Attachment_11_Past_Performance_Questionnaire.docx

DOCX document 30 KB Posted

Attached to
SQQ-89 Product Supportability and Installation
Solicitation number
N00024-15-R-5202
Issued by

About this file

Attachment 11 Past Performance Questionnaire

View the file

Other files

File Type Posted
Attachment_10_Govt_Questions_and_Comments_(Amendment_0002).pdf PDF
N00024-15-R-5202_Revised_Exhibit_A_CDRLs.pdf PDF
N00024-15-R-5202-0002_Conformed_Solicitation.docx DOCX document
N00024-15-R-5202-0002_Conformed_Solicitation.pdf PDF
N00024-15-R-5202-Amended_02-SPS.pdf PDF
N00024-15-R-5202-0001_Conformed_Solicitation.docx DOCX document
N00024-15-R-5202-0001_Conformed_Solicitation.pdf PDF
Revised_Attachment_3_Staffing_Plan.xlsx XLSX spreadsheet
Amendment_0001_N00024-15-R-5202.pdf PDF
Attachment_10_Govt_Questions_and_Comments_(Amendment_0001).pdf PDF
Attachment_4_Government_Furnished_Propoerty.docx DOCX document
Attachment_5_Subcontracting_Plan.docx DOCX document
Attachment_8_Contractor_Award_Announcement_Information.docx DOCX document
Attachment_7_Contractor_Compliance_Checklist.docx DOCX document
N00024-15-R-5202_RFP.docx DOCX document
Exhibit_A_CDRLs.xls XLS spreadsheet
Attachment_10_Govt_Questions_and_Comments.docx DOCX document
Attachment_9_Government_Facility_Estimate.docx DOCX document
Attachment_1_DD254.pdf PDF
N00024-15-R-5202-RFP.pdf PDF
Attachment_3_Staffing_Plan.xlsx XLSX spreadsheet
Attachment_6_Technical_Data_Rights_List.docx DOCX document
Attachment_2_Installation_Schedule.docx DOCX document
Attachment_3_N00024-15-R-5202_Directions.pdf PDF
Attachment_1_N00024-15-R-5202_Section_C.pdf PDF
Attachment_2_N00024-15-R-5202_Registration_Form.pdf PDF
PSM_SOW_12-23-2014_doc.docx DOCX document
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAST PERFORMANCE QUESTIONNAIRE

Competition Sensitive

CONTRACTOR PERFORMANCE EVALUATION SURVEY

CONTRACTOR NAME: CONTRACT NUMBER:

EVALUATION PERIOD: DELIVERY ORDER NO.:

GOVERNMENT TECHNICAL REPRESENTATIVE:

Name (print) Code Phone

Please read the statements below, indicating your relative level of agreement in the box provided. Past Performance Factors are defined on pages 4 and 5:

OUTSTANDING
GOOD
ACCEPTABLE
MARGINAL
UNACCEPTABLE

1. QUALITY OF PRODUCT OR SERVICE:

(a) The Contractor provided a product or service that conformed to contract requirements, specifications, and standards of good workmanship

(b) The Contractor submitted accurate reports.

(c) The Contractor utilized personnel that were appropriate to the effort performed.

2. SCHEDULE:

(a) The tasks required under this effort were performed in a timely manner and in accordance with the period of performance of the contract.

(b) The Contractor was responsive to technical and/or contractual direction.

3. COST CONTROL:

(a) The Contractor performed the effort within the estimated cost/price.

(b) The Contractor submitted accurate invoices on a timely basis.

(c) The Contractor demonstrated cost efficiencies in performing the required effort.

(d) The actual costs/rates realized closely reflected the negotiated costs/rates.

NOTE: For statements indicating “Unacceptable” or for any additional narratives, explanation may be provided on the attached page.

For Official Use Only N00024-15-R-5202

5 Attachment 11 SOURCE SELECTION SENSITIVE INFORMATION – SEE FAR 2.101 and 3.104

Competition Sensitive

CONTRACTOR PERFORMANCE EVALUATION SURVEY CONTINUED

CONTRACTOR NAME: CONTRACT NUMBER:

OUTSTANDING
GOOD
ACCEPTABLE
MARGINAL
UNACCEPTABLE

4. BUSINESS RELATIONSHIPS:

(a) The Contractor demonstrated effective management over the effort performed.

(b) The Contractor maintained an open line of communication so that the COR and/or Technical Point of Contact were apprised of technical, cost, and schedule issues.

(c) The Contractor presented information and correspondence in a clear, concise, and businesslike manner.

(d) The Contractor promptly notified the Contracting Officer’s Representative, Technical Point of Contact, and/or Contracting Officer in a timely manner regarding urgent issues.

(e) The Contractor cooperated with the Government in providing flexible, proactive, and effective recommended solutions to critical program issues.

(f) The Contractor made timely award to, and demonstrated effective management of, its subcontractors.

NOTE: For statements indicating “Unacceptable” or for any additional narratives, explanation may be provided on the attached page.

Competition Sensitive

CONTRACTOR PERFORMANCE EVALUATION SURVEY CONTINUED

CONTRACTOR NAME: CONTRACT NUMBER:

NARRATIVE EXPLANATION:

PAST PERFORMANCE FACTORS:

Outstanding

· The Offeror’s performance of previously awarded relevant contract(s) met contractual requirements and exceeded many to the customers benefit.

· The assessed prior performance was accomplished with very few or very minor problems for which corrective actions taken by, or proposed to be taken by, the Offeror were, or are expected to be, highly effective.

· Performance of completed contracts either was consistently of the highest quality or exhibited a trend of becoming so.

· The Offeror’s past performance records leads to an extremely strong expectation of successful performance.

Good

· The Offeror’s performance of previously awarded relevant contract(s) met contractual requirements and exceeded some to the customer’s benefit.

· The assessed prior performance was accomplished with some minor problems for which corrective actions taken by, or proposed to be taken by, the Offeror were, or are expected to be, effective.

· Performance over completed contracts either was consistently of high quality or exhibited a trend of becoming so.

· The Offeror’s past performance records leads to a strong expectation of successful performance.

Acceptable

· The Offeror’s performance of previously awarded relevant contract(s) met contractual requirements.

· The assessed prior performance was accomplished with some problems for which corrective actions taken by, or proposed to be taken by, the contractor were, or are expected to be, for the most part effective.

· Performance over completed contracts was consistently of adequate or better quality or exhibited a trend of becoming so.

· The Offeror’s past performance record leads to an expectation of successful performance.

Marginal

· The Offeror’s performance of previously awarded relevant contract(s) did not meet most contractual requirements and recovery did not occur with the period of performance.

· The assessed prior performance reflected serious problem(s) for which the Offeror either failed to identify or implement corrective actions or for which corrections actions, implemented, or proposed to be implemented, were, or are expected to be, mostly ineffective.

· Performance over completed contracts was consistently of poor quality or exhibited a trend of becoming so.

· The Offeror’s past performance record leads to a strong expectation that successful performance will not be achieved or that it can occur only with greatly increased levels of Government management and oversight Unacceptable

· The Offeror lacks a relevant past performance record or past performance information is not available or cannot be determined.

· The Offeror will not be evaluated favorably or unfavorably on past performance.

· Does not meet requirements and contains one or more deficiencies and is unawardable.

To be filled in and submitted with the proposal. This Attachment will NOT be incorporated at award. At award, this Attachment will be marked RESERVED

File details come from the government source that posted it. Updated .