N00024-18-R-4400_A0003.pdf
PDF 176 KB Posted
- Attached to
- USS HIGGINS FY18 EDSRA Federal contract opportunity
- Solicitation number
- N00024-18-R-4400
About this file
N00024-18-R-4400 Amendment 0003
View the file
Other files for this federal contract opportunity
Show all 37
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N0002418FR93020
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this Amendment is to delete tw o w ork items (857-11-004 & 857-11-006) and revise the avail start date to 27 Aug 18 and end date to 20 SEP 19.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 39
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 27-Mar-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N0002418R4400
X 9B. DATED (SEE ITEM 11)
31-Jan-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
27-Mar-2018
CODE
NAVAL SEA SYSTEMS COMMAND (HQ)
1333 ISAAC HULL AVE SE
WASHINGTON NAVY YARD DC 20376-2030
N00024 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N0002418R4400
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
SCOPE OF WORK
1. GENERAL REQUIREMENTS
1.1 The Contractor under the direction of the Regional Maintenance Center (RMC) and as an independent Contractor and not as an agent of the Government, shall furnish the material, support (electrical, crane, rigging, etc.) and facilities (except those furnished by the Government under express provisions of this contract) and provide the management, technical, procurement, production, testing and quality assurance necessary to prepare and accomplish the repair and alteration of the FY18 USS HIGGINS (DDG 76) Extended Dry-Docking Selected Restricted Availability (EDSRA) in accordance with the requirements stated in this Section, the Work Item Specifications and Work Item Plans, Drawings, and Other References, the Delivery Schedule, and all other terms and conditions set forth in this contract. Category I NAVSEA FY18 Standard Items through CHG 1 identified under Attachment J-1 are applicable to all items without further reference.
Category II NAVSEA FY18 Standard Items through CHG 1 are applicable when invoked and/or referenced in individual work items specified in Attachment J-1.
NAVSEA Standard items may be found at:
http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI.aspx
1.2 The Contractor shall accomplish planning and scheduling to ensure a rational, integrated and timely plan for receipt, storage and installation of Government Furnished Material as identified in work item specifications, and for accomplishment of production work.
1.3 The Contractor shall provide an integrated milestone plan for the availability. These milestones will include a schedule of key events necessary to meet the contract delivery dates. A critical path analysis and a milestone schedule shall be used to measure schedule accomplishment of the functions and elements required to successfully complete the repair and alteration of FY18 USS HIGGINS (DDG 76) EDSRA within the availability dates herein.
1.4 INTEGRATED PRODUCTION SCHEDULE DEVELOPMENT, UPDATE, AND REVIEWS –
In support of NAVSEA Standard Item requirements and to confirm the contractor has all available input for development of the Integrated Production Schedule, including the development of the Integrated Work Package, Production Schedule, Integration of O, I and D level Work, Integration of AIT and SHIPALT requirements and any other contractor assigned or Third Party work scheduled for accomplishment concurrent with the CNO availability, the contractor shall, with the Regional Maintenance Center (RMC), conduct the Work Package Execution Review (WPER). The WPER will take place at the RMC located at the vessel’s homeport. The RMC will schedule the WPER per the Joint Fleet Maintenance Manual (JFMM) Milestones either as a separate event or concurrent with an Integrated Project Team Development (IPTD) event no later than A-30 for CNO availabilities. This review shall be accomplished following the JFMM, Volume II, Integrated Fleet Maintenance requirements including the Critical Time Period, First 100 Hour Plan. Final 100 Hour plan and identify any schedule or scope impact. See Appendix E of the JFMM II-I-2E-1. The JFMM can be found at https://www.submepp.csd.disa.mil/JFMM/index.htm.
The Contractor shall formally present its Integrated Production Schedule to the Navy Supervisory Authority (NSA) at the WPER, Start of the Availability, 25% complete conference, 50% complete conference, 75% complete conference, production completion meetings, and for pre Sea Trials requirements. The Integrated Production Schedule shall include Alteration Installation Teams (AIT), Government-Contracted Third Party Maintenance Providers, Ship's Force, Commercial Industrial Services (CIS), and Fleet Maintenance Activity (FMA) work to the maximum extent this information is available. At each meeting, the contractor shall present and explain, at minimum, the following information:
1.4.1 The Contractor's latest, Government approved, Integrated Production Schedule created in full compliance with Standard Item 009-60.
1.4.2 The Contractor's current progress in preparing for and/or executing the Availability in accordance with their Integrated Production Schedule. The Contractor shall provide an explanation and mitigation plan for any preparation or execution delays in comparison to their Integrated Production Schedule.
1.4.2.1 The Contractor's plan shall describe opportunities for schedule acceleration (at no cost to the Government unless directly related to a Government caused delay) and potential risks and mitigations to remaining schedule attainment.
1.5 Wherever the term “Job Order” is used in this solicitation/award, it also means “Contract.”
1.6 The Contractor shall report and recommend corrective action during contract performance for those deficiencies discovered which are not covered by the work specifications. As found conditions, needed repairs and corrective action reports will be submitted to the Government in the form of a Condition Found Report (CFR). The Contractor's conditions found reporting shall be in accordance with that set forth in Standard Item 009-01.
