N00024-15-R-2428_Amendment_0006.doc

DOC document 114 KB Posted

Attached to
FY15/16 Landing Craft, Air-Cushion (LCAC) Service Life Extension Program (SLEP)
Solicitation number
N00024-15-R-2428
Issued by

About this file

N00024-15-R-2428 Amendment 0006

View the file

Other files

File Type Posted
N00024-15-R-2428_Amendment_0005.docx DOCX document
N00024-15-R-2428_Att-A-__J-1_TDP.docx DOCX document
N00024-15-R-2428_Amendment_0004.doc DOC document
N00024-15-R-2428_Amendment_0003.docx.doc DOC document
Amendment_0002.doc DOC document
Amendment_0001.docx DOCX document
N00024-15-R-2428_Ad_L-3.docx DOCX document
N00024-15-R-2428_Ad_L-4.docx DOCX document
N00024-15-R-2428_Attach_J-4_GFE.doc DOC document
N00024-15-R-2428_Ad_L-2.docx DOCX document
N00024-15-R-2428_Ad_L-1.docx DOCX document
N00024-15-R-2428_Attach_J-2d_Exh_B_Index.doc DOC document
N00024-15-R-2428_Attach_J-2e_Exh_B.doc DOC document
N00024-15-R-2428_Attach_J-3_Perf_Miles_Pay_Sch.xlsx.xlsx XLSX spreadsheet
N00024-15-R-2428_Attach_J-2a_CDRL_Address_List.doc DOC document
N00024-15-R-2428.docx DOCX document
N00024-15-R-2428_Attach_J-2f_CDRL_Information.doc DOC document
N00024-15-R-2428_Attach_J-1_TDP.docx DOCX document
N00024-15-R-2428_Attach_J-2c_Exh_A.doc DOC document
N00024-15-R-2428_Attach_J-2b_Exh_A_Index.doc DOC document
Draft_RFP_for_FBO.docx DOCX document
Draft_Attach_J-2c_Exh_A_.doc DOC document
Draft_Attach_J-4_GFE_(P)_.doc DOC document
Draft_Attach_J-2d_Exh_B_Index_.doc DOC document
Draft_Attach_J-2b_Exh_A_Index.doc DOC document
Draft_Attach_J-1_TDP.docx DOCX document
Draft_Attach_J-3_Performance_Milestones_Payment.xlsx XLSX spreadsheet
Draft_Attach_J-2e_Exh_B_.doc DOC document
Draft_Attach_J-2a_CDRL_Address_List_A.doc DOC document
Bidders_Questions_Form.docx DOCX document
Amendment_0001.docx DOCX document
TDP_Bidder_Question_Form.docx DOCX document
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

REVISED SUMMARY OF CHANGES

The purpose of this amendment to solicitation N00024-15-R-2428 is to:

a) Respond to questions submitted by potential Offerors;

b) Revise Table C-2

c) Revise Table F-1

d) Revise Table F-2

1. The following questions were submitted by potential Offerors. The Government’s response follows each question. Questions and Answers 023 through 024 are provided in this Amendment 0006.

Question 023: It is recommended that the Government move key events 3.2.2 Communication Systems Validation Testing (Government Test), 3.2.3 Mock INSURV Trial, and 3.1 Runway and Harbor Trials (Work Item 982-31-001) from milestone P3, PRODUCTION WORK COMPLETE to the end of milestone P2, FUEL ON LOAD as key events 2.11, 2.12, and 2.13 respectively.

Answer 023: The Government concurs with the recommendation. Table C-2 has been updated in paragraph 2 below to reflect these changes.

Question 024: ACU-5 and ACU-4 two week downtimes starting at Christmas would potentially interfere with critical events for LCACs 58, 65, and 84. It is recommended that the Government move delivery dates for LCACs 58, 65, and 84 to account for the potential interference.

Answer 024: The Government concurs with the recommendation. Tables F-1 and F-2 have been updated in paragraph 2 below to reflect these changes.

2. As a result of the Questions above, changes to the subject solicitation are made as follows:

a. Table C-2 to the subject solicitation is hereby deleted in its entirety and replaced with the following:

TABLE C-2

MILESTONES AND KEY EVENTS

MILESTONE
KEY EVENT
TITLE

P1*

1. CRAFT INDUCTION

X
1.1 Open and Inspect Reports
X
1.2 Electrical Lite Off
X
1.3 Climate Control System Testing
X
1.4 CAMS Lite Off
X
1.5 Fuel System Testing
X
1.6 Halon Testing
X
1.7 Structural Work, Completion and Tightness Testing (exception of 1.12 below)
X
1.8 Powertrain Alignments
X
1.9 Deep Skirt Installation
X
1.10 Internal Communications Testing
X
1.11 Propulsion Systems Work Complete (to include L/O and HYDR systems removed in work Item 120-11-001).
X
1.12 RESERVED
X
1.13 Bay Vacancy
X
1.14 Chock Pull Test

