This is a cost estimate document for the Brickyard Road FEMA Drainage Improvements project in Florida, prepared as of February 11, 2026. The project involves replacing a 36-inch culvert pipe beneath Brickyard Road that was damaged during Hurricane Sally, with work including roadway reconstruction above the pipe, shoulder armoring, headwall installation, and rip rap placement at the outfall. The estimate encompasses 26 line items covering mobilization, erosion control, unsuitable material removal, dewatering, and traffic maintenance, along with clearing and grubbing across 4,420 square yards, earthwork excavation of 494 cubic yards with 2,067 cubic yards of fill, asphalt removal and replacement, aggregate base installation, articulated concrete block construction across 182 square yards, and pipe installation including 29 linear feet of 24-inch RCP pipe, 76 linear feet of 36-inch RCP pipe, and 134 linear feet of 50-inch jack and bore operations with 36-inch RCP pipe installation.
The probable cost estimate totals $1,454,800.00, with the largest single line item being the 50-inch jack and bore with 36-inch RCP pipe installation at $670,000.00. Other significant costs include unsuitable material removal at $82,500.00, dewatering at $125,000.00, mobilization at $70,000.00, and earthwork fill at $103,350.00. The estimate includes specialized items such as W-beam guardrail installation totaling $16,250.00 and removal of existing infrastructure including the stand pipe, brick wall, and storm pipe. The project is funded through CDBG-DR resources and is part of a larger drainage improvement initiative that includes the Monroe Avenue and Oakfield/Palafox Area Drainage Improvement projects, with the estimate requiring professional Construction Engineering and Inspection services.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pay
Item # DESCRIPTION QUANTITY UNITS UNIT PRICE EXT.
1 Mobilization 1 LS $ 70,000.00 $ 70,000.00
Erosion Control (Silt Fence Type IV, Hay Bales, Floating Turbidity Barrier, SWPPP, NPDES Permit, & Monitoring)
1 LS $ 25,000.00 $ 25,000.00
3 Remove and Replace Unsuitable Materials (Approximately 2,200 CY) 1 LS $ 82,500.00 $ 82,500.00
4 Dewatering 1 LS $ 125,000.00 $ 125,000.00
5 Maintenance of Traffic 1 LS $ 12,500.00 $ 12,500.00
Clearing and Grubbing (Including Trees UNDER 12" dia.), per County Specifications 2230
4420 SY $ 6.25 $ 27,625.00
5 Earthwork Excavation by machine 494 CY $ 25.00 $ 12,350.00
6 Earthwork Fill 2067 CY $ 50.00 $ 103,350.00
7 Earthwork Establishing Grade 4420 SY $ 5.00 $ 22,100.00
8 Centipede Sod, Staked 3913 SY $ 6.25 $ 24,456.25
9 Remove Existing Asphalt 3"-6" Thick 325 SY $ 10.00 $ 3,250.00
10 2" Type SP 12.5 Asphalt, over 1500sy 325 SY $ 18.75 $ 6,093.75
6" Graded aggregate Base "Min. LBR 100 at 100% Modified Proctor", over 1000sy
358 SY $ 62.50 $ 22,375.00
12 12" Stabilized Subgrade, over 1000sy 390 SY $ 12.50 $ 4,875.00
13 Construct Articulated Concrete Block 182 SY $ 312.50 $ 56,875.00
14 Rubble Riprap w/Filter Fabric & Bedding Stone (18" thick) 30 SY $ 250.00 $ 7,500.00
15 24" RCP Pipe 29 LF $ 200.00 $ 5,800.00
16 36" RCP Pipe 76 LF $ 343.75 $ 26,125.00
17 50" Jack & Bore + 36" RCP Pipe Installation 134 LF $ 5,000.00 $ 670,000.00
18 24" Mitered End Section (FDOT Index No 430-022) 1 EA $ 5,625.00 $ 5,625.00
19 36" U-Type Concrete Endwall (FDOT Index No 430-012) 1 EA $ 25,000.00 $ 25,000.00
20 Type "D" DBI (FDOT Index No 425-052) 1 EA $ 10,000.00 $ 10,000.00
21 Doghouse Type "D" DBI (72" Ex Pipe) >6' in depth 1 EA $ 31,250.00 $ 31,250.00
22 W Beam Guardrail with Posts per FDOT Index No 536-001 260 LF $ 62.50 $ 16,250.00
23 End Anchorage Assembly per FDOT Index No 536-001 4 EA $ 6,875.00 $ 27,500.00
24 Remove Existing Stand Pipe 1 LS $ 2,500.00 $ 2,500.00
25 Remove Existing Brick Wall 1 LS $ 25,000.00 $ 25,000.00
26 Remove Existing Storm Pipe (Over 24" Diameter) 78 LF $ 50.00 $ 3,900.00
Grand Total =
BRICKYARD ROAD FEMA - DRAINAGE IMPROVEMENTS
FEBRUARY - PROBABLE COST ESTIMATE
$1,454,800.00