Amendment 0002 - Q A's and Changes to Sections F I and L
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N0002414NR58060
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See Page 2.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 7
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 14-Jan-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N00024-15-R-4202
X 9B. DATED (SEE ITEM 11)
23-Dec-2014
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 5 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
14-Jan-2015
CODE
NAVAL SEA SYSTEMS COMMAND
1333 ISAAC HULL AVE SE - MAIL STOP 2030
WASHINGTON NAVY YARD DC 20376-2030
N00024 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N00024-15-R-4202
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this Amendment 0002 to solicitation N00024-15-R-4202:
1. Under SECTION F - DELIVERIES OR PERFORMANCE the delivery schedule is modified as follows:
The Government requires delivery to be made according to the following schedule:
Item Date 0001 Within ____ months after effective date of contract. (to be filled in by Offeror. Offeror shall propose a delivery date which meets the CLIN 0003 MRG shipset(s) required delivery date per Section F.)
0002 In accordance with DD Form 1423, Attachment J-4 0003 The first MRG shipset shall be delivered no later than 24 months after option exercise with all additional MRG shipsets delivered in six month intervals thereafter.
0004 All MRG assemblies shall be delivered no later than 24 months after option exercise.
0005 The first MRG shipset shall be delivered no later than 24 months after option exercise with all additional MRG shipsets delivered in six month intervals thereafter.
0006 All MRG assemblies shall be delivered no later than 24 months after option exercise.
0007 The first MRG shipset shall be delivered no later than 24 months after option exercise with all additional MRG shipsets delivered in six month intervals thereafter.
0008 All MRG assemblies shall be delivered no later than 24 months after option exercise .
0009 The first MRG shipset shall be delivered no later than 24 months after option exercise with all additional MRG shipsets delivered in six month intervals thereafter.
0010 All MRG assemblies shall be delivered no later than 24 months after option exercise .
0011 The first MRG shipset shall be delivered no later than 24 months after option exercise with all additional MRG shipsets delivered in six month intervals thereafter.
0012 All MRG assemblies shall be delivered no later than 24 months after option exercise .
0013 The first MRG shipset shall be delivered no later than 24 months after option exercise with all additional MRG shipsets delivered in six month intervals thereafter.
0014 All MRG assemblies shall be delivered no later than 24 months after option exercise .
0015 The first MRG shipset shall be delivered no later than 24 months after option exercise with all additional MRG shipsets delivered in six month intervals thereafter.
0016 All MRG assemblies shall be delivered no later than 24 months after option exercise .
0017 3 months after exercise of option
Note: In cases when three or more shipsets are exercised in the immediately preceding option year, the first shipset(s) and/or assembly(ies) delivery(ies) for CLINs 0004 - 0016 shall be required six months after the last required delivery date of the previously exercised option year or 24 months after option exercise, whichever is later.
2. Under SECTION I - CONTRACT CLAUSES the following is modified:
52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)
(NAVSEA VARIATION I) (SEP 2009)
The Government may require the delivery of the numbered line item(s)/subline item(s), identified in the Schedule as an option item(s), in the quantity and at the price(s) stated in the Schedule. If more than one option exists, the Government has the right to unilaterally exercise any such option, in whole or in part up to the total quantity specified in the option item, whether or not it has exercised other options. Option(s) shall be exercised, if at all, by written or telegraphic notice(s) signed by the Contracting Officer and sent within the time(s) specified below:
ITEM(S) LATEST OPTION EXERCISE DATE
0003 31 Mar 2017 0004 31 Mar 2017 0005 31 May 2018 0006 31 May 2018 0007 31 May 2019 0008 31 May 2019 0009 31 May 2020 0010 31 May 2020 0011 31 May 2021 0012 31 May 2021 0013 31 May 2022 0014 31 May 2022 0015 31 May 2023 0016 31 May 2023 0017 31 May 2023
3. Under SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
a. Under A. PHYSICAL FORMAT the following paragraph is modified:
Volumes I, II and III shall be bound together with each Volume and each major section tabbed. The CDs shall follow the same format as the paper copy with volumes and major sections in separate and labeled directories.
