Industry Day Presentation_28-30-32_Final.pdf

PDF 1 MB Posted

Attached to
TIH 28/30/32 Industry Day
Solicitation number
N0025326R7001
Issued by

About this file

This document is an Industry Day presentation for the Technology Insertion Hardware (TIH) 28/30/32 procurement by the Program Executive Office, Undersea Warfare Systems (PEO UWS). The procurement aims to provide the latest generation hardware for submarine combat systems across multiple platform types, including OHIO, 688i, VIRGINIA, COLLINS, COLUMBIA, and AUKUS submarine classes. The contract will be a Full and Open Competition with an Indefinite Delivery/Indefinite Quantity (IDIQ) contract type, using Cost Plus Incentive Fee (CPIF) for engineering services and CPIF/Fixed Price Incentive (FPI) for hardware procurement.

Key details include a planned 9-year period of performance, with the expected Request for Proposal (RFP) release in November 2025 and contract award anticipated in Spring 2027. The technology insertion process focuses on rapid commercial-off-the-shelf (COTS) hardware insertion, aiming to minimize obsolescence, ensure system improvements, and create efficiencies across submarine warfare systems. The procurement will cover hardware components such as computer processing, memory, data storage, input/output interfaces, and virtualization, with the goal of standardizing technology updates across submarine platforms approximately every 2-4 years.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNCLASSIFIEDUNCLASSIFIED

Technology Insertion Hardware 28/30/32 Industry Day Full and Open Competition

Hannah Ross Procuring Contracting Officer

NUWC Division Keyport

CAPT David C. Vehon, USN

Program Manager

PEO UWS, PMS 425

Christina Walsh Deputy Program Manager

PEO UWS, PMS 425

UNCLASSIFIED

Distribution Statement A: Distribution authorized for Public Release

Industry Day Agenda

• Welcome- CAPT Vehon

• Rules of Engagement

• Team Overview

• Technology Insertion Overview

• Traditional Rapid COTS Insertion Model

• SWFTS Re-Architecture Overview

• Implementation

• Tech Insertion Process

• Procurement Concept

• RFP Projected Schedule

• Break

• Q&A and Concluding Remarks

• This briefing is for informational purposes only, in accordance with the latest Government Plan, to enhance Industry’s understanding of the Program Executive Office, Undersea Warfare Systems (PEO UWS) Technology Insertion Hardware (TIH) program and process

TI-28, TI-30, and TI-32 procurement (TIH 28/30/32)

• If issued, the formal solicitation requirements and terms and conditions govern in any procurement oFormal solicitation may differ depending on results of Industry and

Government exchanges

• Industry Day slides will be posted to SAM.gov

Disclaimer

Introduction

• Purpose of this Industry Day oProvide an element of Market Research o Inform Industry on the Technology Insertion Hardware (TIH) 28/30/32 procurement and contracting strategy oSeek feedback from Industry

Rules of Engagement

• All questions should be submitted in writing using the question sheets located at the Registration Desk

• At the conclusion of the presentation, the Government will review the questions submitted following the scheduled break

• The Government will respond to as many questions as possible, however some questions may need additional research in order to properly respond to Industry’s concerns

• Questions and Answers will be posted to SAM.gov

• Side bar discussions with Government personnel are not allowed

• The Government reserves the right to generate a solicitation for this effort

TIH 28/30/32 Team Overview

NUWC DIVISION KEYPORT – CONTRACT HOST

Email: KYPT_TeamSub_TIH@navy.mil

Contracts Team

PCO

Hannah Ross

Contract Specialist Lesley Grafe

Katie Harrigan

Technical Team

PMS425 APM

Ryan Barnard

TDA- NUWC NPT

Christopher Plezia & Scott Aubuchon

UNCLASSIFIED

Distribution Statement A: Distribution authorized for Public Release

COR Team

COR

Chris Halterman

ACOR

TBD

NUWK KPT Proj. Lead Megan Vogt

NUWC KPT Proj. Support Jonathan King

Jen Calkins

PMS425 Deputy APM Shannon Meland

Why Technology Insertion?

