Performance Work Statement Summary
This Performance Work Statement (PWS) describes facility ceiling tile replacement and grid repair/replacement services at Naval Station Norfolk, Building W143, 9550 Decatur Avenue, Norfolk, VA 23511, from October 26, 2026, through January 31, 2027. The contractor must provide all labor, equipment, tools, materials, supervision, and transportation to conduct pre-work inspections, identify and repair damaged ceiling grid members (tees and mains), secure and level the suspension grid system, replace damaged grid on the 1st, 3rd, and 6th floor hallways, and replace all hallway ceiling tiles with Armstrong school zone fine fissured 24"x48"x3/4" tiles (1714). On the 3rd floor, damaged tiles must be matched to existing unique tiles by brand, style, and color. All old ceiling tiles and grid must be legally disposed of off-site with daily trash removal. Work hours are 0700-1600 Monday through Friday, excluding federal holidays. The contractor must comply with OSHA standards (29 CFR Parts 1910 and 1926) and the U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1).
The contractor must submit an Accident Prevention Plan (APP) and Activity Hazard Analysis (AHA) within 15 and 5 business days, respectively, before work commences. A comprehensive Quality Control Plan (QCP) must be approved within 15 calendar days after award. All ceiling tile and grid materials must remain off-site until installation day. Critical performance standards include 95% compliance on grid repair and alignment (1/8" level tolerance over 10 feet), 98% defect-free tile installation with flush fit and no gaps, 100% safety compliance with zero violations, and daily worksite cleanup completed before personnel leave. The Government furnishes facility access, 120V electrical power, water, and emergency medical services. Mandatory deliverables include the APP, QCP, AHA, material technical data sheets, weekly toolbox safety meeting minutes, incident reports, and waste disposal documentation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 4.07c.pdf | ||
| 4.07b Amendment 0002.pdf | ||
| MASTER W-143-6-Model.pdf | ||
| MASTER W-143-1 Model.pdf | ||
| MASTER W-143-3-Model.pdf | ||
| Solicitation Amendment N0018926QL3420001 SF 30 (1).pdf | ||
| Wage Determination 2015-4341.pdf | ||
| Solicitation - N0018926QL342.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT
(PWS)
FACILITY CEILING TILE REPLACEMENT AND GRID REPAIR/REPLACEMENT
SERVICES
1.0 GENERAL INFORMATION
1.1 Background
The Federal Government requires professional facility support services to maintain safe, functional, and aesthetically appropriate interior environments across its real property inventory. Over time, suspended acoustic ceiling systems degrade due to building movement, humidity, utility maintenance access, and general wear. To preserve facility integrity, professional intervention is required to repair or in some cases replace structural grid suspension systems and replace all ceiling tiles due to them not matching, being damaged, stained, or missing.
1.2 Scope of Work
The Contractor shall provide all personnel, equipment, tools, materials, supervision, transportation, and non-personal services necessary to perform ceiling grid repair, alignment, and acoustic ceiling tile replacement services as defined in this Performance Work Statement (PWS). The work includes, but is not limited to:
• Conducting pre-work inspections of ceiling systems.
• Identifying and repairing damaged, bent, or misaligned ceiling grid members
(tees and mains).
• Securing and leveling the suspension grid system, including replacing or adding hanger wires.
• Replace grid that has sustained damage by being bent, missing, or is discolored and/or rusted on 1st, 3rd, and 6th floor hallways.
• Replace all hallway ceiling tiles on the 1st ,3rd, and 6th floor hallways with
Armstrong school zone fine fissured 24”x48”x3/4” (1714). On the 3rd floor hallways, replace all damaged ceiling tiles with matching tiles that are unique to that floor. Contractor will need to identify the 3rd floor ceiling tile and match the same brand, style, and color.
• Legally dispose of all old ceiling tiles and ceiling tile grid offsite. Trash needs to be removed from the worksite daily.
• Coordinating work around existing utility fixtures (HVAC diffusers, lighting fixtures, fire sprinklers, and life safety sensors).
• New ceiling tile and grid must be stored offsite and only brought to the worksite to be installed the same day.