P2*

2. FUEL ON LOAD

X
2.1 CDR Testing
X
2.2 Propulsion and Auxiliary Systems Testing
X
2.2.1 CAMS Control and Sensors Functional Testing
X
2.2.2 Fuel System Operational Testing
X
2.2.3 APU Engine Starts
X
2.2.3.1 Generator Start Testing
X
2.2.3.2 Generator Set Control System Functional Testing
X
2.2.4 ETF40B Engine Starts
X
2.2.5 Balance Lift Fans and Props
X
2.2.6 Engine and Transmission Functional Testing (High Power Runs)
X
2.2.7 BAAS System Testing
X
2.2.8 Cold Weather System Testing
X
2.3 Water Wash System Testing
X
2.4 Ramp System Testing
X
2.5 Exterior Communications Testing
X
2.6 Navigation Systems Testing
X
2.6.1 Radar Functional Testing
X
2.6.2 Embedded GPS/EGI Testing
X
2.6.3 Lights and Horn Testing
X
2.7 Lighting System Functional Testing
X
2.8 Painting
X
2.9 Compartment Close Out Inspections
X
2.10 Infrared Survey (Government Test)
X
2.11 Communication Systems Validation Testing (Government Test)
X
2.12 Mock INSURV Trial
X
2.13 Runway and Harbor Trials (Work Item 982-31-001)

P3*

3. PRODUCTION WORK COMPLETE

X
3.1 INSURV Trial Preparations
X
3.1.1 ACU Craft Preparation Period
X
3.2. INSURV TRIAL
X
3.2.1 INSURV Trial Card Correction Period

4. CRAFT DELIVERY

* - Applicable to B.3.3 Craft Schedule Incentive

b. Table F-1 to the subject solicitation is hereby deleted in its entirety and replaced with the following:

TABLE F-1

ITEM
Craft
MILESTONES DATES

Craft Induction

(Note 1)

Fuel On Load
Production Work Complete
Craft Delivery
LCAC 58
01 Dec 2015
*
*
24 Mar 2017
LCAC 64
07 Jun 2016
*
*
01 Sep 2017
LCAC 65
04 Oct 2016
*
*
02 Feb 2018
LCAC 76
21 Feb 2017
*
*
18 May 2018

* - To be completed by Offeror. The Fuel On Load Date must be a date after Bay Vacancy. The Offeror shall determine the Production Work Complete Date corresponding to the date when work requirements identified in Table C-2, Milestone 2 through Milestone 3 will be complete. For LCAC 58 and 65, the time period between Fuel On Load and Craft Delivery shall be a minimum of five months to accommodate a sufficient period to complete testing requirements. For LCAC 64 and 76, the time period between Fuel On Load and Craft Delivery shall be a minimum of four months to accommodate a sufficient period to complete testing requirements. For LCAC 58 and 65, the Craft Delivery Date shall be 16 months after each Craft Induction Date. For LCAC 64 and 76, the Craft Delivery Date shall be 15 months after each Craft Induction Date.

Note 1 - The Craft Induction Date is the date that Contractor shall initiate SLEP availability. Craft shall not be scheduled for induction on days ACU support is not available as defined in Section C, paragraphs C.1.3.2.3. See EARLY INDUCTION below.

c. Table F-2 to the subject solicitation is hereby deleted in its entirety and replaced with the following:

TABLE F-2

ITEM
Craft
MILESTONES DATES

Craft Induction

(Note 1)

Fuel On Load (T1)
Production Work Complete (T2)
Craft Delivery

(T3) (Note 2)

LCAC 84
01 Dec 2015
*
*
24 Mar 2017
LCAC 85
07 Jun 2016
*
*
1 Sep 2017

* - To be completed by Offeror. The Fuel On Load Date must be a date after Bay Vacancy. The Offeror shall determine the Production Work Complete Date corresponding to the date when work requirements identified in Table C-2, Milestone 2 through Milestone 3 will be complete. For LCAC 84, the time period between Fuel On Load and Craft Delivery shall be a minimum of five months to accommodate a sufficient period to complete testing requirements. For LCAC 85, the time period between Fuel On Load and Craft Delivery shall be a minimum of four months to accommodate a sufficient period to complete testing requirements. For LCAC 84, the Craft Delivery Date shall be 16 months after the Craft Induction Date. For LCAC 85, the Craft Delivery Date shall be 15 months after the Craft Induction Date.

Note 1 - The Craft Induction Date is the date that Contractor shall initiate SLEP availability. Craft shall not be scheduled for induction on days ACU support is not available as defined in Section C, paragraphs C.1.4.1.3. See EARLY INDUCTION below.

3. Receipt of Proposals is not extended as a result of this amendment.

4. Except as provided herein, all other terms and conditions of solicitation N00024-15-R-2428 remain unchanged.

File details come from the government source that posted it. Updated .