1.7 The Navy may send a site inspection team to perform an inspection of the contractor's facility prior to arrival of the vessel
1.8 GOVERNMENT FURNISHED MATERIAL: Government Furnished Material (GFM) cited in the solicitation will be shipped to the contractor’s facility at or before A-30. The successful offeror is to coordinate delivery of Government Furnished Material with the Project Manager. Government property permanently removed from a vessel that requires a Property Administrator's disposition instructions shall be properly prepared for shipment and be delivered as directed by the Property Administrator. GFM will be listed in paragraph 5 of the Work Item(s). The successful offeror warehouse that receives GFE is required have a DODAAC number. Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a Department of Defense unit, activity, or organization that has the authority to requisition, contract for, receive, have custody of, issue, or ship DoD assets, or fund/pay bills for materials and/or services. The first positions of the code designate the particular Service/Agency element of ownership.
1.9 FIRE PREVENTION: The contractor will meet requirements of the NAVSEA Industrial Ship Safety
Manual for Fire Prevention and Response (8010 Manual) and NAVSEA Standard Item 009-08. The contractor will account for required fire drills in the proposed work schedule.
1.10 PAINT ABATEMENT: Paint abatement, to include removal of hot paint, will be conducted in accordance with NAVSEA Standard Item 009-32. Paint abatement will be included as part of pricing for all proposals and is not subject to additional growth.
1.11 QUALITY ASSURANCE
1.11.1 QUALITY ASSURANCE PROGRAM - The Contractor shall provide and maintain a quality assurance program acceptable to the Government, and shall perform or have performed the inspections and tests pursuant to that program to substantiate that the material and workmanship provided pursuant to the job order conform to the drawings, specifications, job orders, and contract requirements listed herein. The Contractor's quality assurance program shall be in accordance with that set forth in Standard Item 009-
04. In addition to its rights under clause 252.217-7005 “Inspection and Manner of Doing Work”, the Government shall have the right to deem work or material furnished by the Contractor to be incomplete and not in accordance with the requirements of the job order by reason of the Contractor's failure to comply with the requirements of its quality assurance program and, as such, the Contractor shall not be entitled to progress payments for said work and material.
1.11.2 Quality Assurance Surveillance Plan (QASP) - The Contractor shall meet the performance/acceptable quality level requirements for each deliverable/assessment area in the QASP, Attachment J-5. There will be monetary deductions based on unfavorable contractor performance as stated in the QASP. There is no maximum dollar limit to the deductions which can be assessed against the Contractor for failing to meet the performance/acceptable quality level requirements.
1.12 IDENTIFICATION OF CONDITION FOUND- In accordance with the requirements of NAVSEA
Standard Item 009-01, the contractor shall identify needed repairs and recommend corrective action during contract performance for work/deficiencies discovered which are not covered by the existing work package. For conditions to impact the critical path(s) /controlling item(s), the contractor shall notify the government via electronic media within 24-hours of discovery. This initial notification need not include all content required for a Condition Found Report (CFR), but must include a description of the condition/deficiency and an estimated timeframe for the offeror's professional recommendation for resolution, which shall not exceed five (5) working days as specified below.
Recommended repairs and corrective actions shall be submitted to the Government in the form of a CFR (intended to represent the "Work Request" described in DFARS 252.217-7028 “Over and Above Work”) per CDRL A002.
1.12.1 CONDITION FOUND NOTIFICATION TO GOVERNMENT
CFRs shall be submitted through the Navy Maintenance Database Re-platform (NMDR) within five (5) working days of discovery of the condition. At a minimum, the CFR will include the following:
(1) Identify contract, ship, and hull number
(2) Serialized by CFR number
(3) Identification of the applicable Work Item number
(4) Date requirement was discovered
(5) Description of the work requirement
(6) Specific location of the work
(7) Recommendation for corrective action
(8) Recommendation for the appropriate/best time to accomplish the work (i.e. during current availability with or without schedule change, future CNO or Continuous Maintenance Availability). Provide supporting rationale for the recommendation, such as cost efficiencies, availability of work force, availability of material, premium expenditures, etc.
(9) Identification of related changes, if any, to the internal milestones and production and contract completion dates.
1.12.2 GOVERNMENT REVIEW AND RESPONSE TO CFR
The Maintenance Team will review the CFR. If the CFR is inadequate or incomplete, it will be rejected with time continuing to accrue (relative to five (5) working day requirement). As appropriate, the Government and contractor will need to meet, conduct ship checks and/or discuss the recommendation for corrective action further to determine the full scope of work required prior to final approval of the CFR. The contractor's accuracy reflected in the CFRs submitted may be evaluated in CPARS and utilized for past performance ratings on future requirements. Additionally, deductions may be assessed in accordance with Attachment J-5, QASP.
1.13 REQUEST FOR CONTRACT CHANGE (RCC)
In the event a growth requirement or new work is validated and fully scoped, the Government may generate a Request for Contract Change (RCC) which the ACO may request a firm fixed price proposal from the contractor.