• Enforcing strict adherence to federal, state, and local safety regulations, specifically including OSHA standards and the U.S. Army Corps of Engineers (USACE) Safety and Health Requirements Manual (EM 385-1-1).
1.3 Period of Performance
The Period of Performance shall be 26 October, 2026 – 31 January, 2027
1.4 Place of Performance
The services shall be performed at Naval Station Norfolk, Building Number W143, and 9550 Decatur Avenue, Norfolk, VA23511.
1.5 Work Hours and Federal Holidays
• Normal Work Hours: All work shall be performed between the hours of 0700 and 1600, Monday through Friday, excluding Federal Holidays, unless otherwise approved by the COR.
• Federal Holidays: The Contractor is not required to perform routine services on the following federal holidays:
• New Year’s Day
• Martin Luther King Jr.’s Birthday
• Washington’s Birthday (Presidents' Day)
• Memorial Day
• Juneteenth National Independence Day
• Independence Day
• Labor Day
• Columbus Day
• Veterans Day
• Thanksgiving Day
• Christmas Day
2.0 DEFINITIONS AND ACRONYMS
• Acoustical Ceiling Tile (ACT): A ceiling tile made from sound-absorbing materials, typically mineral fiber, fiberglass, or composite materials, designed to lay within a suspended metal grid.
• Activity Hazard Analysis (AHA): A systematic project management and safety process used to identify hazards and establish controls for specific construction/maintenance tasks.
• Accident Prevention Plan (APP): A comprehensive, site-specific safety and health plan developed by the Contractor and approved by the Government prior to work initiation.
• Contracting Officer (CO): The federal official with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings.
• Contracting Officer’s Representative (COR): An individual designated and authorized in writing by the Contracting Officer to perform specific technical or administrative functions.
• Deficiency: Any part of the work that fails to meet the performance standards, codes, or technical requirements established in this contract.
• EM 385-1-1: The United States Army Corps of Engineers (USACE) Safety and Health Requirements Manual, which prescribes safety and occupational health requirements for federal and military projects.
• Main Runner (Main Tee): The primary load-bearing metal channel in a suspended ceiling grid system.
• OSHA: The Occupational Safety and Health Administration.
• Performance Work Statement (PWS): A statement of work for performance-based acquisitions that describes the required results in clear, specific, and objective terms.
• Quality Control Plan (QCP): The Contractor’s internal plan to self-inspect, monitor, and guarantee that all services meet PWS standards.
• Cross Tee: The secondary metal channels that snap into the main runners to form the grid pattern supporting the ceiling tiles.
3.0 GOVERNMENT FURNISHED PROPERTY,
EQUIPMENT, AND SERVICES (GFP/E/S)
3.1 Government Furnished Space (GFS)
The Government will provide the Contractor with reasonable access to the facility interior to execute the required services. No dedicated on-site storage space for materials or equipment is guaranteed unless coordinate and approved in writing by the COR.
3.2 Utilities
The Government will furnish electrical power (120V) and water from existing facility outlets for use by the Contractor solely for the execution of this contract. The Contractor shall conserve utilities and utilize safe, compliant connections.
3.3 Emergency Medical Services
The Government will provide first-response emergency medical services (e.g., local fire/rescue transport) at the Contractor's expense, if needed, during the performance of duties.
4.0 CONTRACTOR FURNISHED ITEMS AND
SERVICES
4.1 General
Except for those items specifically stated to be Government-furnished in Section 3.0, the Contractor shall furnish everything required to perform this contract. This includes all labor, supervision, materials (matching existing acoustic ceiling tiles and suspension grids), specialized tools, scaffolding, ladders, personal protective equipment (PPE), containment materials, and transport vehicles.
4.2 Material Specifications
• Ceiling Tiles:
-Material: Wet-formed mineral fiber -Dimensions: 24" x 48" x 3/4" (nominal) -Edge Profile: Square Lay-In (15/16") -Surface Finish: Factory-applied latex paint with non-directional fine fissured visual -Color: White -Sound Absorption (NRC): 0.70 -Sound Blocking (CAC): 40 -Light Reflectance (LR): 82% -Fire Performance: Class A (UL) — Flame Spread 25 or under, Smoke Developed 50 or under -Sag/Humidity Resistance: High humidity and sag resistance -Sustainability: Bio-based content, meets ANSI S12.60 Classroom Guidelines
• Grid Components: Replacement grid components must match the existing grid profile, structural classification, and color.
