SOW_TO_1.pdf
PDF 21 KB Posted
- Attached to
- Military Support Division Support Services Federal contract opportunity
- Solicitation number
- N00173-14-R-RV04
About this file
SOW TO 1
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF-30.pdf | ||
| SOW_TO_3.pdf | ||
| Attachment_8_Acronyms_and_Definitions.pdf | ||
| Attachment_7_Task_Order_Cost_Spreadsheet.xlsx | XLSX spreadsheet | |
| Amendment_1_to_Solicitation_14-R-RV04.pdf | ||
| Q A_dtd_7_7_14.pdf | ||
| SOW_TO_4.pdf | ||
| Attachment_11_-_Indirect_Rate_Schedule.xlsx | XLSX spreadsheet | |
| SOW_TO_2.pdf | ||
| Attachment_6_Task_Order_Price_Spreadsheet.xlsx | XLSX spreadsheet | |
| SOW_TO_5.pdf | ||
| SOW_TO_2.pdf | ||
| Attachment_L-2_-_Previous_Contracting_Efforts.docx | DOCX document | |
| Task_Order_Cost_Spreadsheet.xlsx | XLSX spreadsheet | |
| Attachment_L-1.docx | DOCX document | |
| SOW_TO_4.pdf | ||
| SOW_TO_1.pdf | ||
| Exhibit_A.pdf | ||
| Attachment_1_-_Requirements_for_On-Site_Contractors.pdf | ||
| Task_Order_Staffing_Plan.xlsx | XLSX spreadsheet | |
| SOW_TO_3.pdf | ||
| Solicitation_14-R-RV04.pdf | ||
| Attachment_7_Acronyms_and_Definitions.pdf | ||
| Attachment_8.pdf |
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N00173-14-R-RV04
Statement of Work Task Order 0001
Analysis/Design of Airborne S&T Platforms/Modification Dated 03/20/2014
1.0 Introduction
The purpose of this contract is to provide support to the NRL Military Support Division, Code 1400 to accomplish airborne-related S&T requirements.
2.0 Scope
The contractor shall support a research project involving multiple antenna and rack installations to conduct an antenna comparison onboard NP-3C aircraft.
3.0 Task Description
The contractor shall support the NRL Military Support Division’s execution of a research project involving multiple antenna and rack installations by completing the following task:
3.1 The Contractor shall provide an engineering and feasibility study for project installation for government scientist that includes multiple cameras, radar, sensors and integrated workstations
3.2 The contractor shall design the following items
• Dual antenna installation in bomb bay equipment pallet(BEP)
• New electronic integration in BEP
• Multiple equipment racks
• Exterior blade antenna installation
3.3 The contractor shall provide an analysis of the following items:
• Dual antenna installation
• Equipment racks
• Blade antenna installation
4.0 Deliverables
• Completed documentation for a PDR for the project installation, including o Provide detailed drawing for all parts to be manufactured o Provide assembly level drawings showing interrelationship of all components and sub assemblies o Provide all required electrical diagrams, mechanical drawings and analyses, needed to obtain NAVAIR flight clearance release.
5.0 Delivery Date
All documents must be provided to the Government no later than 26 days after task order award.
File details come from the government source that posted it. Updated .