Mod F L3 SPAWAR Global Work Breakdown Structure (GWBS) ~ Mod F

1 Product Investment2 Common Elements (cont'd)
1.1Prime Mission Product2.6Initial Spares
1.1.1Hardware2.7Support Equipment
1.1.2Software2.7.1Peculiar Support Equipment
1.1.3Integration, Assembly, Test and Checkout2.7.2Common Support Equipment
1.2Science and Technology2.8System Facilities and Laboratories
2.8.1Development/Integration/Production Labs
2 Common Elements2.8.2Other Facilities
2.1Program Management2.9System Training
2.1.1Acquisition Management2.9.1Training Equipment
2.1.2Project Management2.9.2Training Services
2.1.3Financial Management2.9.3Schoolhouse and Formal Training Courses
2.1.4Logistics Management2.10Purchased Services
2.1.5Internal Project IT
2.1.6Contract Management3 Operations and Support
2.1.7Travel3.1Mission Personnel
2.1.8Cost Estimation and Analysis3.2Unit Operations
2.1.9Legal3.3Maintenance
2.1.10Foreign Military Sales - Pre-Letter of Request3.3.1Consumable Materials and Repair Parts
2.1.11Foreign Military Sales - Case Development3.3.2Depot-Level Repairables (DLRs)
2.1.12Foreign Military Sales - Case Execution3.3.3Intermediate Maintenance
2.1.13Foreign Military Sales - Case Closure3.3.4Depot Maintenance
2.1.14Foreign Military Sales - Business Sustaining3.3.5Other Maintenance
2.2Systems Engineering3.4Sustaining Support
2.2.1Studies & Design3.4.1Software Maintenance
2.2.2Architecture3.4.2License Maintenance Fees
2.2.3Human Systems Integration3.4.3Technical Support
2.2.4Technical Authority3.4.4Logistics Support
2.2.5Certification Authority3.4.5Sustainment Engineering
2.2.6Systems Engineering Management3.4.6Mission Product/Support Operations
2.2.7Requirements Analysis3.4.7Fleet C4I Systems Sustainment
2.2.8Configuration Management3.5Hardware Modifications and Tech Refresh
2.2.9Logistics Engineering3.6Demilitarization and Disposal
2.2.10Fleet Experimentation
2.2.11Cybersecurity Engineering4 Management and Administration
2.2.12Government Technical Oversight/Independent Verification & Validation4.1Command/PEO Management and Administration
2.3System Test and Evaluation4.1.1General Management
2.3.1System DT&E4.1.2Small Business and Inspection Administration
2.3.2System OT&E4.1.3Total Force Management
2.3.3System FOT&E4.1.4Information Technology Management
2.3.4Security Testing4.1.5Command Operations & Support
2.3.5Systems Integration/Interoperability Testing4.1.6Corporate Strategy
2.4Platform / Site Activation / Installation4.1.7Corporate Communications & Public Affairs
2.4.1Installation Planning4.1.8Special Programs Oversight & Compliance
2.4.2Installation Design4.1.9Legal - General Law
2.4.3System Installation and Turnover4.1.10Command Representation
2.4.4Installation Policy and Process Development4.1.11Sponsor/Customer Coordination
2.4.5Installation Process and Risk Assessment4.1.12Computer Workstation Seat Costs
2.5Data4.2Withholds (External and Internal)
2.5.1Technical Publications4.2.1External Withholds
2.5.2Engineering Data4.2.2Internal Withholds
2.5.3Management Data
2.5.4Logistics Management Information
2.5.5Data Repository
2.5.6Integrated Data Environment (IDE)
2.5.7Document and Content Management

