RFP__N00024-18-R-5102_Batch_No._5_Bidder's_Questions_-_Non-Proprietary_FINAL.docx

DOCX document 19 KB Posted

Attached to
Request For Proposal: Guided Missile Frigate Combat System Ship Integration and Test
Solicitation number
N00024-18-R-5102
Issued by

About this file

N00024-18-R-5012 Batch 5 Bidder's Questions

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment J-13 – Bidder’s Question Submittal Form N00024-18-R-5102 – Guided Missile Frigate (FFG(X)) Combat System (CS) Ship Integration & Test (SI&T)

Please complete the highlighted fields. For additional questions, please copy the above table onto a separate page for each additional question. Company name must be completed for tracking purposes. However, company names will be withheld from any responses distributed by the Government. Please clearly indicate if a question or comment contains proprietary information. DO NOT SUBMIT CLASSIFIED QUESTIONS USING THIS FORM.

Batch No.: 5
Question No.: 1
Date: June 5, 2018
Source Document
Page Number
Item
Excerpt of Content
Proprietary Information
RFP
91, 133
Section H LOE Alternate I

Section L, sub-section 10.6 Volume VII Factor 5: Cost/Price Proposal Section H LOE Alternate I paragraph a) states that the total level of effort for the performance of this contract shall be 1,408,300 total man-hours of direct labor. Section L, sub-section 10.6 Volume VII Factor 5: Cost/Price Proposal 10.6.2, sub-section 2 – Pricing Support Information states that the Basis of Estimates shall include CLIN 0001, 0002, 0006 and 0011. The bullets below that statement identify specifically that the offeror shall present all direct and indirect labor costs associated with each BOE in a separate appendix.

Non-Proprietary

Question/Comment & Requested Action

CLINs 0001 and 0011 are completion tasks identified in Section B to be CPIF, and the hours for these two CLINs are not included in the total level of effort of 1,408,300 man-hours. Will the government offer guidance on how to estimate and price these two CLINs, 0001 and 0011, after the entire LOE has already been allocated across the other CLINs in Section B?

Government Response

The 1,408,300 man-hours are for LOE CLINs only. The 1,408,300 man-hours do not include completion CLINs 0001 and 0011. The Government will not provide hours for the completion CLINs 0001 and 0011. The Contractor shall price completion CLINs 0001 and 0011 based on their experience and knowledge and provide BOEs.

Please complete the highlighted fields. For additional questions, please copy the above table onto a separate page for each additional question. Company name must be completed for tracking purposes. However, company names will be withheld from any responses distributed by the Government. Please clearly indicate if a question or comment contains proprietary information. DO NOT SUBMIT CLASSIFIED QUESTIONS USING THIS FORM.

Batch No.: 5
Question No.: 2
Date: June 5, 2018
Source Document
Page Number
Item
Excerpt of Content
Proprietary Information
RFP
128, 140
Section 10.3.2.1

DFAR 252.234-7001

DFAR 252.234-7002

Section 10.3.2.1 Cost Performance states that EVMS management procedures will comply with the EVMS requirements clause of the contract.

Question/Comment & Requested Action

The only EVMS clauses identified are DFARs 252.234-7001 and 252.234-7002 incorporated by reference. Is it the government’s intent that a DCAA certified EVMS be installed in accordance with 252.234-7002 or will an EVMS like system with similar management and reporting processes be acceptable in performance of this contract?

Government Response

The Contractor shall comply with DFARs 252.234-7001 and 252.234-7002 for EVMS.

Please complete the highlighted fields. For additional questions, please copy the above table onto a separate page for each additional question. Company name must be completed for tracking purposes. However, company names will be withheld from any responses distributed by the Government. Please clearly indicate if a question or comment contains proprietary information. DO NOT SUBMIT CLASSIFIED QUESTIONS USING THIS FORM.

Batch No.: 5
Question No.: 3
Date: June 5, 2018
Source Document
Page Number
Item
Excerpt of Content
Proprietary Information
RFP
1
Block 9
Submission date is currently 9 July 2018

Question/Comment & Requested Action

The government’s response to question 1 or 2 may cause the need for significant rework in staffing allocations and cost estimates. Would the government allow a two-week extension in order to recover from the impacts of your answer.

Government Response

No, The government does not agree with the request to extend the proposal due date.