• Hanger Wire: Galvanized carbon steel wire, minimum 12-gauge, compliant with
ASTM C635/C635M.
5.0 SPECIFIC TASKS / PERFORMANCE
REQUIREMENTS
The Contractor shall execute the tasks detailed below in a professional manner, minimizing disruption to federal personnel and facility operations.
5.1 Site Assessment and Preparation
• The Contractor shall inspect the designated work areas to identify any structural, electrical, mechanical, or plumbing obstructions above or within the ceiling system.
• The Contractor shall protect all existing facility assets (including walls, floors, carpeting, desks, IT infrastructure, and sensitive equipment) from dust, debris, and damage.
• The Contractor shall deploy drop cloths, heavy plastic sheeting, and dust curtains prior to removing any tiles or manipulating the ceiling grid.
5.2 Ceiling Grid Repair and Alignment
• Structural Integrity: The Contractor shall repair, reinforce, or replace bent, damaged, rusted, or structurally compromised grid sections.
• Leveling and Squaring: The Contractor shall level and square the grid network to a tolerance of no more than 1/8 inch over 10 feet.
• Suspension Support: The Contractor shall verify that hanger wires are secured to the building structure (not to conduits, pipes, or ductwork) at intervals not exceeding 4 feet on center, and within 8 inches of any grid splices or wall moldings, in accordance with ASTM C636.
5.3 Ceiling Tile Replacement
• Demolition and Removal: The Contractor shall carefully remove undamaged, damaged, stained, broken, warped, or mold-contaminated tiles.
• Precision Installation: The Contractor shall measure, cut, and fit new acoustical ceiling tiles seamlessly into the repaired grid.
• Fit and Appearance: Installed tiles must sit flat on the grid flanges with no visible gaps, warps, or uneven surfaces. Cut edges on perimeter tiles must be clean, straight, and properly supported by wall moldings.
5.4 Utility and Fixture Coordination
• The Contractor shall ensure that ceiling-mounted fixtures (HVAC registers/diffusers, lighting fixtures, exit signs, fire sprinklers, smoke detectors, and occupancy sensors) are not disturbed or compromised during grid alignment or tile replacement.
• Any ceiling tile cuts made around utilities or fixtures must be clean, tight, and professional, leaving no gaps exceeding 1/16 inch, unless otherwise governed by manufacturer installation requirements (e.g., sprinkler escutcheon plates).
• Heavy light fixtures or HVAC diffusers must be supported independently by hanger wires attached to the building structure; the Contractor shall notify the COR immediately if any utility fixture is found to be resting entirely on the ceiling grid without independent support.
5.5 Housekeeping and Waste Management
• The Contractor shall maintain a clean work area on a daily basis. All dust, tile fragments, grid scraps, and general waste must be cleaned up continuously.
• The Contractor shall perform a thorough vacuuming of the work area daily utilizing HEPA-filtered vacuum cleaners to capture fine mineral fiber dust.
• The Contractor shall clean up all sections of hallway being worked each day, to include cleaning off any dust that falls on hanging items on the walls, dust on the wall board itself, and all flooring to include baseboards.
• All generated waste shall be legally disposed of off-site at an authorized disposal facility. The Contractor shall provide disposal receipts or manifests to the COR upon request.
6.0 SAFETY, HEALTH, AND ENVIRONMENTAL
REQUIREMENTS
Compliance with safety standards is a critical performance metric for this contract.
The Government will strictly enforce safety regulations, and any failure to comply may result in an immediate Stop Work Order at the Contractor's expense.