• Support Rapid COTS Insertion (RCI) Goals o Keep pace with technology o Minimize obsolescence o Ensure continuous opportunity for system improvements

• Standardize the method for regular updates o Migrate technology on Model Year approach across platform types > target every ~2 years o Incorporate plan for an individual platform technology upgrade cycle > target every 4-6 years (every other TI)

• Develop a system that delivers best value to the Government o Achieve tighter coupling between design/development, and subsequent production for increased cost savings o Consolidate number of processing, network and OS variants as technology allows o Utilize low-cost commodity elements and minimize non-recurring effort for hardware

• Create efficiencies, reduce risk, and improve overall system reliability o Provide the mechanical infrastructure to ease technology migrations o Minimize shipyard / platform impacts

• Follow market trends of commercial products

• TIH makes up the vast majority of the Combat Control System (BYG-1) shipset and is also a part of the Sonar shipset

• TIH delivers submarine combat system hardware to the entire USN submarine fleet and Royal Australian Navy (RAN) Collins Class submarine fleet

• Warfighters depend on BYG-1 to perform all functions onboard a Submarine including but not limited to:

oSafely navigate oTrack and target surface and subsurface contacts oConduct Tomahawk and Harpoon strike planning oConduct Intelligence, Surveillance, and Reconnaissance (ISR) oConduct Special Operation Forces (SOF) missions

Importance of TIH to the Fleet

TIH Customers

UNCLASSIFIED

Distribution Statement A: Distribution authorized for Public Release

• PMS425/PMS450/PMS397: AN/BYG-1 NRE, production, field engineering support, Onboard Repair Parts (OBRP), spares, and pre-cable kits

• PMS401/PMS450: Select Submarine Sonar System (ARCI) NRE and production

• PMS425 RAN: Royal Australian Navy (RAN) AN/BYG-1 NRE, production, select spares

• PMS435: Spares procurement

• PMS415: CSA and WSQ-9 hardware

• AUKUS: Potential AN/BYG-1 NRE, production, select spares

Submarine Acoustic

Systems (PMS401)

Submarine

Electromagnetic

Systems (PMS435)

Undersea

Defensive Warfare

Systems (PMS415)

VIRGINIA Class

(PMS450)

COLUMBIA

Class

(PMS397)

SWFTS Project

Office

(SUB-S)

Submarine Combat and Weapons Control

Systems (PMS425)

AUKUS

Examples of Existing TI Hardware

ECDWS MFS

AEC ATC

HDW

ECDWS: Enhanced Control Display Workstation HDW: Horizontal Decision Workstation MFS: Multi-Function Server DDW: Decoupled Display Workstation

AEC: Auxiliary Equipment Cabinet ATC: Advanced Tactical Console CSA: Countermeasure Set, Acoustic

CSA

DDW

What Is TIH 28/30/32?

• TIH 28/30/32 contract will provide the latest generation hardware to Team Submarine platforms

• Anticipated components include oComputer processing and memory oData storage and extraction o Input/Output (I/O) interfaces to support processing systems designed around commercially available hardware and software o Implementation of virtualization

• Procurements may include oUpgrade kits, enclosures, and/or full-up systems for the OHIO Class, 688i

Class, VIRGINIA Class, COLLINS Class, COLUMBIA Class, and AUKUS

• TI-28 VA and 688i will be build-to-print from TI-26 design

• TI-28 OH and CLB will require NRE design effort

• TI-30 and TI-32 will be a full new design for all variants

Traditional Rapid COTS Insertion

• Keep pace with technology

• Minimize obsolescence

• Ensure continuous opportunity for system improvements

Goals

• Plan of Record: TIs fielded every two years; individual boat upgrades every four-six years

• Maintains production industrial base

• Ensures trained personnel for manufacturing and testing

• Uses “state of the practice” hardware vice “state of the art”