The contractor shall provide all Change Order Price Analysis (COPA) proposals to the ACO in response to RCCs within seven (7) calendar days. A contractor’s COPA shall remain valid for a minimum of 14 calendar days, unless otherwise specified on an individual RCC by the ACO; if another timeline is specified by the Government on an individual RCC, the contractor’s COPA shall remain valid for that amount of time. A COPA addressing a change to the FFP contract shall include at a minimum:
a. Labor hours to be performed by the Prime Contractor __________
b. Subcontractor Quote (If applicable) * $__________
c. Material Quote (If applicable)** $__________
d. Mark-up (If applicable) $__________
*Subcontractor quotes shall include labor hours, labor rate, material (part number, description, unit cost, quantity, total cost, and vendor quotes for each line item), and tiered subcontractor quotes (if applicable)
** Material quote shall include the part number, description, unit cost, quantities, total cost, and vendor quotes for each line item
Note 1: Labor hours for both prime and subcontractor shall be provided broken down by trade and labor mix.
Note 2: The required documentation must accompany the COPA for the COPA to be considered submitted to the ACO. See Attachment J-5, QASP, for deductions associated with late or invalid COPA submittals.
If circumstances arise where the contractor is unable to submit a COPA within seven (7) calendar days, the contractor shall notify the ACO in writing of the specific circumstances and provide a revised date in which a COPA proposal will be submitted. Additional time needed to complete a COPA may be granted solely at the discretion of the ACO. The new timeframe granted, solely at the discretion of the ACO and may differ from the contractor’s request, shall be met by the contractor.
Deductions may be assessed in accordance with Attachment J-5, QASP
1.14 AUTHORIZED CHANGES ONLY BY THE CONTRACTING OFFICER – No order, statement, or conduct of Government personnel who visit the Contractor's facilities or in any other manner communicates with Contractor personnel during the performance of this contract shall constitute a change under the "Changes" clause of this contract. The Contractor shall not comply with any order, direction or request of Government personnel unless it is issued in writing and signed by the Contracting Officer, or is pursuant to specific authority otherwise included as a part of this contract.
The Contracting Officer is the only person authorized to approve changes in any of the requirements of this contract and, notwithstanding provisions contained elsewhere in this contract, the said authority remains solely the Contracting Officer's. In the event the contractor effects any change at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in charges incurred as a result thereof.
1.15 NAVY MAINTENANCE DATABASE (NMD): The Contractor shall use NMD for the submission of Condition Found Reports throughout the administration of this contract. NMD is located at https://mfom.sscno.nmci.navy.mil/MFOM/DodStatement.aspx.
1.16 ORGANIZATION CHART AND EMPLOYEE ROSTER:
1.16.1 ORGANIZATION CHART - Within 30 days of contract award, submit a chart detailing each management, technical, engineering and production position from the highest company level to the lowest supervisory level. Include descriptions of each position describing the duties, responsibilities, authority and names of the individuals filling the positions. The organizational chart must represent the facility that will perform the work.
1.16.2 EMPLOYEE ROSTER: After receipt of award and prior to starting work aboard the vessel, the contractor must submit a list of employees who will work aboard ship to the Commanding Officer of the ship via the NSA Security Office. The list should be on company letterhead, include each employee's name and security clearance when required, and bear the signature of a company official.
2. LOCATION: Government provided pier space may be provided for a limited period. If the contractor elects to utilize the Government pier space, the offload period shall last no longer than 14 days from the start of the Availability before the ship transits to the Contractor’s facility. All other work shall be completed at the contractor’s facilities.
2.1 DRYDOCK CERTIFICATION - The dry-docking of all vessels shall be accomplished in dry docks certified in accordance with MIL-STD-1625D(SH) dated 27 August 2009.
3 SCHEDULE: Upon successful completion of TYCOM Sea Trials, the Contractor period of performance will end on 20SEP19 (A+389). In order to support Dock Trials, Fast Cruise and Sea Trials, USS HIGGINS must be delivered to the government no later than 9SEP19. Ship will return NBSD upon completion of contractor’s sea trials.
3.1 MILESTONES: In addition to the contract completion date of 20 September 2019, the Government has established execution dates for the milestones identified in Attachment J-3.
3.1.1 If any milestone event is not accomplished by the date provided, and the failure to accomplish any such milestone event does not arise from a cause beyond the control and without fault or negligence of the Contractor, such failure may be deemed to constitute a failure to perform this contract in accordance with its terms within the meaning of subparagraph (a)(1)(ii) of the clause of this contract entitled "DEFAULT” (DFARS 252.217- 7009).
3.1.2 The Contractor shall schedule the performance of all items in the USS HIGGINS (DDG 76) SHIP EDSRA work package, including work items included as both Base and Option items, so as to permit a contract scope increase up to 119,199 “hours” and $6,750,736 in “material” to be performed as "Additional Requirements" (including growth and new work).
“Material,” as defined for the application of this paragraph, is defined as physical deliverable materials, exclusive of prime and subcontractor labor. “Hours,” as defined for the application of this paragraph is to include both prime and subcontract labor hours. The contractor agrees that these Additional Requirements, if ordered, shall be performed concurrently with the aforementioned work items, during the contract period of performance, without impacting, accelerating, or causing delay or disruption to the work required by the aforementioned work items, to any other Government contract, or to any other work in progress for the Government. The 'Additional Requirements' cited above are not intended to limit the scope of this contract, which is for a fully mission capable vessel
The "Additional Requirements," if required, shall be ordered during the contract period of performance, as may be modified, on the following schedule:
No more than 75% of the hours or material following the 25% schedule point the availability (as measured in days between the “Start Availability” and “End of Availability” milestones in Attachment J-3).
