This is a preliminary engineer's cost estimate for the Monroe Avenue Drainage Improvements project in Escambia County, Florida, prepared in February 2026 as part of a Hurricane Sally recovery initiative funded through the Community Development Block Grant-Disaster Recovery (CDBG-DR HS005) program. The project encompasses repair and re-stabilization of 500 linear feet of damaged articulated block ditch with Concrete Canvas overlay installation, removal and replacement of a double 36-inch arch pipe culvert with a cast-in-place box culvert, and roadway reconstruction including milling, resurfacing, curb and gutter installation. The scope includes multiple construction line items such as mobilization, clearing and grubbing (4,488 square yards), earthwork excavation and borrow materials (795.8 and 621.2 cubic yards respectively), asphalt paving (244 square yards), concrete ditch paving (1,025 square yards), drainage piping and inlet work, erosion control measures, and permanent stabilization features including centipede sod (1,856 square yards) and rip rap placement (160 square yards). A mandatory pre-solicitation meeting for the related Construction Engineering & Inspection (CE&I) Services solicitation is scheduled for March 11, 2026, with questions due by March 30, 2026, and CE&I service proposals due April 6, 2026.
The total construction cost estimate for the Monroe Avenue project is $704,992.32, comprising a construction subtotal of $607,125.51 and a 20 percent contingency of $97,866.81. Unit prices are derived from the Escambia County General Paving and Drainage Pricing Agreement valid January 1 through December 31, 2026, with additional pricing sourced from an Energy and Environment LLC quote dated February 13, 2026, for Concrete Canvas materials and installation totaling $117,791.45. The county's CE&I service contract preference establishes a maximum cost ceiling of 7.5 percent of estimated construction costs, structured as a "Not to Exceed" agreement based on hourly rates for full-time onsite inspections. Consultants previously awarded contracts for environmental assessment, design services, or owner's representative services on these projects are ineligible to bid on CE&I services. The preliminary nature of this estimate reflects pre-60 percent plan development status, indicating that final construction costs may be subject to adjustment as design plans advance.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Date:
Project No:
Item No. Description Unit Quantity Unit Price Proposed Amount
02100-00101 Mobilization (5%) EA 1 23,301.62$ 23,301.62$
03100-00102 Clearing and Grubbing (Including Trees UNDER 12" dia) SY 4488 3.25$ 14,585.01$
04100-00102 Earthwork Excavation (by machine) CY 795.8 7.00$ 5,570.32$
04100-00104 Earthwork Borrow (Fill) CY 621.2 16.60$ 10,312.10$
04100-00108 Remove and Replace Unsuitable Materials CY 311.1 22.78$ 7,087.11$
04100-00116 Dewatering, Well Point LF 20.0 30.36$ 607.20$
05200-00107 2" Type SP 12.5 Asphalt, less than 1500sy SY 244 12.84$ 3,138.67$
05600-00108 Saw cut Existing Asphalt LF 44 2.50$ 110.00$
05500-00103 Mill Existing Asphalt, 1.5" - 3" Thickness, less than 1500sy SY 244 6.25$ 1,527.78$
06100-00105 12" Stabilized Subgrade, less than 1000sy SY 98 3.75$ 366.67$
06200-00105 8" Graded aggregate Base "Min. LBR 100 at 100% Modified Proctor", less than 1000sy SY 98 33.08$ 3,234.49$
06300-00101 4" Type B-12.5, LBR 100, less than 1000sy SY 98 26.25$ 2,566.67$
07900-00105 Maintenance of Traffic (5%) LS 1 5,700.00$ 5,700.00$ n/a Object Markers (Typ 2) EA 2 115.00$ 230.00$
08100-00103 FDOT Type D curb, FDOT Index 300 LF 356 20.00$ 7,120.00$
08400-00102 FDOT Type Reinforced Concrete Ditch Paving w/ Weep Holes, FDOT Index 281, Min 3.5" thick SY 1025 59.95$ 61,448.75$
08500-00103 Removal of existing concrete up to 6" thick SY 7 6.25$ 43.75$ n/a Culvert Class IV concrete CY 36.1 3,500.00$ 126,350.00$ n/a Straight Concrete Endwall Class IV Concrete, 5'x4'. 0 degree, retangular CY 45.2 3,500.00$ 158,200.00$ n/a Reinforcing Steel - Roadway LB 2320 3.50$ 8,120.00$
09100-00205 Curb Inlet Top, Type 5 EA 2 4,200.00$ 8,400.00$
09200-00603 18" RCP Pipe, 0'-6' depth LF 16 59.14$ 946.24$
09300-00302 18" RCP Side Drain MES, FDOT Index 273, 280 EA 2 1,214.06$ 2,428.12$
09500-00105 Pipe Removal, 30" and larger LF 60 31.25$ 1,875.00$
13100-00101 Centipede Sod, Staked SY 1856 3.00$ 5,568.00$
13200-00101 18" Depth Rip Rap Rubble w/ 4" Bedding Stone and Geotextile SY 160 137.50$ 22,000.00$
13300-00101 Sand Bags EA 21 31.25$ 656.25$
13300-00102 Silt Fence Type III LF 698 1.56$ 1,088.88$
13300-00105 Floating Turbidity Barrier LF 90 27.50$ 2,475.00$
13300-00107 Baled Hay or Straw EA 17 11.25$ 191.25$
13300-00109 Erosion Control Plan EA 1 1,375.00$ 1,375.00$
13300-00112 NPDES Construction General Permit, NOI, NOT EA 1 1,875.00$ 1,875.00$
13400-00101 Remove Existing Rubble (Stone Rip Rap or Concrete) CY 15.1 43.75$ 661.34$
13400-00103 Project Mowing, Maintenance, Litter Control, etc. AC 0.93 187.50$ 173.85$
Subtotal 489,334.06$
N/A Energy and Environment LLC Concrete Canvas Unit Quantity Unit Price Proposed Amount
Concrete Canvas, CCX Mat (28 Short Rolls) SF 14322 5.15$ 73,758.30$
Concrete Canvas, CCT1 Batched, 5 Rolls T1 Batch SF 540 4.25$ 2,295.00$
250mm (10") J Pegs Box (100ea) EA 3 410.00$ 1,230.00$
Screws, Stainless Steel Collated 30mm (1000/EA) EA 5 160.00$ 800.00$
Grout/Sealant EA 1 500.00$ 500.00$
Concrete Anchor Bolts (50 EA) EA 12 185.00$ 2,220.00$
Materials Sales Tax (7.5%) - - - 6,060.25$
Freight Shipment LS 1 2,700.00$ 3,000.00$
Installation LS 1 16,470.30$ 27,927.90$
Subtotal 117,791.45$
Construction Total 607,125.51$
Contingencies (20%) 97,866.81$
Total 704,992.32$
NOTES: 1. UNIT PRICES DERIVED FROM ESCAMBIA COUNTY GENERAL PAVING AND DRAINAGE PRICING AGREEMENT, VALID JANUARY 1, 2026 - DECEMBER 31, 2026
2. CONCRETE CANVAS UNIT COSTS BASED UPON ENERGY AND ENVIRONMENT LLC QUOTE DATED 2/13/2026
Engineer's Estimate
Monroe Avenue Cost Estimate
Feb-26
Preliminary Engineers Estimate - Pre-60% plan development FEMA PD 02-03.79.52.12