• Ensures broad industry support and competitive pricing

Year 1

Year 2

Year 3 Year 4

Year 5 Year 6

TI Kit Procurement

Year 7

Kit Installation

TI-X + 3

4-6 years between individual boat Tech

Insertions

TI-X + 1

TI-X + 2

TI-X

Uninterrupted Cycle of Tech Insertion Procurements and Installations

TI22 TI24 TI26

APB23 APB25 APB27APB21

TI20

• SWFTS is made up of PMS425 (combat control system), PMS401 (sonar), and PMS435 (imaging and electronic warfare)

• Focus on “commonality” oCommon infrastructure oCommon architecture and software oCommon COTS components oCommon mounting oCommon documentation oCommon Software (drivers & diagnostics)

Submarine Warfare Federated Tactical System (SWFTS) Background

• Purpose: Allow for quicker modernization of SWFTS hardware systems and allow for rapid capability fielding to the fleet

• How:

oDecouple hardware and software by designing hardware for future growth, and designing software to be hardware agnostic

▪ Continue movement of SWFTS functions into cloud-based infrastructure via containers

▪ Decouple delivery process from redelivering full subsystem builds to allow for more granular application redelivery oCommon Infrastructure and resources

▪ Continue the movement of subsystem containerized functions and hardware resources into the Common Computing Environment (CCE)

▪ Common Hardware among SWFTS systems

• By achieving SWFTS Re-architecture, the Rapid COTS Insertion model will change allowing all future software builds (APBs) to be fielded on all compatible hardware builds (TIs)

• Enables potential reduced deckplate scope during modernizations

SWFTS Re-architecture

Implementation

• Approximately 7-14 Platform upgrades per year including new construction units

• Individual platforms typically receive every other TI oUpgrades every 4 to 6 years

• Reduced non-recurring effort for hardware development, training, and logistics products

• First Technology Insertion (TI) introduction occurs approximately 1st quarter every odd Calendar Year (CY)

• Combat Control, Sonar, Common Infrastructure Services (CIS), Integrated Submarine Imaging System (ISIS), and Electronic Surveillance (ES) installations are aligned

Technology Insertion: Process

• Perform TI Trade Studies with all of SWFTS to evaluate and down-select promising technology

• Coordinate with subsystems via the SWFTS Architecture IPT (A- IPT) and Hardware Platform & Components Architecture Working Groups (AWG) to develop the common infrastructure which includes both HW and SW architectures and components (physical, network, OS, etc.)

• Supports the development of the hardware Bill of Materials (BOM) and the development of the physical interfaces to support subsystems’ design and build requirements

• TIH prime is a stakeholder and participant throughout the process

PEO UWS Technology Insertion process drives Non-Propulsion Electronic Systems (NPES) HW selection for both TIH and non-TIH procured HW

TI Process ≠ TIH

Defining the Product How do we tell you what we need?

INITIAL REQUIREMENTS

Program Offices establish requirements for their TI baselines

• Power, weight, cooling

• Installation

• Variants required

• Functionality / capability

• Cost threshold

TIH Contract Relevancy

• Contractor early involvement

• Participate in A-IPT & work with PARMs to develop early design concepts & requirements

• Contractor will be provided GFI:

o Technical Data Package (TDP) o Installation Control Drawings (ICD) o Configuration Item Specification

(CIS)

• Contract Vehicle o CPIF for NRE/Development

• Desire for:

o Technology innovation, evolution & commonality o Flexibility o Teamwork o Ease of construction / installation o Ease of maintainability o Reduced Total Ownership Cost

Combat Control, Sonar, ISIS/EW

DESIGN & DEVELOPMENT

The SWFTS Architecture IPT (A- IPT) is the overarching group that leads SWFTS Hardware and Software Development

The A-IPT is broken into Hardware Platform &

Components Architecture Working Groups (AWG) to conduct initial design and development

