS 06 March 2020
1. In ATTACHMENT 1, Personnel Requirements for Labor Categories, 3. Outside Plant (OSP) Technician (Key Personnel--Resume Submission and Approval Required), requires “IAT Level II Certified IAW DoD 8570.01-M.”
However, 2.2.2 IAWF only requires IAT Level II, Security+ certification for “employees operating and maintaining
. . . Switches.” Can the Outside Plant (OSP) Technicians be exempted from IAT Level II Certified IAW DoD 8570.01-M, so long as they are not operating or maintaining the NCTAMS PAC DET PS DSN Switches?
- OSP Technicians that do not operate or maintain switches are not required to have IAT Level II, Security+ certification. Please note on the Key Personnel list that they are proposed only as OSP work.
(End of Summary of Changes)