Mod F L4

SPAWAR Global Work Breakdown Structure (GWBS) ~ Mod F
1 Product Investment2 Common Elements (cont'd)
1.1Prime Mission Product2.4Platform/Site Activation/Installation
810101001.1.1Hardware820401002.4.1Installation Planning
810102001.1.2Software820402002.4.2Installation Design
810103001.1.3Integration, Assembly, Test and Checkout820403002.4.3System Installation and Turnover
810200001.2Science and Technology820404002.4.4Installation Policy and Process Development
820405002.4.5Installation Process and Risk Assessment
2 Common Elements2.5Data
2.1Program Management820501002.5.1Technical Publications
820101002.1.1Acquisition Management820502002.5.2Engineering Data
820102002.1.2Project Management820503002.5.3Management Data
820103002.1.3Financial Management820504002.5.4Logistics Management Information
820103012.1.3.1Accounting Compliance Reports & Products820505002.5.5Data Repository
820103022.1.3.2Budget/POM/PR Formulation, Presentation & Defense820506002.5.6Integrated Data Environment (IDE)
820103032.1.3.3Funds Allocation & Execution820507002.5.7Document and Content Management
820102042.1.3.4Studies, Reporting, Analysis820600002.6Initial Spares
820102052.1.3.5Travel Fund Management2.7Support Equipment
820104002.1.4Logistics Management820701002.7.1Peculiar Support Equipment
820104012.1.4.1Logistics Management Policy820702002.7.2Common Support Equipment
820104022.1.4.2Logistics Management Assessment2.8System Facilities and Laboratories
820104032.1.4.3Logistics Management Acquisition820801002.8.1Development/Integration/Production Labs
820104042.1.4.4Logistics Business Case Analysis (BCA)820802002.8.2Other Facilities
820105002.1.5Internal Project IT2.9System Training
820106002.1.6Contract Management820901002.9.1Training Equipment
820106012.1.6.1Planning820902002.9.2Training Services
820106022.1.6.2Solicitation820903002.9.3Schoolhouse and Formal Training Courses
820106032.1.6.3Evaluation821000002.10Purchased Services
820106042.1.6.4Negotiation
820106052.1.6.5Award3 Operation and Support
820106062.1.6.6Post Award Administration3.1Mission Personnel
820106072.1.6.7Policy Support3.2Unit Operations
820106082.1.6.8Contract Systems/Procurement Automation3.3Maintenance
820107002.1.7Travel3.3.1Consumable Materials and Repair Parts
820108002.1.8Cost Estimation and Analysis3.3.2Depot-Level Repairables (DLRs)
820109002.1.9Legal3.3.3Intermediate Maintenance
820110002.1.10Foreign Military Sales - Pre-Letter of Request830304003.3.4Depot Maintenance
820111002.1.11Foreign Military Sales - Case Development3.3.5Other Maintenance
820112002.1.12Foreign Military Sales - Case Execution830400003.4Sustaining Support
820113002.1.13Foreign Military Sales - Case Closure830401003.4.1Software Maintenance
820114002.1.14Foreign Military Sales - Business Sustaining830402003.4.2License Maintenance Fees
2.2Systems Engineering830403003.4.3Technical Support
820201002.2.1Studies & Design830403013.4.3.1Distance Support
820201012.2.1.1SPAWAR Enterprise Architecture Optimization830403023.4.3.2On Site Support
820201022.2.1.2Capability Fielding Decision Support830403033.4.3.3Proactive Systems Support
820201032.2.1.3Portfolio Health Assessments830404003.4.4Logistics Support
820201042.2.1.4Engineering Risk/Threat Assessments830404013.4.4.1Supply Support
820201052.2.1.5Program/Project Level Studies & Design830404023.4.4.2Maintenance Of Tech Data & Documentation
820202002.2.2Architecture830404033.4.4.3Configuration Management for Fielded Systems
820202012.2.2.1Future Architecture830405003.4.5Sustainment Engineering
820202022.2.2.2Architecture Product Development830405013.4.5.1Maintenance Engineering
820202032.2.2.3Program Level Architecture830405023.4.5.2Lifecycle Engineering
820203002.2.3Human Systems Integration830405033.4.5.3Lifecycle Testing
820204002.2.4Technical Authority830406003.4.6Mission Product/Support Operations
820204012.2.4.1Standards830407003.4.7Fleet C4I Systems Sustainment
820204022.2.4.2Interface Management830500003.5Hardware Modifications and Tech Refresh
820204032.2.4.3Systems Engineering Technical Reviews (SETRs)3.6Demilitarization and Disposal
820204042.2.4.4Technical Warrant Holder (TWH) Services
820205002.2.5Certification Authority
820205012.2.5.1System or Element Certifications
820205022.2.5.2System of Systems Certifications
820206002.2.6Systems Engineering Management
820206012.2.6.1System of Systems Engineering (SoSE)
820206022.2.6.2Engineering Acquisition Documentation
820206032.2.6.3Program Engineering Management
820207002.2.7Requirements Analysis
820208002.2.8Configuration Management
820209002.2.9Logistics Engineering
820210002.2.10Fleet Experimentation
820211002.2.11Cybersecurity Engineering
820211012.2.11.1Risk Management Framework (RMF) & CYBERSAFE
820211022.2.11.2Systems Security Engineering
820212002.2.12Government Technical Oversight/Independent Verification & Validation
2.3System Test and Evaluation
820301002.3.1System DT&E
820302002.3.2System OT&E
820303002.3.3System FOT&E
820304002.3.4Security Testing
820305002.3.5Systems Integration/Interoperability Testing
4 Management and Administration
4.1Command/PEO Management and Administration
840101004.1.1General Management
840101014.1.1.1Supervision/Management - General
840101024.1.1.2Travel Administration
840101034.1.1.3Supplies
840101044.1.1.4Training - Command Directed
840101054.1.1.5Training - DAWIA/DAU
840101064.1.1.6Training - Skills Development
840102004.1.2Small Business and Inspection Administration
840102014.1.2.1Small Business Programs
840102024.1.2.2Small Business Innovative Research (SBIR)
840102034.1.2.3Evaluation, Investigation and Management Control
840102044.1.2.4Audits
840103004.1.3Total Force Management
840103014.1.3.1Workforce Planning/Human Capital Strategy
840103024.1.3.2Civilian Personnel Management
840103034.1.3.3Military Manpower Planning and Management
840103044.1.3.4Reserve Manpower Management
840103054.1.3.5Training Program Management
840104004.1.4Information Technology Management
840104014.1.4.1Corporate Information Technology Applications Management
840104024.1.4.2Information Resources Management
840104034.1.4.3Information Technology Governance Strategy
840104044.1.4.4Information Technology Budget Management
840104054.1.4.5Portfolio Management
840104064.1.4.6INTERNAL IT Operations, Network Mgmt., Systems, Applications and SW Licenses
840104084.1.4.7NMCI/NGEN IT Service Request Management
840104084.1.4.8Telecommunications/Conference Support
840104094.1.4.9Information Assurance Management
840104104.1.4.10Computer Network Defense (CND) and Network Security
840104114.1.4.11Certification and Accreditation (C&A)/Federal Info Security Mgmt. Act (FISMA)
840104124.1.4.12Internal Use Corporate IT
840105004.1.5Command Operations & Support
840105014.1.5.1Common Support & Service Management
840105024.1.5.2Facilities Management & Support
840105034.1.5.3Workspace Planning & Management
840105044.1.5.4Safety Management
840105054.1.5.5Environmental Engineering & Support
840105064.1.5.6Physical Security
840105074.1.5.7Industrial, Personal and Information Security
840105084.1.5.8Administrative Support Activities
840105094.1.5.9Purchase Card Administration
840105104.1.5.10Accountable Property Management
840106004.1.6Corporate Strategy
840106014.1.6.1Strategic Management
840106024.1.6.2Process Management Command Work
840106034.1.6.3Knowledge Management
840106044.1.6.4Records Management
840106054.1.6.5Special Project Assignments
840107004.1.7Corporate Communications & Public Affairs
840107014.1.7.1Public Affairs/ Community Relations
840107024.1.7.2Corporate Communications
840107034.1.7.3Congressional Liaison
840107044.1.7.4Publications, Electronic Media, and Public Website Support
840108004.1.8Special Programs Oversight & Compliance
840109004.1.9Legal - General Law
840110004.1.10Command Representation
840111004.1.11Sponsor/Customer Coordination
840112004.1.12Computer Workstation Seat Costs
4.2Withholds (External and Internal)
840201004.2.1External Withholds
840202004.2.2Internal Withholds