No more than 50% of the hours or material following the 50% schedule point the availability (as measured in days between the “Start Availability” and “End of Availability” milestones in Attachment J-3).
No more than 25% of the hours or material following the 75% schedule point the availability (as measured in days between the “Start Availability” and “End of Availability” milestones in Attachment J-3).
3.2 DELAYS / DISRUPTIONS: The contractor shall coordinate the work effort with the NSA Project Manager on a daily basis to prevent changing situations from causing delays and disruptions. Disruption due to minor delays in obtaining access to spaces and operation of equipment are to be expected. A minor delay is defined as eight (8) hours or less. These disruptions are considered normal rather than unusual occurrences during the performance of tasks ordered under this contract. If, during contract performance, delays greater than those indicated above are encountered, the Contractor shall immediately verbally notify the Project Manager and Contracting Officer, followed by a written statement within 24 hours after occurrence of delay, stating time of impact, reason for delay, duration of impact, number of people affected, action taken to properly schedule the work, action taken to minimize impact, and the names of the Government person(s) contacted.
3.3 SCHEDULE AND ASSOCIATED REPORTS: The proposed scheduling of work, resources, key events and milestones submitted by the Contractor in accordance with Standard Item 009-60 during the course of contract performance shall not be materially different from the Schedule and Associated Reports provided in the Contractor’s technical proposal.
3.4 MILESTONES FOR CERTAIN REPORTS: Quality Assurance Plan (QASP) Attachment J-5 Deliverable 2: The Contractor shall complete the necessary work associated with the reports due on or before the first 20% of the docking duration as well as the reports due on or before the first 20% of the availability duration and submit to the Government the required reports in the necessary format and containing the required information as specified in the Work Item in accordance with their prescribed due dates or be subject to the deductions provided in Attachment J-5 Quality Assurance Surveillance Plan.
3.5 MILESTONE DEFINITIONS: The following milestones shall be considered achieved (certified) if all work associated with each of the key events as identified in the Key Event Readiness List (ERL) are complete in accordance with this section. All incomplete ERL line items must be accepted and certified by the SUPERVISOR.
The milestones are considered achieved if all heavy industrial work in the compartments associated with each milestone is complete.
“Heavy industrial work” is hot work, cutting, grinding, deck work (PRC, Terrazzo, NOMEX), and spray painting and any other industrial type of work that would either limit compartment access or limit the availability of services in the compartment. Access routes need not be released but must be passable or alternate routes made available at all times.
1. Milestone 1
a) Milestone 1 is considered achieved if all heavy industrial work in the compartments associated with this milestone (listed below) is complete in accordance with work items 438-90-003; 73088K, GEDMS Upgrade.
b) Turnover 1 consists of the following compartments:
4-254-0-E; MER-2
1-158-4-Q; OPS Office 1-206-3-A; Repair-5 1-268-0-C; Central Control Station 1-300-0-C; Combat Systems Equipment Room #3 3-300-0-C; IC/Gyro Room #2 4-370-6-A; Supply Dept Storeroom #4 3-310-2-L; Crew Berthing #5 3-220-2-Q; Supply Support Center 3-126-2-Q; Power Supply Conversion Room 3-97-02-L; Crew Berthing #2 4-94-0-C; IC/GYRO Room #1
4-126-0-E; AUX-1
3-220-01-A; Supply Dept Storeroom #1 3-300-1-L; Crew Berthing #4 3-338-1-L; Crew Berthing #6 2-300-01-L; Crew Berthing #3 1-254-6-L; Passageway 1-174-01-L; Passageway
Contractor shall complete the following contractor responsible work, in accordance with the work items and the compartment release schedule:
Installation of foundations and equipment onto foundations (except AIT installed equipment less than 75lbs).
Installation and Hydrostatic testing of hydraulic piping disturbed by the installation of GEDMS Maintenance Group.
Installation of interferences disturbed by the rip out and/or installation of equipment under this turnover.
Installation and welding complete of new cableways to include cable trays / ladders.
Installation of lagging removed or disturbed by the rip out and/or installation of foundations or equipment under this turnover.
Preservation and painting of new and disturbed foundations and disturbed surfaces.
2. Milestone Turnovers 2
a) Milestone 2 is considered achieved if all heavy industrial work in the compartments
438-90-003; 73088K, GEDMS Upgrade and 438-90-004; 71604K, Machinery Control System Upgrade (MCS).
b) Turnover 2 consists of the following compartments:
4-174-0-E; MER-1
1-206-3-A; Repair-5 1-268-0-C; Central Control Station 1-97-1-A; Repair-2 01-130-2-Q; Admin Office 01-130-0-Q; Combat System Maintenance Central
4-126-0-E; AUX-1
1-78-01-L; Passageway
Installation of interferences disturbed by the rip out and/or installation of equipment under this turnover.
Installation, welding, and air test of access cut(s) required for rigging of equipment under this turnover.
