This document is LBNL's Response to Questions 3 regarding RFQ MG-05222024 for SR PTL Vacuum Chambers. The RFQ indicates that LBNL is seeking a single vendor to provide the entire scope of work, though the vendor may propose an alternative delivery schedule. The first article must be delivered 10 weeks after First Article Approval, with production items due 35 weeks after the First Article's Approval. The RFQ also includes the solicitation number, agency (Department of Energy), anticipated award date, response instructions, and a list of required documents such as the Statement of Work, General Provisions, and Price Proposal Schedule.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LBNL Response to Questions 03 Re: LBNL RFQ MG-05222024 – 05/31/2024
1. Is LBNL looking to source the entire SOW from a single vendor, or can the supplier choose which parts they may submit a quote for?
LBNL Response: The quote must be for the entire scope.
2. Regarding the schedule in the SOW:
Is that for all items all at once, everything and all quantities are due 35 weeks after approval of the first article? Or could it be staggered delivery starting after the 35 weeks?
LBNL Response: The first Article is to be delivered 10 weeks After FDR’s Approval and the production items are to be delivered 35 weeks After the First Article's Approval. The vendor, however, may propose an alternative delivery schedule.