6.1 Regulatory Compliance Standards
The Contractor shall comply with all applicable Federal, State, and local safety and occupational health laws and regulations, including but not limited to:
• OSHA General Industry Standards: 29 CFR Part 1910
• OSHA Construction Industry Standards: 29 CFR Part 1926
• USACE Safety and Health Requirements Manual: EM 385-1-1 (current version in effect at time of award)
6.2 Accident Prevention Plan (APP) and Activity Hazard
Analysis (AHA)
• Accident Prevention Plan (APP): In accordance with EM 385-1-1, Section
01.A.12, the Contractor shall submit a written, site-specific APP to the Contracting Officer for approval within fifteen (15) calendar days after contract award. No on-site work shall begin until the APP is approved.
• Activity Hazard Analysis (AHA): In accordance with EM 385-1-1, Section 01.A.13, the Contractor shall prepare and submit an AHA for each phase of work (e.g., grid demolition, wire installation, tile fitting).
• The AHA shall define the activity being performed, identify the hazards associated with each step, and detail the specific safety controls, training, and PPE required to mitigate those hazards.
• The AHA shall be reviewed and signed by the Contractor's designated Competent Person and submitted to the COR for acceptance prior to commencing that specific phase of work.
6.3 Fall Protection and Ladder Safety
Since ceiling work requires elevated access, the Contractor must manage fall risks in strict compliance with OSHA 29 CFR 1926 Subpart M (Fall Protection), OSHA 29 CFR 1926 Subpart X (Stairways and Ladders), and EM 385-1-1, Section 21 (Fall Protection) and Section 24 (Safe Access, Ladders, and Scaffolding).
• Ladders: Only commercial-grade, non-conductive (Type IA or IAA fiberglass) ladders shall be used. Metal ladders are strictly prohibited. Ladders must be inspected daily by a Competent Person.
• Scaffolding & Work Platforms: If rolling baker scaffolds or scissor lifts are utilized, they must be equipped with standard guardrails (top rails, mid-rails, and toe boards) and locking casters. Scissor lift operators must be fully trained and certified, utilizing appropriate fall restraint systems as required by EM 385- 1-1 Section 21.H.
• Three-Point Contact: Employees must maintain three points of contact while climbing or descending ladders.
6.4 Personal Protective Equipment (PPE)
The Contractor shall ensure all employees are outfitted with, and properly utilize, the mandatory PPE required for the work environment in accordance with OSHA 29 CFR 1926 Subpart E and EM 385-1-1, Section 05:
• Head Protection: ANSI Z89.1-compliant hard hats or bump caps (depending on overhead clearance hazard levels as assessed in the AHA).
• Eye and Face Protection: ANSI Z87.1-compliant safety glasses with side shields are mandatory at all times during overhead demolition and installation to protect against falling debris and fibers.
• Hand Protection: Cut-resistant gloves matching the task (e.g., ANSI Cut Level A3 or higher when using utility knives or handling metal grid edges).
• Respiratory Protection: NIOSH-approved N95 particulate respirators shall be made available and worn when handling dusty ceiling tiles or when required by the silica control plan.
• Footwear: Protective, slip-resistant, closed-toe work boots.
6.5 Safety Meetings and Reporting
• Toolbox Safety Meetings: The Contractor shall conduct weekly "toolbox" safety meetings with all on-site personnel. Meeting minutes, including topics discussed and attendee signatures, shall be submitted to the COR weekly.
• Accident Reporting: The Contractor shall immediately notify the CO and COR within one (1) hour of any occupational injury, illness, near-miss, or property damage. A written accident report (using USACE ENG Form 3396 or equivalent federal incident reporting template) shall be submitted within twenty-four (24) hours.
7.0 QUALITY CONTROL AND QUALITY
ASSURANCE
7.1 Quality Control Plan (QCP)
The Contractor shall establish and maintain a comprehensive Quality Control Plan (QCP) to ensure the requirements of this contract are met.
• The QCP shall be submitted to the COR for approval within fifteen (15) calendar days after contract award.
• The plan shall identify the Quality Control Manager (QCM) responsible for inspecting the work, tracking deficiencies, and coordinating corrective actions.
• The QCP shall include an inspection checklist covering grid leveling, hanger wire tension, tile fit, and site clean-up.