Installation and hydro testing of piping systems removed as interferences or relocated.
Installation and welding complete of new cableways to include cable trays / ladders.
Installation of lagging removed or disturbed by the rip out and/or installation of
3. Milestone Turnovers 3
a) Milestone 3 is considered achieved if all heavy industrial work in the compartments
438-90-003; 73088K, GEDMS Upgrade and 438-90-004; 71604K, Machinery Control System Upgrade (MCS).
b) Turnover 3 consists of the following compartments:
4-174-0-E; MER-1
1-97-1-A; Repair-2 01-130-0-Q; Combat System Maintenance Central
4-126-0-E; AUX-1
4-442-0-E; Steering Gear Room 2-381-2-Q; Electrical Workshop 2-410-2-A; Repair-3 1-304-2-A; Repair-5A / DC Equip Office
Contractor shall complete the following contractor responsible work, in accordance with the work items and the compartment release schedule:
Installation of interferences disturbed by the rip out and/or installation of equipment under this turnover.
Installation, welding, and air test of access cut(s) required for rigging of equipment under this turnover.
Installation and hydro testing of piping systems removed as interferences or relocated.
Installation and welding complete of new cableways to include cable trays / ladders.
Installation of lagging removed or disturbed by the rip out and/or installation of
4. Milestone Turnovers 4
a) Milestone 4 is considered achieved if all heavy industrial work in the compartments
438-90-003; 73088K, GEDMS Upgrade, 438-90-004; 71604K, Machinery Control System Upgrade (MCS), and 438-90-002; 71726K, Integrated Bridge Navigation System Upgrade
(IBNS).
b) Turnover 4 consists of the following compartments:
4-254-0-E; MER-2
4-442-0-E; Steering Gear Room 2-410-2-A; Repair-3 3-370-0-E; #3 Generator Room 4-94-0-C; IC/Gyro Room #1 2-126-2-C; Combat Systems Equipment Room #2 3-300-0-C; IC/Gyro Room #2 02-133-1-L; Passageway 03-142-2-Q; Electronic Workshop #1 1-126-0-C; Combat Information Center 04-130-0-C; Pilot House
Contractor shall complete the following contractor responsible work, in accordance with the work items and the compartment release schedule:
Installation of interferences disturbed by the rip out and/or installation of equipment under this turnover.
Installation, welding, and air test of access cut(s) required for rigging of equipment under this turnover.
Installation and hydro testing of piping systems removed as interferences or relocated.
Installation and welding complete of new cableways to include cable trays / ladders.
Installation of lagging removed or disturbed by the rip out and/or installation of
5. Milestone Turnovers 5
a) Milestone 5 is considered achieved if all heavy industrial work in the compartments
438-90-003; 73088K, GEDMS Upgrade, 438-90-004; 71604K, Machinery Control System Upgrade (MCS), and 438-90-002; 71726K, Integrated Bridge Navigation System Upgrade
(IBNS).
b) Turnover 5 consists of the following compartments:
2-53-1-C; Combat Systems Equipment Room #1 03-142-2-Q; Electronic Workshop #1 1-126-0-C; Combat Information Center 04-130-0-C; Pilot House 2-370-3-A; Supply Dept. Storeroom #2 2-78-01-L; Crew Berthing #1 1-18-0-Q; Sonar Equipment Room #1 01-130-0-Q; Combat System Maintenance Center 2-338-1-L; Passageway
4-370-5-A; Supply Storeroom #3 2-126-1-C; Radio Central 1-84-1-Q; GSE WKSHP / Inert Gas Cylinder Storeroom 2-116-1-T; Access Trunk 03-128-0-C; RADAR Room #1 03-142-0-C; RADAR Room #2 03-128-1-Q; Array Room #1
Installation of interferences disturbed by the rip out and/or installation of equipment under this turnover.
Installation, welding, and air test of access cut(s) required for rigging of equipment under this turnover.
Installation and hydro testing of piping systems removed as interferences or relocated.
Installation and welding complete of new cableways to include cable trays / ladders.
Installation of lagging removed or disturbed by the rip out and/or installation of
6. Milestone Turnovers 6
a) Milestone 6 is considered achieved if all heavy industrial work in the compartments
438-90-003; 73088K, GEDMS Upgrade, 438-90-004; 71604K, Machinery Control System Upgrade (MCS), 438-90-002; 71726K, Integrated Bridge Navigation System Upgrade (IBNS), and 438-90-001 80612K, Integrated Conditioning and Assessment System Install
(ICAS).
b) Turnover 6 consists of the following compartments:
2-53-1-C; Combat Systems Equipment Room #1
4-126-0-E; AUX-1
4-174-0-E; MER-1
4-254-0-E; MER-2
3-370-0-E; #3 Generator Room 03-142-2-Q; Electrical Load Center Room #1 1-254-2-Q; Electrical Load Center Room #2 3-126-2-Q; Power Conversion Room #1 3-319-0-Q; Power Conversion Room
Installation of interferences disturbed by the rip out and/or installation of equipment under this turnover.
Installation, welding, and air test of access cut(s) required for rigging of equipment under this turnover.
Installation and hydro testing of piping systems removed as interferences or relocated.
Installation and welding complete of new cableways to include cable trays / ladders.