• Processing / Storage

• Network / Time

• Cabinet (Backup Included)

• Displays & OMI (HW)

• Hotel Services

• Platform Metrics & Modeling

PARM Reps System Developers TIH Contractor

Building and Testing

Building & Testing Hardware

• Develop build & test procedures

• Initiate logistics development

• Procure COTS HW for PARM early I&T

• Build Engineering Development Models

(EDM)

• Develop plan for EQT; conduct EQT testing (if applicable)

• Accomplish performance testing against specifications

• Incorporate feedback into design and

ILS

• Interface with PARMs and A-IPT on all efforts

TIH Contract Relevancy

• Contract Vehicle o CPIF for Development / Procurement of EDMs and advanced integration hardware

• Desire for:

o Flexibility o Teamwork / cooperation o Workmanship and reliability o First pass quality

18UNCLASSIFIED

Producing Hardware

Transition to Production

• Complete design

• Prepare final production drawing package for orderable configuration

• Complete ILS

TIH Contract Relevancy

• Contract Vehicle o CPIF/FPIF for production

• Desire for:

o Quality o Cost o Schedule o Workmanship o Reliability

Hardware Production

• Produce kits, enclosures or other hardware as required

• Factory Acceptance Testing

• Work with vendors

Installation & Field Support

• Install kits or hardware

• Provide support services for installed hardware

Procurement Concept

• Type of Award oFull and Open Competition

• Contract Type o IDIQ Contract, D-Type for Engineering Services, Production and Support

• Contract Incentives oCost Plus Incentive Fee (CPIF) for Engineering and Technical Services oCost Plus Incentive Fee (CPIF)/Fixed Price Incentive (FPI) for Hardware Procurement/Production

• Period of Performance anticipated to be 9 years

• Proposal due 30-45 days from RFP release

Additional Information

• Performance Work Statement (PWS) posted on SAM.gov

• Next Steps oElectronic Technical Information Center (ETIC) in process for posting of technical documentation oETIC availability and access procedures will be posted on SAM.gov

• Tentative Schedule oExpected RFP release: November 2025 oExpected Contract Award: Spring 2027

1. Ideas from industry for innovation, improvements in agility (technical?)

2. Comment on any current or potential technical, cost, schedule or performance risks that you would like to make the Government aware of as it relates to the requirement.

3. Recommendations/feedback on the statement of work.

4. Based on the SOW/presentation and your review of the plans and specifications, what are your top 3 overall project concerns?

5. Comment on any fee structure or cost sharing ratios that might incentivize the offeror to submit a proposal in response to the solicitation.

6. Provide any additional feedback that you feel is relevant.

• Additional questions were requested in the Industry Day registration form

UNCLASSIFIED 22

Contracts Questions

Break

At this time, please submit all questions at the Registration Desk

Questions and Answers Session and

Concluding Remarks

Slide 1: Technology Insertion Hardware 28/30/32 Industry Day Full and Open Competition
Slide 2: Industry Day Agenda
Slide 3: Disclaimer
Slide 4: Introduction
Slide 5: Rules of Engagement
Slide 6: TIH 28/30/32 Team Overview
Slide 7: Why Technology Insertion?
Slide 8: Importance of TIH to the Fleet
Slide 9: TIH Customers
Slide 10: Examples of Existing TI Hardware
Slide 11: What Is TIH 28/30/32?
Slide 12: Traditional Rapid COTS Insertion
Slide 13: Submarine Warfare Federated Tactical System (SWFTS) Background
Slide 14: SWFTS Re-architecture
Slide 15: Implementation
Slide 16: Technology Insertion: Process
Slide 17: Defining the Product How do we tell you what we need?
Slide 18: Building and Testing
Slide 19: Producing Hardware
Slide 20: Procurement Concept
Slide 21: Additional Information
Slide 22: Contracts Questions
Slide 23: Break
Slide 24: Questions and Answers Session and Concluding Remarks