Data Dictionary

WBSWBS DescriptionUserDefinitionExamples
1PRODUCT INVESTMENTEfforts that happen during the Materiel Solution Analysis, Technical Maturation & Risk Reduction, Engineering & Manufacturing Development, and Production & Deployment phases. This element does not necessarily exclude any appropriations.
1.1PRIME MISSION PRODUCTThe hardware and software used to accomplish the primary mission of the defense materiel item. This element includes the design, development, and production of complete units (i.e., the prototype or operationally configured units, which satisfy the requirements of their applicable specifications, regardless of end use) and is comprised of the sub elements below.Includes:

- All integration, assembly, test and checkout, as well as all technical and management activities associated with individual hardware/software elements.

- All whole and partial prime contractor, subcontractor, and vendor breadboards, brassboards, and qualification test units.

- Factory special test equipment, special tooling, and production planning required to fabricate the PMP.

1.1.1HardwareEchelon II
Echelon IIIHardware components designed, developed, produced, or procured for the specific product. Includes, with lower level sub-elements, the design/production engineering, program management, systems engineering, integration, and testing associated with those sub-elements. (As necessary, the program will, for their use, establish additional levels of indenture needed to accurately identify/describe the hardware required for the Prime Mission Product.)Development Examples:

- PMP Design

- Engineering Demonstration Model

- Prototypes

- Test units that are not part of a lab Production Examples:

- Low Rate Initial Production

- Full Rate Production Includes:

- HW Modifications that occur before Full Operational Capability (FOC) that happen while a production line is open.

Excludes:

- Reengineering activities associated with such modifications belong in '2.2 Systems Engineering'.

- HW Modifications after FOC or Tech Refresh that would occur after the system is fielded even if using procurement funds (e.g., OPN). For these, use element '3.5 Hardware Modifications and Tech Refresh'.

- Hardware required for development, integration, or production labs. For this, use '2.8 System Facilities and Laboratories'

- Mock-up for training purposes or Technical Training Equipment (use 2.9.1 Training Equipment)

1.1.2SoftwareEchelon II
Echelon IIISoftware that is specifically developed/procured for the operations and maintenance or functional control of a computer system. It includes the associated effort needed to analyze, design, build, and test a custom software application as well as the associated effort for assessing and tailoring Commercial-Off-The-Shelf (COTS) software applications or modules that can be attributed to a specific software service or bundle of services with the PMP system.
Includes, with lower level sub-elements, the production engineering, program management, systems engineering, integration, assembly and test associated with those sub-elements. (As necessary, the program will establish additional levels of indenture needed to accurately identify/describe the software required for the Prime Mission Product.)Development Examples:

- PMP SW Design

- SW Models/Prototypes

- SW packages Production Examples:

- Non-recurring SW licenses

- Initial Commercial-Off-the-Shelf procurement

- Non-recurring warranty purchases

Excludes:

- Recurring SW license or warranty fees which belong in '3.4.2 Software Maintenance Fees.'

- SW required for development, integration, or production labs. For this, use '2.8 System Facilities and Laboratories'

- Mock-up for training purposes or Technical Training Equipment (use 2.9.1 Training Equipment)

1.1.3Integration, Assembly, Test, and CheckoutEchelon II
Echelon III"Pre-Delivery" integration, assembly, and testing of the HW and SW of the Prime Mission Product. All technical and functional activities associated with the design development, and production of structures, equipment, parts, materials, and software required to assemble the PMP as a whole.Only use in spend plan If separate performer from Hardware/Software Developer does IA&T.

Includes:

- The set up, conduct, and review of testing assembled components or subsystems prior to installation (i.e., Pre-Installation Test and Check-Out (PITCO))

- Inspection activities related to receiving, factory, and sub-vendor liaison.

- Quality planning and control

- Integration of SW (including loading and verification of firmware

- Product acceptance testing activities (e.g., DD250 receipt of materials)

- Tooling (initial production facilities, factory support equipment), including planning, design, and fabrication.

Excludes:

- All systems engineering/program management and system test and evaluation which are associated with the complete system

- IA&T performed as part of the Installation process. (Use 2.4.3)

- Government technical oversight outside of product acceptance testing (e.g., design agent) or independent verification and validation (IV&V)

- Pre-installation testing (e.g. PITCO), Post installation testing (e.g. SOVT), and/or government acceptance testing associated with equipment alterations or field changes (use 3.4.5.3 Lifecycle Testing)

1.2 Science and Technology Echelon 3 The systematic study directed toward greater knowledge or understanding of the fundamental aspects of phenomena and of observable facts, to understand the means to meet a recognized and specific need.