Installation of lagging removed or disturbed by the rip out and/or installation of
7. Milestone Turnovers 7
a) Milestone 7 is considered achieved if all heavy industrial work in the compartments
438-90-003; 73088K, GEDMS Upgrade, 438-90-004; 71604K, Machinery Control System Upgrade (MCS), 438-90-002; 541-90-001; 70403K, Digital Fuel Control System Installation, accomplish, and 437-90-001; 77829K, Installation of RADAR & TDR TLIs for DFM, JP-5 and Potable Water Tanks, accomplish.
b) Turnover 7 consists of the following compartments:
3-18-0-Q; Sonar Room #3
4-126-0-E; AUX-1
4-174-0-E; MER-1
4-220-0-E, AUX-2
4-254-0-E; MER-2
5-300-01-E; A/C Machinery Room 3-370-0-E; #3 Generator Room 4-442-0-E; Steering Gear Room 1-191-0-Q; Crew Galley 02-158-6-L; Wardroom Galley 1-238-1-Q; Scullery 2-414-0-Q; Laundry
Installation of interferences disturbed by the rip out and/or installation of equipment under this turnover.
Installation, welding, and air test of access cut(s) required for rigging of equipment under this turnover.
Installation and hydro testing of piping systems removed as interferences or relocated.
Installation and welding complete of new cableways to include cable trays / ladders.
Installation of lagging removed or disturbed by the rip out and/or installation of foundations or equipment under this turnover.
8. Milestone Turnovers 8: Engineering Plant Production Completion Date (PCD) (Key Event) a.) Engineering plant Production Completion Date (PCD) is an availability key event that provides sufficient time for the necessary steps to be taken by Ship’s Force to shift from a maintenance environment back to operations. It is the intent that all major work and cold plant testing in all main propulsion and auxiliary spaces will be complete by all maintenance providers by the scheduled engineering plant PCD. The time reserved between PCD and propulsion plant light off is set aside to allow Ship’s Force to complete pre-event certifications, clearance of tag outs, complete any remaining discrepancy corrections, continued deep cleaning, small valve maintenance, Ship’s Force startup maintenance, valve lineups, temporary service removal, and, if required, any groom teams in areas requiring special emphasis. This time is necessary to allow Ship’s Force to transition to an operational environment and focus necessary training and complete final preparations for the Light Off Assessment (LOA)/propulsion plant light off.
b.) All production work must be complete and satisfactorily tested with required OQE submitted and accepted by the SUPERVISOR, in the main propulsion machinery spaces, steering gear rooms, shaft alleys, pump rooms, auxiliary machinery rooms, to include associated intakes, uptakes, stacks, mixing rooms and government designated fuel tanks prior to the scheduled Light-Off Assessment.
c.) The term complete is defined to mean the accomplishment of all contractor responsible work that is possible without lighting off the ship’s service gas turbine generators and/or main propulsion generators. The following non inclusive list contains examples of items worked via the Contract to be considered when deciding whether or not the NSA is ready to call engineering plant PCD and begin the shift from a maintenance environment back to operations:
Temporary services removed, except for those required by Ship’s Force or late emergency industrial activity work required for LOA.
Access openings and ladders installed and clear for passage.
All damage control/firefighting systems worked during an availability and satisfactorily tested and returned to operational status.
o These systems include, but are not limited to: Casualty Power, Emergency Lighting, Aqueous Film Forming Foam (AFFF), Carbon Dioxide, Fire main, Halon, Main Drainage, and Secondary Drainage systems.
Major lagging repairs, painting, and flange shielding completed. Some minor lagging repairs, painting, and flange shielding may remain pending agreement with the Maintenance Team.
Completion of any remaining work will be de-conflicted by Ship’s Force, NSA’s Project Manager, and Prime Contractor’s senior Project Manager to minimize effect on shipboard training.
All machinery in-place and assembled with cold checks completed satisfactorily in accordance with current instructions.
All deck plates and supports installed.
All industrial tools, material and debris removed.
All main propulsion and auxiliary piping, valves, and systems intact, hydrostatic tightness tests completed satisfactorily and remote valve operator and associated/indicator tests completed satisfactorily.
Engineering and auxiliary space turnover complete.
Ship distributed systems that impact engineering or auxiliary spaces are in intact and operational.
9. Milestone Turnovers 9: Dock Trial (DT), Fast Cruise (FC), and Sea Trials (ST) (Key Event)
i. Dock Trial and Sea Trials are defined in the JFMM as an availability key events that constitutes the final determination of a ship's material readiness and ability to rejoin the Fleet as a fully operational unit. For contractual purposes, Dock Trials and Sea Trials is defined as follows:
ii. All equipment/systems necessary to support underway operations that were worked by the contractor during the availability are reinstalled/intact with required shop tests/checkpoints satisfactorily completed.
iii. Recognizing that the Commanding Officer is the final authority on determining ship preparedness to go to sea, the following should be assessed in making the determination that the contractor has met the Sea Trial milestone and that the ship is prepared to conduct underway operations:
Propulsion and propulsion related machinery reinstalled/intact with required contractor checkpoints completed. Ship’s force should complete equipment hot/cold checks as required by EOSS/PMS. In addition to all main propulsion systems and support systems, this equipment includes steering and damage control systems.