The technical proposal (Volume I) shall not contain more than five foldouts. The Integrated Master Schedule provided within the management proposal (Volume II) may be provided as a foldout. Foldouts are not permitted in any other volume. A foldout is defined as any document larger than a standard 8 ½ by 11 inch sized page. Each foldout shall count as one page. The narrative material in the proposal shall be single spaced with type no smaller than 12 point characters and 1 inch margins. A page is defined as one side of a sheet 8 1/2 inches by 11 inches. The page count shall not include cover pages, title pages, table of contents, list of illustrations, tab pages, resumes, Small Business Subcontracting Plans, Reference Information Sheets (RIS) or the Integrated Master Schedule (IMS) described below. Documents, spreadsheet or other data submitted on CD must be compatible with Microsoft Office products. The first page of each volume shall be in accordance with FAR 52.215-1 Instructions to Offerors – Competitive Acquisition.
b. Under Volume IV - Price Proposal, 2.0 SF 33 SOLICITATION SET the following paragraph is modified:
c. RFP Sections B through J - The Offeror shall submit Sections B through J with all appropriate information completed as required by the RFP. The Offeror shall complete the pricing information for all Section B CLINs in accordance with the instructions in Section 3.0 “PRICING PROPOSAL”. The Offeror shall fill-in the proposed delivery date for CLIN 0001 in Section F. This date will become contractually binding upon award.
4. The following questions are answered relative to Solicitation N00024-15-R-4202:
Question 3: In RFP N00024-15-R-4202, the delivery requirements for the first MRG shipset CLIN 0003 on Page 53 state a required delivery no later the 31 Dec 2018. The latest option exercise date for CLIN 0003 stated on Page 70 indicates that the option can be executed as late as 31 May 2017. This indicates that the delivery timeframe for the first MRG shipset could be as short as 19 months after an option order is placed. Please confirm that this is accurate and that the various dates are correct.
Answer 3: See changes made by this Amendment 0002.
Question 4: What is the anticipated contract award date? In order to prepare an IMS meeting the RFP requirements and ensure accurate fiscal year pricing, it is best if we have an assumed start date.
Answer 4: The Offeror may assume a contract award date of their choice for the purposes of developing an IMS.
Question 5: Section C.4.5 refers to “modify Contractor Furnished Equipment CPP Hydraulic Pump”, please clarify that this is “government furnished equipment” relative to this subject contract.
Answer 5: The subject pump, as specified in paragraph 1.2.3 of Attachment J-1, is classified as "Equipment to be furnished by the Contractor for Factory Testing", and is not furnished by the Government.
Question 6: CLIN 0001 Delivery is required "Within 12 months after effective date of contract." If CLIN 0001 design exceeds this period can the offeror propose a schedule in which CLIN 0001 delivery exceeds 12 months but provides delivery of the CLIN 0003 shipsets within the required timeframe?
Answer 6: See changes made by this Amendment 0002.
Question 7: In cases where an FY option quantity of 3 shipsets is selected and the following FY selects 1 or more shipsets, the 3rd shipset of the initial year will fall on the same delivery date as the initial shipset of the second year.
In these cases will the statement “all additional MRG shipsets shall be delivered in six month intervals thereafter" applies across all line Items and not just within an line item. Can the subsequent year shipset (CLINs 0005, 0007, 0009, 0011, 0015) allow for delivery to be required six months after the previous exercised shipset delivery or 24 months after option exercise, whichever is later?
Answer 7: See changes made by this Amendment 0002.
Question 8: In cases where an FY option quantity of 3 shipsets is selected and the following FY selects 1 or more shipsets plus 1 or more assemblies, there is a potential to have up to 2 shipsets and 2 assemblies (6 MRG assemblies in total) due for delivery on the same date. In this case can an alternate due date for the assemblies be negotiated at time of option exercise?
Answer 8: See changes made by this Amendment 0002.
Question 9: Testing on a single assembly when a single assembly is ordered (e.g. 0004AA, 0006AA, etc) will not have another assembly or half shipset available to accomplish production testing (using the back-to-back testing method). To accomplish the required acceptance test, either one of the shipset orders and/or the single assembly order will have to be impacted to allow test of the single assembly. In this case can an alternate delivery date for the assembly and other shipset deliveries will be negotiated at the time of exercise to allow for acceptance testing of the single assembly using the back-to-back testing method or will the Navy consider procuring a CLIN 0004 Assembly to remain at the production site through the duration of production to serve as dedicated test equipment. This reduces delivery risk on all subsequent year orders and enables single unit testing. This final unit would be delivered as the last production unit under the contract.
Answer 9: No. The Government will not procure a CLIN 0004 Assembly to remain at the production site through the duration of production to serve as dedicated test equipment. All delivery dates are as specified in the RFP.
Question 10: 52.217-7 OPTION FOR INCREASED QUANTITY, allows CLIN 0003 option exercise as late as 31 May 2017. This does not support a hard CLIN 0003 first shipset delivery date of 31 Dec 2018 (~19 mos). All other CLIN deliveries are set as contingent: "months after option exercise." Additionally, First Article Testing must be done on this unit prior to delivery (up to 3 months). The latest option exercise date for CLIN 0003 must support the first unit manufacturing and testing of 24 plus 3 months to ensure low risk first shipset Dec 2018 delivery.