It also includes development of subsystems and components and efforts to integrate subsystems and components into system prototypes for field experiments and/or tests in a simulated environment.

Advises senior leadership on strategic S&T planning; Identifies and promotes applicable new technology to provide transformational capability from labs, industry, and academia; Acts as honest broker to leverage investments and provide independent/objective test and evaluation; Addresses over-arching issues for integration and interoperability; Implements stronger practices to improve technology transition processes; Serves as a relationship manager to facilitate coordination on S&T development and transition issues S&T work for Office of Naval Research (ONR) & Defense Advanced Research Projects Agency (DARPA) (Budget Activity 1-3)

Includes:

- Basic Research and Development (R&D)

- Applied R&D

- Advanced R&D

2COMMON ELEMENTSElements common to all programs/projects.Common WBS elements should be applied to the appropriate levels within the WBS which they support. In other words, if systems engineering is required to support a Level 3 WBS element, the System Engineering WBS element would appear at Level 4 of the WBS under the Level 3 element it supports. The intent is to understand the total effort associated with designing, developing, and producing a WBS element.
2.1Program ManagementProgram management costs directly associated with a specific system or product. These include efforts directly associated with the business and administrative planning, organizing, directing, coordinating, controlling, and approval actions designated to accomplish the program objectives. It includes administration, project controls, product effectiveness, data and configuration management, subcontract management and security management. This element is a roll-up of costs associated with lower levels.

Includes:

- Cost, schedule, performance measurement management, warranty administration, contract management, data management, vendor liaison, subcontract management.

- Logistics tasks management and technical control, and the business management of the support elements. Planning and management of all the functions of logistics (maintenance support planning and support facilities planning; other support requirements determination; support equipment; supply support; packaging, handling, storage, and transportation; training system requirements determination; computer resource determination; organizational, intermediate, and depot maintenance determination management; and data management).

Excludes:

- Costs of the developer, producer or modernizer associated with elements 1.1.1, 1.1.2, and 1.1.3.

2.1.1 Acquisition Management "Systems Acquisition" activities on DoD acquisition programs and the associated acquisition strategy. Development of background information and planning to include the development and review of formal acquisition documents required by the DoD 5000 and Milestone Decision Authority. Includes:

- Writing and/or coordinating program acquisition documentation including, but not limited to Acquisition Strategy Report (ASR), Acquisition Program Baseline (APB), Test and Evaluation Master Plan (TEMP), Acquisition Plan (AP), Analysis of Alternatives (AoA), Risk Management Plan (RMP), Cost Performance Report (CPR), Integrated Master Schedule (IMS), Milestone Briefs, Selected Acquisition Report (SAR), Defense Acquisition Executive Summary (DAES), Acquisition Decision Memorandum (ADM), Cost Analysis Requirements Description (CARD), 2366A/B Certification Memorandum, Acquisition Information Assurance Strategy (AIAS), Clinger-Cohen Act (CCA) Compliance, Technology Development Strategy (TDS), Life-Cycle Signature Support Plan (LSSP), Program Protection plan (PPP), System Threat Assessment (STA), System Threat Assessment Report (STAR), Technical Data Rights Strategy (TDRS) etc.

2.1.2 Project Management Project management efforts including cost, schedule, performance measurement management, warranty administration, contract/subcontract management, data management, vendor liaison, project execution, risk management, earned value management, etc. Includes:

- Establishment of a risk management process that includes risk planning, risk assessment (identification and analysis), risk management, and risk monitoring to be integrated and continuously applied throughout the project.

- Development and maintenance of the Integrated Master Plan and Integrated Master Schedule, event driven plans that define major tasks and detailed schedules.

- Integrated Baseline Reviews & Support.

- Generating the monthly Cost Performance Reports (CPR) and Contract Funds Status Report (CSFR).

- Collection/analysis of costs for EVM calculations and tracking.

2.1.3 Financial Management Financial management including planning, programming, budgeting, and execution (PPBE), cost accounting and analysis. Program Objectives Memorandum (POM), Budget, Spend Plan, Funds Execution, Accounting and Business Analysis & Reporting.

Includes:

- PPBE requirements; preparation and defense of budget, answers to budget drills, resolution of budget issues (controls, expenditures, meeting benchmarks), input into the POM process for funded/unfunded issues and offsets, spend plan management, execution tracking (preparing funding docs, tracking status - committed, obligated, expended), financial and managerial accounting, and resource management studies and analysis.

- Includes comptroller and other overhead/G&A financial management responsibilities.

- Includes all costs associated with the development, procurement, maintenance, systems/database administration, and license fees for Command/PEO wide financial systems and applications.

2.1.3.1 Accounting Compliance Reports & Products Functional operations involved in authorizing, recording, classifying, analyzing, and reporting financial information related to financing sources, gains, expenses, losses, transfers, assets, liabilities, equity, and internal controls Includes:

- Billing and payment documentation; funds and accounting approval documentation; unmatched disbursements/negative unliquidated disbursements (UMD/NULO) reconciliation (i.e., pay & payroll documents, Other Customer & FMS Funds Review/Approval/Documentation, Accounting Policy Analysis/Documentation/Fiscal Law opinion, Plant Property Asset Management documents, funds/accounting approval documentation, billing/payment documentation, DoN Financial Improvement Program/Clean Financials.