7.2 Quality Assurance and Performance Requirements
Summary (PRS) The Government will evaluate the Contractor's performance under this contract using Quality Assurance surveillance methods. The Performance Requirements
Summary (PRS) below outlines the critical performance indicators, standards, acceptable quality levels (AQL), and methods of surveillance.
Performance Objective
PWS
Paragraph
Performance Standard
Acceptable Quality Level
(AQL)
Method of Surveillance
Grid Repair & Alignment
5.2 Grid is
structurally sound, level to within 1/8" over 10', and aligned properly.
Hanger wires secure.
95% compliance on all inspected grids. Zero structural failures.
Direct observation / Random sampling.
Tile Installation Quality
5.3 Tiles fit flush, match existing finishes, are clean, with no gaps or damaged edges.
98% defect-free tiles in completed areas.
100% inspection of completed areas.
Safety Compliance
6.0 Adherence to
OSHA, EM
385-1-1, and the approved
APP/AHA.
Proper PPE worn.
100% compliance.
Zero safety violations tolerated.
Periodic surveillance and safety audits.
Clean-up & Housekeeping
5.5 Work area
vacuumed, protected surfaces clean, trash removed daily.
Clean-up must be completed before leaving the site each day.
Daily walk-through by
COR.
Deliverable Submittals
8.0 Mandatory
submittals
(APP, QCP,
100% on-time delivery of
Tracking log review.
AHA)
delivered on time.
major safety plans.
8.0 DELIVERABLES
The Contractor shall provide the following deliverables to the COR within the designated timeframes:
Deliverable PWS Paragraph Format / Destination
Due Date
Accident Prevention Plan
(APP)
6.2 PDF / COR and
CO
Within 15 calendar days after contract award.
Activity Hazard Analysis (AHA)
6.2 PDF / COR Minimum 5
business days prior to starting a work phase.
Quality Control Plan (QCP)
7.1 PDF / COR and
CO
Within 15 calendar days after contract award.
Material Technical Data Sheets
4.2 PDF / COR Prior to purchasing
or delivering ceiling tiles/grid to the site.
Toolbox Safety Meeting Minutes
6.5 PDF or Hardcopy
/ COR
Weekly.
Accident / Incident Report
6.5 PDF / COR and
CO
Verbal within 1 hour; written report within 24 hours of occurrence.
Waste Disposal Receipts/Manifests
5.5 PDF or Hardcopy
/ COR
Upon completion of demolition/disposal phase.
| PERFORMANCE WORK STATEMENT (PWS) |
| 1.0 GENERAL INFORMATION |
| 1.1 Background |
| 1.2 Scope of Work |
| 1.3 Period of Performance |
| 1.4 Place of Performance |
| 1.5 Work Hours and Federal Holidays |
| 2.0 DEFINITIONS AND ACRONYMS |
| 3.0 GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES (GFP/E/S) |
| 3.1 Government Furnished Space (GFS) |
| 3.2 Utilities |
| 3.3 Emergency Medical Services |
| 4.0 CONTRACTOR FURNISHED ITEMS AND SERVICES |
| 4.1 General |
| 4.2 Material Specifications |
| 5.0 SPECIFIC TASKS / PERFORMANCE REQUIREMENTS |
| 5.1 Site Assessment and Preparation |
| 5.2 Ceiling Grid Repair and Alignment |
| 5.3 Ceiling Tile Replacement |
| 5.4 Utility and Fixture Coordination |
| 5.5 Housekeeping and Waste Management |
| 6.0 SAFETY, HEALTH, AND ENVIRONMENTAL REQUIREMENTS |
| 6.1 Regulatory Compliance Standards |
| 6.2 Accident Prevention Plan (APP) and Activity Hazard Analysis (AHA) |
| 6.3 Fall Protection and Ladder Safety |
| 6.4 Personal Protective Equipment (PPE) |
| 6.5 Safety Meetings and Reporting |
| 7.0 QUALITY CONTROL AND QUALITY ASSURANCE |
| 7.1 Quality Control Plan (QCP) |
| 7.2 Quality Assurance and Performance Requirements Summary (PRS) |
8.0 DELIVERABLES