Answer 10:
See changes made by this Amendment 0002.
Question 11: Long Lead-Time Material (LLM) is customarily ordered upon the completion of CLIN 0001 PDR to support first article manufacturing and testing, and in this case is needed to support low risk 31 Dec 2018 first shipset delivery. Since CLIN 0003 may not yet be exercised, LLM will need to be priced in CLIN 0001. The draft RFP did allow LLM to be ordered after successful PDR per section C.2.6.2.
Answer 11: LLM shall not be included in CLIN 0001 pricing.
Question 12: In reference to "Provide a schedule for design, manufacture, and testing ... including:
1. Design of the reduction gear with designated milestones for design reviews, release for material procurement, delivery of required reports and analyses (as defined in the CDRLs) as well as final release for manufacture.
2. Manufacture and test of the DDG 51 Class reduction gears."
Can the IMS be exempt from the page count so that the requirements can be properly addressed?
Answer 12: See changes made by this Amendment 0002.
Question 13: In reference to "e. Discuss the ability of proposed facilities to manufacture and test the maximum number of reduction gears, (three ship sets), required for delivery in any one year."
Note that three shipsets can be ordered in one FY year order, but with a 6-month delivery interval, the maximum from that option is still two (2) shipsets in one year. Looking across multiple option CLINs, if a maximum number of units are ordered in consecutive years, then the equivalent of four (4) shipsets would be delivered in one year (e.g.
the 3rd shipset from FY17, the first two shipsets from FY18, and both FY18 assemblies is the equivalent of four (4) shipsets).
Please clarify what "maximum...three ship sets" is referring to and whether the six months delivery interval applies to this discussion.
Answer 13: The RFP remains unchanged. The Offeror shall comply with the requirements of Section L, Volume II, paragraph e.
Question 14: Please clarify the random selection process for TEP 'total price', including whether both ship sets and assemblies are in each option year selection?
Answer 14: The random selection process for the Total Evaluated Price (TEP) will remain as stated in Section M of the RFP.
Question 15: Will existing weld and NDT procedures, approved for the current DDG-51 program, be acceptable for a new designed MRG provided the weld procedures are applicable to the joint designs specified in the new MRG design? This enables existing DDG51 MRG second tier suppliers to leverage their current approved procedures.
Request that language be added to the statement of work allowing for weld and NDT procedures in use on the current DDG-51 to be utilized for this offering.
Answer 15: All weld and NDT procedures planned for use in performance of this contract shall be submitted to the Government for review and approval per the Performance Specification and CDRL A005.
Question 16: Will existing weld and NDT procedures, approved for current NAVY programs (To MIL-STD-271F, MIL-STD-278F or T9074-AS-GIB-010/271 and S9074-AR-GIB-010/278) be acceptable for a new designed MRG provided the weld procedures are applicable to the joint designs specified in the new MRG design? Request that language be added to the statement of work allowing for weld and NDT procedures in use on the current Navy programs to be utilized for this offering.
Answer 16: All weld and NDT procedures planned for use in performance of this contract shall be submitted to the Government for review and approval per the Performance Specification and CDRL A005.
Question 17: In reference to "D. Certification of Level III (NDT Examiner) personnel shall be based on (1) successful completion of appropriate American Society for Nondestructive Testing Level III Examinations and (2) successful completion of specific and practical examinations based on NAVSEA Technical Publication T9074-AS- GIB-010/271 and associated fabrication documents."
Requiring NDT Level III personnel to have both Tech Pub 271 and American Society for Nondestructive Testing certification is more restrictive than paragraph 1.6 of 010/271 technical publication, and will drive cost to force additional certifications, and is not aligned with industry practice. Industry has or is adopting the Tech Pubs certification.
Recommend modifying the Level III certification requirement to be similar to 4.4.c and require all Level III personnel be certified with NAVSEA's Technical Publication. As an alternative, at a minimum, change the "and" to an "or" so that either one of the certifications are required rather than both.
Answer 17: The RFP remains unchanged.
Question 18: In reference to "Measurements shall be taken on the reference gear(s) by a third-party measurement facility, the selection of which is subject to approval by PMS 400D." Can the government provide a list of acceptable third-party measurement facilities and/or what their criteria for approval is?
Answer 18: No, the Government will not provide a list of third-party measurement facilities or the criteria by which Government approval of the contractor proposed third-party measurement facilities will be granted.