All temporary rigging removed from the ship, unless specifically required for Sea Trial evolutions.
Messing and sanitary facilities operational and available for use.
Power boats to be used in an emergency shall be fully operational, fitted out, and provisioned as prescribed by applicable references.
All davits shall be operational.
All air inflatable lifeboats shall be onboard and properly installed and within PMS certification requirements.
All navigation devices and equipment shall be tested to ensure proper operation.
Work on all compartments whose water tight integrity is essential to the safety of the ship shall be completed and, where authorized, satisfactorily tested.
iv. The ship’s CO is responsible for conducting Sea Trials in accordance with an agenda developed by the NSA, concurred on by the Ship’s CO and approved by the ISIC.
v. Since the purpose of the trial is to determine the material readiness of the ship, all systems/equipment overhauled by the contractor will be tested in accordance with a contractor-prepared test procedure which will document the results of the test and require operation of the system/equipment in all modes. A Ship's Force Trial Officer will be appointed to coordinate with the Prime Contractor Trial Coordinator throughout the Sea Trial. The Trial Officer will accept the results of all tests for the ship. Ship's Force personnel will operate all equipment during the Sea Trial in accordance with standard operating instructions or Sea Trial test procedures, as appropriate.
10. Milestone Turnover 10 Undock Ship (Key Event)
Undocking is identified as a key event in the JFMM, Volume II, Part I that is identified for inclusion in the production schedule. The undocking key event shall a mutually agreed upon time between the NSA, contractor, SF and all other Maintenance providers for undocking the ship. At this time ALL work items identified as drydock related are complete or if NOT complete, documentation has been provided and approved through the NSA Chief Engineer as safe for undocking with necessary provisions. Complete is defined as all CARs, CFRs, OQE (including docking reports), Testing and WAF evolutions are appropriately completed/closed and satisfactorily answered. Undocking shall be considered complete when the ship safely crosses the sill of the dry dock.
11. Milestone Turnovers 11: Habitability Work Complete (Milestone)
This milestone is considered complete when all contracted work that impacted habitability spaces and habitability support systems is completed. Completion of habitability spaces shall be evidenced by closeout of spaces per NAVSEA Standard item 009-81. Minor exceptions are allowed, provided they do not interfere with Ship’s Force daily operations nor pose a sanitary concern. Key areas of concern are: safety of the crew, sanitation and serviceability of food preparation, serving, and eating areas;
livability of berthing and sanitary spaces; cleanliness. The following non inclusive list contains examples of items (including associated machinery, equipment, electrical, alarm, control, piping, and ventilation systems) required for Habitability Work Complete milestone to be met:
a. Messing, berthing, and living compartments, including galley, scullery, pantry, mess decks, walk-in freezer, chill and thaw boxes, dry provisions and breakout storerooms, wardroom, CPO mess, berthing compartments, staterooms, lounges, wash rooms, water closets and showers, laundry, and associated passageways and access routes.
c. Refrigeration and air conditioning machinery rooms complete. Walk-in freezer, chill and thaw boxes shall be intact, tested and operational. e. Office spaces utilized by Ship’s Force in the execution of their duties are complete.
f. Medical and dental spaces are complete.
While some specific Ship’s Force requirements (e.g. availability of LAN, fitness facilities, etc…) may impact the date upon which Ship’s Force chooses to return to the ship, this milestone will be considered complete when the above requirements are met. The actual date for Ship’s Force return will be coordinated by Ship’s Force, NSA’s Project Manager, and KTR.
12. Milestone Turnovers 12: Combat Systems AEGIS Light Off (Key Event)
Combat System Testing milestone is considered complete when all contracted work that impacts Level 3 testing of Combat System equipment, including support systems, is completed to the degree to provide for uninterrupted Level 3 testing. Minor exceptions are allowed provided they do not interfere with Ships Force ability to operate the equipment. Completion of Combat System spaces shall be by closeout of spaces per NAVSEA Standard item 009-81 with documented exceptions.
Level 3 testing is the initial light off of the individual cabinet/equipment. This requires services to the cabinet/equipment.
The following services shall be available on a continuous basis to support Combat System Testing:
115 volt 60 Hz single phase power, 115 volt 60 Hz 3 phase power, 115 volt 400 Hz single phase power, 440 volt 400 Hz 3 phase power, 28 VDC power, 115 volt 400 Hz 3 phase power, 440 volt 60 Hz 3 phase power, Inertial Navigation Systems (INS), Data Multiplex System (DMS), Sound Powered Telephones, HVAC, Sea Water Cooling, Chilled Water, Distilled Water, Electronics Cooling Water, HP Air, LP Air (100 PSI), Electronics Dry Air, and Ships Service Generators or shore power as appropriate.
For compartments, the degree required includes completion of major industrial work, final paint, completion of compartment air testing and final painting of supporting fan rooms.
For support systems, which are ship wide distributed in nature, the degree required includes complete installation of the branches supporting the combat system and completion of support systems test procedures or applicable portions of the support system test procedures such that the support equipment is operating within design parameters.
To include removal of all staging on 02 Level and above, including all communications antennas.