2.1.3.2 Budget/POM/PR Formulation, Presentation & Defense Development, submission and justification of the Budget and POM/PR submissions. Includes:

- All Budget exhibit development, review and defense; development and submission of all POM/PR materials and responses to actions associated with POM/PR guidance (i.e., serials, warning and planning orders, offsets and excursions); impact statements and reclamas associated with budget and POM process.

2.1.3.3 Funds Allocation & Execution Funds allocation, execution planning and actual execution of funds. Execution planning begins following initial submission of FMB Budget in July. Includes:

- Execution and prior year: control tracking, spend plan management and execution, preparation of funding documents and contract FAD sheets, and monitoring/tracking of commitments, obligations, and expenditures. Also includes responses to data calls and inquiries associated with execution of funds (i.e., Mid-Year Review, impact statements for control adjustments as required, and other data calls on execution year funds utilization).

- Execution allocation and execution includes establishment, allocation, tracking & reconciliation of program funding (i.e., Spend Plans). Execution monitoring includes tracking of commitments, obligations & expenditures.

2.1.3.4 Studies, Reporting, Analysis Data calls, responding to requests for information and resource data analysis. Includes:

- Financial management studies, reporting and analysis not directly supporting budget/POM/PR processes, including input to stakeholder/leadership briefs for Team SPAWAR resources, productivity and other cost trend analysis, and responses to financial data calls which apply across Team SPAWAR.

2.1.3.5Travel Fund ManagementComptroller administration of the Defense Travel System in accounting department. Managing the funds associated with travelComptroller Use Only
2.1.4Logistics ManagementLogistics management directly associated with the Prime Mission Product to include activity to adequately perform supportability analysis and planning for each ILS element and develop logistics plans and reports. Specifically, develop logistics plans and reports to include Integrated Logistic Support Plan (ILSP), Logistic Resources Funding Summary (LRFS), User’s Logistic Support Summary (ULSS), Maintenance Plan, Depot Plan, Material Support Date (MSD) Transition Plan, Program Support Data (PSD), Configuration Management (CM) Plan, Training Planning Process Methodology (TRPPM), Navy Training Systems Plan (NTSP), Job Task Analysis ( JTA), Training System Installation Plan (TSIP), Computer Resources Life Cycle Management Plan (CRLCMP), Packaging, Handling, Storage and Transportation (PHS&T), Program Environmental, Health and Safety (PEHSE), Unique Identification (UID) Plan and Diminishing Manufacturing Sources and Material Shortages (DMSMS) Plan.Develop Logistics Policy, Plans and Reports: Integrated Logistics Support Plan (ILSP),Logistics Requirement Funding Summary (LRFS), Depot Plan, User's Logistic Support Summary (ULSS), Training Planning Process Methodology (TRPPM), Navy Training System Plan (NTSP), Training System Installation Plan (TSIP), Maintenance Plan, Material Support Date (MSD) Transition Planning, Computer Resources Life Cycle Management Plan (CRLCMP), Packaging, Handling, Storage and Transportation (PHS&T), Containers, PSD Development, Program Environmental, Health and Safety (PEHSE), Unique Identification (UID), Diminishing Manufacturing Sources and Material Shortages (DMSMS), Performance-Based Logistics (PDL) Strategy, Life Cycle Sustainment Olan (LCSP), etc.

Includes:

- Management of ILS certifications from a policy/acquisition perspective (all other activities associated with ILS certifications belong in '3.4.4.3 Maintenance of Technical Data & Documentation')

Excludes:

- materials required for systems already in the sustainment phase (that would belong under '3.4.4.2 Maintenance of Technical Data & Documentation'

2.1.4.1 Logistics Management Policy Provide logistics policy for the SPAWAR claimancy to ensure sustainable products are acquired and sustained per Fleet requirements. Excludes:

- materials required for systems already in the sustainment phase (that would belong under '3.4.4.2 Maintenance of Technical Data & Documentation'

2.1.4.2 Logistics Management Assessment Provide PEOs with an assessment at of whether acquisitions will meet sustainability goals after fielding, at IOC and FOC, whether PEO products continue to achieve required fleet operational availability per DoN requirements. Excludes:

- materials required for systems already in the sustainment phase (that would belong under '3.4.4.2 Maintenance of Technical Data & Documentation'

2.1.4.3 Logistics Management Acquisition Logistics management acquisition directly associated with the Prime Mission Product to include activities throughout the system development cycle to ensure the design and acquisition of cost-effective, supportable systems and to ensure that these systems are provided to the user with the necessary support infrastructure for achieving the user's peacetime and wartime readiness requirements. These activities include establishing logistics support concepts, analysis, data and resources in the development, coordination and management of Integrated Logistics Support (ILS) products and services. Specific integrated logistics support planning may include the following: Configuration Management/Status Accounting, Supply Support/Supply Management, System Training Planning and Implementation, Maintenance Engineering and Planning, Systems Integration/Engineering, Systems Operation and Maintenance Training and Technical Manuals, Reliability and Maintainability/System Safety assessments, and Cost/Schedule (Program) Control. Participate in conducting supportability studies, reliability and maintainability analyses, and assessments and remedial actions as required. Translate requirements to specifications and coordinate development of Integrated Logistics Support Plans (ILSP), Maintenance Concepts/Plans, Navy Training Support Pans (NTSP), Acquisition Management Plans, Logistics Requirements and Funding Summaries (LRFS), Program Support Data Sheets (PSD), Warranty Plans and Assessments, Logistics Support Systems Specifications, and Proposals. Includes:

- Studies and Plans, ILSP, LRFS, Depot Plan, ULSS, TRPPM, NTSP, TSIP, Maintenance Plan, MSD Transition Planning, CRLCMP, PHS&T, Containers, PSD Development, CRLCMP, PESHE, UID, DMSMS

Includes: Management of ILS certifications from a policy/acquisition perspective (all other activities associated with ILS certifications belong in '3.4.4.3 Maintenance of Technical Data & Documentation')

Excludes:

- materials required for systems already in the sustainment phase (that would belong under '3.4.4.2 Maintenance of Technical Data & Documentation'

2.1.4.4Logistics Business Case Analysis (BCA)A BCA is a decision making tool used to estimate the costs between alternative support strategies (i.e., traditional or existing vs. proposed alternative). The BCA compares the total estimated product support costs between the baseline support strategy to determine the best value means of supporting a system, subsystem, or component.
2.1.5Internal Project ITInformation Technology directly associated with a Program/Project, including development, maintenance, and operations of applications used to support program/project execution objectives (to include Business and financial systems, internal use software licenses, databases, tools as well as web-site operation/maintenance and webmaster support for Program office web sites for information collection and dissemination.)Program web sites, business financial systems, and other software/tools purchased, developed, maintained to support Program office operations
2.1.6Contract ManagementContract management, including activities associated with Contract Preparation through Contract Award and Contract Management /Execution.
Contract Planning, Solicitation, Evaluation, Negotiation, Award and Post-Award Administration.

Includes:

- Contract management directly associated with the Prime Mission Product and

- Contract management in support of overhead/G&A requirements.

2.1.6.1 Planning Defining requirements, performing market research, developing acquisition planning and strategy, conducting contract planning conference. Includes:

- Products that support planning for contract award or modification. May include Broad Area Announcements, Determination and Findings, FEDBIZOPP, market research findings, J&As.

2.1.6.2 Solicitation Preparing the solicitation; publicizing the planned procurement; amending the solicitation, as necessary; communicating with the offerors, as necessary; and receiving the offers. Includes:

- SOWs, SOOs, CDRLS, RFPs, security documentation, Small Business coordination, market research, wage determination, certified cost and pricing waivers, protest litigation, MOPAS.

2.1.6.3 Evaluation Evaluation of proposals received in response to solicitation; identification of the strengths, weaknesses, significant weaknesses, and deficiencies contained in the proposals; and providing a sound basis for the source selection authority (SSA) or procuring contracting officer (PCO) to make an informed and defensible award decision. Includes:

- Oral presentations, establishing competitive range and holding discussions, pre-award debriefings, field pricing assistance, final proposal revision, completion of source selection reports, and business clearances.

2.1.6.4NegotiationDiscussions that occur between the PCO and each offeror within the competitive range and permit the offeror to revise or modify their proposal to correct any perceived weakness that would preclude award without discussions.
2.1.6.5AwardEfforts associated with the award of a contract.Includes:

- Pre-award notification to unsuccessful offerors, award announcements, post-award debriefings, assignment of contract administration/COR and contract/modification distribution.

2.1.6.6 Post Award Administration Post-award contract actions. Includes:

- TDL's, post-award conferences, contract modifications, contract terminations, Contractor Performance Assessment Reporting System (CPARS), contract completion and closeout.

2.1.6.7 Policy Support Efforts needed to interpret and implement acquisition policy and keep workforce up to date on the latest changes in the acquisition process. Includes:

- Interpreting statutes, developing implementing guidance, training the workforce, monitoring compliance and gathering, analyzing and submitting data calls for higher level review.

2.1.6.8Contract Systems/Procurement AutomationIncludes all costs associated with the development, procurement, maintenance, systems/database administration, and license fees for Command/PEO wide contract/procurement systems and applications.Includes : system administration of PD2 (SPS), WAWF, FPDS-NG, EDA
2.1.7TravelAll travel costs, to include airfare, lodging, meals and incidental expenses.The cost of travel (airfare, rental cars, hotel, per diem, etc.)

Includes:

- Cost of travel for CIV/MIL.

Excludes: Labor costs while traveling.

2.1.8Cost Estimation and AnalysisCost and Affordability, Cost as An Independent Variable (CAIV) & Program Life Cycle Cost. The planning of Programs based on realistic projections of the dollars and manpower likely to be available in future years, identifying the total costs of ownership and the major drivers of total ownership costs, and addressing affordability in establishing capability needs.
Program Lifecycle Cost Estimate, Business Case Analysis, Cost Studies, Affordability Assessment (AA), Independent Cost Estimate (ICE), DoD Component Cost Estimate.

Includes:

- PLCCE development; support to ICE and the DoD Component cost position; support of CAIG, NCCA, and SYSCOM Cost Organization; special cost studies; sensitivity analysis; cost risk analysis; Business Case Analysis; response to FMS P&As; any other cost estimation/analysis.

- Cost estimating software procurement/licenses and Command Cost Systems/Database administration.

2.1.9 Legal Legal services relating to the acquisition and program procurement of major C4ISR, Enterprise Information Technology (IT), and Space systems and capabilities, equipment, goods, and services, including the fiscal, accounting, and budgetary aspects thereof. Legal advice provided for all phases of acquisition process, including claims and disputes. Legal reviews and advice on program contracts and acquisition statutes & regulations; intellectual property/trademarks/copy rights/data rights, etc.

Includes:

- Accurate legal reviews and advice/opinions to help ensure compliance with applicable statutes and regulations relating to contracting actions, both pre and post contract award and administration of contracts; proper use of funds for those contacts, and required contract litigation support. The evaluation of contract claims asserted by or against the Navy; FMS and international agreements, including co-production, cooperative research and development and related agreements, and matters relating to the Arms Export Control Act; all matters within the field of intellectual property, including patents, invention disclosures, trademarks, copyrights, royalty payments, technical data, infringement claims/litigation and similar matters.

