SOW_Amend 02.docx

DOCX document 32 KB Posted

Attached to
INSTALLATION OF 183 WINDOW A/C UNITS INCLUDING MATERIALS
Solicitation number
N0024425QS055
Issued by

About this file

This Statement of Work (SOW) details the installation of 183 GE 6,000 BTU Electronic Window Air Conditioner units for Assault Craft Unit Five (ACU-5) at Marine Corps Base Camp Pendleton. The project involves installing air conditioning units across two barracks buildings (87 units in Building 1 and 96 units in Building 2), with specific requirements for each unit including plexiglass inserts, weather stripping, mounting brackets, extension cords, and associated installation hardware.

The solicitation (N0024425QS055) is a Small Business Set-Aside competition under NAICS code 333415, with a size standard of 1,250 employees. The contract requires providing materials and installing the air conditioner units with no structural modifications. The period of performance is 30 days after contract award, with the installation location at ACU-5, Donald Cook Road, Building 31940, Camp Pendleton. Payment will be processed through the Wide Area Workflow (WAWF) system, and contractor personnel will be escorted by ACU-5 Galley personnel while on the military installation.

View the file

Other files

File Type Posted
WD 2015-5635.txt TXT text file
Combined Synopsis Solicitation N00244-25-Q-S055_Amend 05.pdf PDF
SOW_Amend 04.docx DOCX document
Combined Synopsis Solicitation N00244-25-Q-S055_Amend 04.pdf PDF
QA No 3.pdf PDF
QA No 2.pdf PDF
Price List Template for AC Material and Installation_Amend 02.xlsx XLSX spreadsheet
QA No 1.pdf PDF
Combined Synopsis Solicitation N00244-25-Q-S055.pdf PDF
SOW.docx DOCX document
Price List Template for AC Material and Installation.xlsx XLSX spreadsheet
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 02: The purpose of amendment 02 is to:

1. Correct Item 1 in Building 2 of this SOW to correct size of 30.250“X 40.500.

2. Add additional description to Item 2 (weather stripping insulation) of both buildings.

3. Add additional description to Item 4 (extension cord) of both buildings.

All other terms and conditions remain unchanged.

STATEMENT OF WORK (SOW)

Installation of 183 GE 6,000 BTU Electronic Window Air Conditioner Units ASSAULT CRAFT UNIT FIVE Barracks room (ACU-5)

1. PURPOSE: ACU-5 requires installation of 183 GE 6,000 BTU Electronic Window Air Conditioner between two barracks building rooms for health and conform of the crew located at MCB Camp Pendleton.

2. SCOPE: This requirement is to fulfill crew needs during warm weather and summer season. Currently there is no air conditioning units being used nor installed in any of the rooms occupied by ACU-5 crew members at the barracks. NO structural modification required, both PWD at Marine Corps Base and NAVFAC concur and authorized to proceed with the installation. See attached memorandum.

2.1 The contractor shall provide parts and installation of 183 AC units and listed parts below. Required parts must be EQUAL or SAME and compatible with GE 6,000 BTU Electronic Window Air Conditioner model# AHW06LZ.

Building# 1 (87 units)

Item
Nomenclature
Part No.
QTY
Unit
1
Plexiglass Insert 26x27.5 inches Generic Clear .13 inches Acrylic
87
Each
2
Weather Stripping Insulation:

Weather Seal foam (Generic - 1-1/4 in Thick x 42 in L - Durable Polyurethane Foam Strip)

00810083557397
87
Each
3
AC Mounting Bracket
DA-080
87
Each
4
Extension Cord: with a flat head - 10 ft.
B0D4TNCJ5K
87
Each
5
(5) Tapcon screws per unit
24525
435
Each
6
(5) 1/2" self-tapping screws per install
21308
435
Each
7
Silicone (1/8 of tube per install)
317778410
87
Each
8
Foil tape per install
317579705
87
Each
9
INSTALLATION OF MATERIAL AND A/C UNITS
87
Each

Building# 2 (96 units)

Item
Nomenclature
Part No.
QTY
Unit
1
Plexiglass Insert 26x27.5 inches Generic Clear .13 inches Acrylic

30.250“X 40.500 (Generic Clear .13 inches Acrylic)

96
Each
2
Weather Stripping Insulation : Weather Seal foam (Generic - 1-1/4 in Thick x 42 in L - Durable Polyurethane Foam Strip)
00810083557397
96
Each
3
AC Mounting Bracket
DA-080
96
Each
4
Extension Cord: with a flat head - 10 ft
B0D4TNCJ5K
96
Each
5
(5) Tapcon screws per unit
24525
480
Each
6
(5) 1/2" self-tapping screws per install
21308
480
Each
7
Silicone (1/8 of tube per install)
317778410
96
Each
8
Foil tape per install
317579705
96
Each
9
INSTALLATION OF MATERIAL AND A/C UNITS
96
Each

2.2 Contractor MUST prestart AC units and clean-up after completing installation.

3. PERIOD OF PERFORMANCE: 30 DAYS after contract award

4. PLACE OF PERFORMANCE: Place of performance will be at Assault Craft Unit FIVE, Donald Cook Road, Bldg. 31940 Camp Pendleton, Oceanside, CA 92055.

5. Compliance and Standards.

5.1 Items requested must be the SAME or EQUAL based on minimum specifications due to exact measurements of existing windows.

5.2 While on military installation, the Contractor shall be subject to monitoring and inspection, but under no circumstances shall such personnel be deemed employees or agents of the government.

6. Security.

Personnel performing this task do not require a security clearance.

ACU-5 Galley personnel will provide escorts on base for Contractor during and while delivering equipment and working at ACU-5.

7. Invoicing and payment.

Payment will be processed via WAWF system.

WAWF Acceptor: Provided at time of Award.

Telephone number:

WAWF Certifier:

Email address:

File details come from the government source that posted it. Updated .