Question 19: In reference to "3.1.1.3 The assembly’s ship's interface arrangements shall be identical (with respect to form, fit, function) to the existing DDG-51 ship design. The specific interface requirements are contained in the ICD. It is the intent of this specification, and required of the Contractor to provide assemblies which minimize the need for ship redesign."
Specific locations for the Isolators and the Snubbers on the gearcase require colocated mounting hard points and impedances which may be slightly different from the current gearcase design. The snubber locations, for example, depend upon the center of gravity (CG) of the gearcase to be most effective and thus lowest cost.
Please confirm that a supplier has the ability, within the overall dimensions of the mentioned foundations, to relocate the isolator and snubber attachments locations on the interfacing surface of each snubber and isolations foundation drawing (Dwg 802-8479485 through 802-8479488).
Answer 19: The Government will not modify the Interface Control Drawings (ICDs). Any proposed design shall meet all interface requirements as contained within the ICDs.
Question 20: In reference to 3.1.1.3 “The assembly’s ship's interface arrangements shall be identical (with respect to form, fit, function) to the existing DDG-51 ship design. The specific interface requirements are contained in the ICD. It is the intent of this specification, and required of the Contractor to provide assemblies which minimize the need for ship redesign."
Using the existing mount is the best means for achieving the stated 3.1.1.3 requirement. To leverage the current Navy DDG51 mount please provide any addition data to support design integration.
(1) Can the Government provide drawings and performance details of the current Vertical, Fore/Aft, and Athwartship Isolators in order to characterize their dynamic performance within overall MRG design.
(2) Additionally, can the government provide the source or sources from where the mounts can be procured. (3) Alternatively, would the government consider providing the mounts as GFE?
Answer 20: (1) The current isolator design characteristics are proprietary data, which cannot be provided by the Government. Please refer to Attachment J-1 which specifies structureborne noise level requirements and the requirements of a structureborne noise isolation system. (2) No, the contractor is responsible for sourcing isolators as part of the overall design. (3) No, the Government will not provide the isolators as GFE.
Question 21: In reference to "3.1.1.3 The assembly’s ship's interface arrangements shall be identical (with respect to form, fit, function) to the existing DDG-51 ship design. The specific interface requirements are contained in the ICD. It is the intent of this specification, and required of the Contractor to provide assemblies which minimize the need for ship redesign."
If existing mount design and performance data is not available, providing the most cost effective mount may best be accomplished by an integration with the vertical snubbler and isolators foundation.
Would the government be open to an MRG solution that provides the vertical isolation foundation along with the gear assembly and its isolation system.
Note that interface drawings like NAVSEA Dwg 8479491 Rev B (DDG 51 Class Input/Output Shaft Positions) reference positions from below the isolator foundations, the surface that was the interface for earlier procurements (1990). This surface would become the interface for the gear vertical support.
Answer 21: The contractor shall comply with all of the specific interface requirements contained in the Interface Control Drawings as provided in the RFP.
Question 22: Section 2.1 provides an order of preference of specifications.
Clarification is needed with respect to welding specification to S9074-AR-GIB-010/278, which appears to be a referenced specification at level c, in the order of precedence list. In appendix B, section 9.0 revisions to earlier MIL-STD-278E and MIL-STD-278F are mentioned. Appendix B appears both above (level b) the referenced S9074-AR-GIC-010/278 if it is explicitly invoked or below (level d) if it is invoked as a default.
Are bidders able to propose weld procedures currently in production for similar reduction gear service or are all bidders required to update to S9074-AR-GIB-010/278?
Will the Navy consider modifying the welding procedure requirement in a direct statement within J-1 (level a) that "all weld procedures shall be updated for compliance to the NAVSEA's Technical Publication S9074-AR-GIC- 010/278" or as an alternative, indicate that "approved weld procedures for existing gears in similar US Navy service may be used without update to NAVSEA's Technical Publication S9074-AR-GIC-010/278."
Answer 22: As per the Performance Specification the appendices are lower precedence documents to the Performance Specification itself. Since T9074-AR-GIB-010/278 is referenced in the Performance Specification then T9074-AR-GIB-010/278 is invoked. Weld procedures shall be as specified in the Performance Specification and CDRL A005.
Question 23: Please provide the Data Acquisition Documents listed below which are cited in block 4 on the CDRL DD Form 1423-1 in Attachment J-4. The document reference numbers could not be located in the DLA ASSIST database or other resources for review.
DI-E-2037
DI-ENVR-80706
DI-HFAC-80938A
AMS-2825
TMCR-NDMS-090122
Answer 23: These documents will be posted with secure access on www.fbo.gov .
http://www.fbo.gov/