2.1.10 Foreign Military Sales - Pre Letter of Request Identify & Analyze Requirements External Communication Activities to Generate & Identify Requirements

Develop Proposed SolutionsFMS Admin
2.1.11Foreign Military Sales - Case DevelopmentReview & validate Letter of Request and/or Standardized Training List (STL)

Initiate Letter of Offer and Acceptance (LOA), Amendment, Modification, P&A, Notifications

Provide LOA DataFMS Admin
2.1.12Foreign Military Sales - Case ExecutionImplement FMS Case

Produce FMS Funding Docs/Contract Development Planning FMS Order Fulfillment/Country Allocations Transactions Manage FMS Deliveries of Articles and/or Services Manage FMS/Monitor FMS Case/Country Allocations Execution

Support Other SYSCOMs/ActivitiesFMS Admin
2.1.13Foreign Military Sales - Case ClosureVerify/Reconcile Supply/Service Complete Cases
Close CaseFMS Admin
2.1.14Foreign Military Sales - Business SustainingManage Information/Support Required Reporting

Develop Security Assistance Workforce Perform General Administrative Functions Receive, Interpret & Analyze Security Assistance Policy Manage Contractor Support Services Manage Resources Improve Processes Support Business Sustaining Requests for Information

Oversee and Support Database ManagementFMS Admin
2.2Systems EngineeringServices of a technical nature that are directly associated with the efforts of directing and controlling a totally integrated engineering effort of a Prime Mission Product. This element is a roll-up of costs associated with lower levels.Support services for system engineering associated with a Product, includes such functions as translating operational requirements into functional allocations, developing error budgets, and allocating functions to system components.

Excludes:

(1) actual design engineering and the production engineering directly related to the WBS element with which it is associated (1.1), and

(2) systems engineering effort that can be associated specifically with the equipment (hardware / software) element (sub-elements of 1.1), and

(3) efforts covered in other WBS elements, for example:

a. risk management associated with 2.1.1 (Acquisition Management);

b. training plan preparation and general logistics plans associated with 2.1.4 (Logistics Management);

c. implementation and execution of configuration management and configuration status accounting associated with 2.1.6 (Configuration Management);

d. analysis of reliability, maintainability, and availability and supportability assessments associated with 2.2.9 (Logistics Engineering);

e. maintaining a master engineering specification and establishing a drawing depository service associated with 2.5.5 (Data Repository);

f. update, maintenance, modification, integration, and configuration management of software associated with 3.4.1 (Software Maintenance);

g. developing and reviewing CM plans, specs and procedures, ECPs and field changes; maintaining and updating maintenance inspection criteria and procedures, assisting in design reviews, evaluating and validating maintenance actions and their frequency, evaluating or performing testing services or field changes, recommending improvements to test procedures, reviewing technical content of training materials, recommending updates to training materials, etc. associated with sub-elements of 3.4 Sustaining Support.

2.2.1 Studies & Design System definition, overall system design, design integrity analysis, system optimization, system/cost effectiveness analysis, and intra-system and inter-system compatibility assurance; the integration and balancing of reliability, maintainability, producibility, safety, human health, environmental protection, and survivability; security requirements, configuration management and configuration control; quality assurance program, value engineering, assessment of systems inter-operability and integration into host site/platform, design of test and demonstration plans; determination of software development or software test facility/ environment requirements. Usually occurs prior to contract award

Includes:

- Design Studies, Analysis of Alternatives (AoAs), Program Objectives Memorandum (POM) Studies, Trade Studies, Test and Evaluation Strategy (TES).

Excludes:

- Preparation of equipment and component performance specifications which is found in '2.2.7 Requirements Analysis'

2.2.1.1SPAWAR Enterprise Architecture OptimizationAnalytical investigations of systems-of-systems architectural data, typically in an operational context, for the purpose of determining recommendations for the purpose of optimizing the IT and IA Target Architectures in the areas of system and cost effectiveness, interoperability, impacts from changing standards and specifications, and impacts to and from operating procedures.Development of Reference Target Architectures for platforms or capabilities such as NTC, DDGs, CVNS, FMV, etc.
2.2.1.2Capability Fielding Decision SupportAnalytical investigations of system or systems-of-systems architectural data, typically in an operational context, for the purpose of assisting the PEOs/PMWs identify impacts of design and/or fielding decisions.Includes:

Carrier Strike Group Study, DDG Capabilities Build Study, E622 Effectively Study

2.2.1.3 Portfolio Health Assessments Analytical investigations of system or systems-of-systems architectural data, typically in an operational context, for the purpose of informing acquisition decisions on the areas of system and cost effectiveness, interoperability, operational impacts resulting from the loss or addition of specified ID capabilities. Includes:

Portfolio Health Assessments, N81 Studies

2.2.1.4Engineering Risk/Threat AssessmentsProvides advanced risk and threat analyses to support the development and deployment of complex systems or systems of systems.Engineering Risk/Threat Assessment include structured maturity assessments; event chain methodology, probabilistic risk assessments; Failure mode, effects and criticality analysis (FMECA); Failure Modes and Effects Analysis (FMEA); modeling and simulations of key risk factors, and failure timing and propagation models.
2.2.1.5Program / Project Level Studies & DesignSystem level studies for individual programs and projects. Includes other studies not captured in 2.2.1.1 thru 2.2.1.4Includes:

- Trade Studies, design studies, cost/effectiveness studies, performance studies, and analytical investigation of engineering and technical data to determine or predict system performance

2.2.2 Architecture Operational System of Systems (SoS) and System Level Architecting, modeling and simulation, verification and validation and external interface definition and management. Operational System of Systems (SoS) and System Level Architecting, modeling and simulation, and external interface definition and mgmt.