Includes all production work (including non-skid) above the 02 level shall be completed.
13. Milestone Turnovers 13: 25/50/75 Percent Completion Conferences (Milestone)
Interim Completion Conferences. Milestones to document the availability completion percentage. For these Milestones, the maintenance team shall review and document work listed as complete and verify against OQE and proof of work certification. The emphasis for the maintenance team shall be to certify all work as soon as possible after completion. For any work listed as complete, there shall be follow-on status entries to document OQE on file and completion of Work Certification. If OQE and Work Certification have not been completed, there shall be follow-on status entries to document when it is scheduled to be performed.
14. Milestone Turnovers 14: Contractor End Date (Key Event)
The official end of the Contractors period of performance will be upon completion of the TYCOM approved Sea Trial Agenda. The successful completion of the maintenance and modernization period depends on reaching a mutual agreement among the NSA, Ship’s Force, and MSR that all work authorized in the approved work package specifications and supplemental work authorizations have been either satisfactorily completed, or an agreement has been reached concerning a completion plan and schedule for any items partially completed.
a.) The Contractor shall successfully accomplish the major milestones on, or prior to, the dates listed on the Key Event/Milestone schedule provided.
b.) If any milestone or key event is not accomplished by the date listed, and the failure to accomplish any such event does not arise from a cause beyond the control and without fault or negligence of the Contractor, such failure may be deemed to constitute a failure to perform this contract in accordance with its terms within the meaning of subparagraph (a)(1)(ii) of the clause of this contract entitled "DEFAULT (FIXED-PRICE SUPPLY AND SERVICE)" (FAR 52.249-8) or "DEFAULT (FIXED-PRICE RESEARCH AND DEVELOPMENT)" (FAR 52.249-9), as applicable.
4 SAFETY:
4.1 SAFETY INSPECTOR / FIRE MARSHAL: In addition to the safety standards provided in the specifications, the contractor is responsible for providing an experienced Safety Inspector/Fire Marshal who will accomplish daily inspections of the Contractor's entire work area on the ship, together with the Contracting Office’s Safety Representative. This Inspector or Fire Marshal shall not be one of the Contractor's supervisors or superintendents normally assigned to the ship and shall be identified in the contractor’s approved Safety Plan.
4.2 PERSONAL PROTECTIVE EQUIPMENT: Whenever work is performed aboard U.S. Naval Ships or vessels at piers or dry docks of a Naval Shipyard or Naval Station, Contractor employees (including management personnel) shall have and use at all times the following personal protective equipment:
(a) Protective hard hats that meet the following specifications:
(1) Protective helmets purchased after July 5, 1994 shall comply with ANSI Z89.1-1986, "American National Standard for Personnel Protection-Protective Headwear for Industrial Workers-Requirements," or shall be demonstrated to be equally effective.
(2) Protective helmets purchased before July 5, 1994 shall comply with ANSI Standard "American National Standard Safety requirements for Industrial Head Protection," Z89.1- 1969, or shall be demonstrated by the employer to be equally effective. [Ref. 29 CFR
1910.135 Head Protection]
(b) Approved type Plano or prescription glasses meeting the following specifications:
(1) Protective eye and face devices purchased after July 5, 1994 shall comply with ANSI standard Z87.1-1989, "American National Standard Practice for Occupational and Educational Eye and Face Protection", or shall be demonstrated by the employer to be equally effective.
(2) Protective eye and face devices purchased before July 5, 1994 shall comply with ANSI "USA standard for Occupational and Educational Eye and Face Protection", Z87.1- 1968, or shall be demonstrated by the employer to be equally effective. [Ref. 29 CRF
1910.133 Protective eye and face devices.]
(c) Safety toe shoes, with built-in protective toe box that meet the following specifications:
(1) Protective footwear purchased after July 5, 1994 shall comply with ANSI Standard Z41-1991, "American National Standard for Personal Protection-Protective Footwear", or shall be demonstrated by the employer to be equally effective.
(2) Protective footwear purchased before July 5, 1994 shall comply with the ANSI standard "USA Standard for Men's Safety Toe Footwear", Z41.1 1967, or shall be demonstrated by the employer to be equally effective [Ref. 29 CFR 1910.136 Protective eye and face devices.]
4.3 BLACK OXIDE COATED THREADED FASTENERS (BOCTFs): Due to safety concerns, use of BOCTFs is not authorized when installing or replacing threaded fasteners in the accomplishment of any work required by any Work Item in this contract.
4.4 FORCE PROTECTION CONDITION: The Navy is currently in force protection condition Bravo.
Any costs associated with delays, disruptions, or security precautions associated with this force protection condition level shall be included in your proposal. Contractors will not receive additional compensation for delays, disruptions, or security precautions associated with this force protection condition level.
4.5 FIRE DRILL: The Contractor shall coordinate the execution of a full scale fire drill with the NSA within the first 30 days after the ship's arrival at the contractor's facility. The drill will include at a minimum the requirements of the drill specified in NAVSEA Standard Items 009-08 (Fire Protection at Contractor's Facility; Accomplish) and 009-28 (Fire Prevention Requirements). For the contractor, this drill will require all production work to stop for a minimum of 4 hours during day shift on the selected day.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.