Includes:

- Information Support Plan (contains OV, SV, and TV)

- The labor required to analyze, design, and develop the interfaces with other host vehicle subsystems.

2.2.2.1Future ArchitectureLeverage existing architecture data from programs/projects, using a rigorous model-based systems engineering process to develop target architectures across the C4I/EIS/Space domains.
Key Enabler for CHENG to execute his role as TA (IT, IA & SYSCOM). SPAWAR Enterprise Architectures (e.g., Thin Line Architectures; DFIA-compliant network architectures). Supports development of POM impact statements addressing: cost, schedule, and performance expectations of select technologies/solutions

2.2.2.2 Architecture Product Development Generation of fit-for-purpose system-of-system architecture products funded by SPAWAR to meet customer (i.e., SPAWAR TA, OPNAV, PEO, Other Customer) needs that are not directly attributable to other POR/Sponsor tasking. Includes:

Baseline Architectures (e.g., Mission Technical Baselines (MTBs), Integrated Capability Technical Baselines (ICTBs)

2.2.2.3Program Level ArchitectureGeneration of system architecture data and products directly attributable to other SPAWAR/POR/Sponsor tasking.Fee-for-Service DoDAF views
2.2.3Human Systems IntegrationThe engineering process and the series of tasks required to define, as a comprehensive technical and engineering effort, the integration of doctrine, manpower, and personnel integration, materiel development, operational effectiveness, human characteristics, skill capabilities, training, manning implication, and other related elements into a comprehensive effort.Human Systems Integration (HSI) Plan; engineering process to integrate user characteristics into Product Design
2.2.4Technical AuthorityServices in the execution of Technical Authority - establishment, monitoring, and approval of technical standards, tools, and processes in conformance with higher authority policy, requirements, architectures and standards. SPAWAR exercises three types of Technical Authority:

-- SPAWAR SYSCOM Technical Authority -- Navy Information Technology Technical Authority -- Navy Information Assurance Technical Authority (Navy Cybersecurity Technical Authority) Includes:

-- SPAWAR SYSCOM Technical Authority: Enterprise Architectures, Data Strategies, Design Specifications; SPAWAR SE policies and processes -- Navy Information Technology Technical Authority: IT Standards; Operating System Migration; Application Rationalization and Reduction; Mobile; Unified Capabilities/VTC/VOIP -- Navy Information Assurance Technical Authority (Navy Cybersecurity Technical Authority): Cybersecurity Standards, Processes and Policies; Best Practices; Implementation Guidance

2.2.4.1 Standards A standard establishes uniform engineering or technical criteria, methods, processes, and practices. This process mandates SPAWAR/IT/IA and Cyber standards for Navy and supports standardization processes that support TA such as the Defense Standardization Program per OPNAVINST 2000.31A and SPAWARINST 4120.

Develop, review and approve MIL-STDs, SPAWAR and Navy standardization documents, input to industry standards, and Technical Profiles. Establish standards that support TA processes such as for the Configuration Management (CM) Technical Process Owner (TPO). Includes:

-- SPAWAR SYSCOM Technical Authority: SPAWAR Standards (e.g., Common Services); Implementation Guidance

-- Navy Information Technology Technical Authority: IT Standards (e.g., Hosting, Operating Systems)

-- Navy Information Assurance Technical Authority (Navy Cybersecurity Technical Authority): Cybersecurity Standards (e.g., Host Level Protection, Information Systems Continuous Monitoring, Navy Cyber Situational Awareness (NCSA)); Cyber Best Practices; Implementation Guidance; CYBERSAFE Standards

2.2.4.2Interface ManagementInterface Management Process includes the activities of defining, controlling, and communicating the information needed to enable unrelated objects (including systems, services, equipment, software, and data) to co-function.Platform specific C4I Network Interface Documents are used identify and to document SPAWAR to SPAWAR system level Interfaces, SPAWAR to Non-SPAWAR interfaces and all interfaces to the GIG with the purpose of providing visibility and context into inter-system relationships, documenting approved controlling interface specifications, and tracking interface and system modifications. Developing these CNIDs is an important and necessary step toward exerting IT TA and the Interface Management process.
2.2.4.3Systems Engineering Technical Reviews (SETRs)Provide SPAWAR Technical Authority Systems Engineering Technical Reviews (SETRs) based on type of acquisition, maturity of Program / Project, phase in the acquisition life cycle, and decision to be supported by the review. The focus of the independent review is to ensure compliance with Statutory/Regulatory guidance, compliance to the Naval Vision, and implementation of sound systems engineering practices.SPAWAR Chief Engineer Technical Authority SETR fall into one of five types:

- Traditional: predominantly Systems Requirements Review (SRR), System Functional Review (SFR), Preliminary Design Review (PDR), Critical Design Review (CDR), Test Readiness Review / Operational Test Readiness Review (TRR / OTRR)

- Rapid Information Technology (IT) / Streamlining IT: Build Technical Review (BTR) prior to a Build Decision, and Fielding Technical Review (FTR) prior to a Fielding Decision

- Capability Build Review (CBR): CBR - Initial for ensuring requirements are correctly and completely articulated, CBR - Design to assess that the proposed build design…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it.