MB-1791 MGCW PLANS signed.pdf

PDF 3 MB Posted

Attached to
Myriad Gardens Chilled Water Installation
Solicitation number
MB-1791
Issued by
Oklahoma County, Hobart City, Oklahoma

About this file

The document is a comprehensive set of mechanical design and construction documents for the Myriad Gardens Chilled Water Installation project in Oklahoma City, Oklahoma. The project is being undertaken by the City of Oklahoma City's Public Works Department and involves the installation of new chilled water piping, air handling units (AHUs), and associated mechanical systems. The project is scheduled for bid on August 4, 2025, with detailed plans for replacing and modifying existing HVAC infrastructure at the Myriad Gardens facility located at 301 W. Reno Avenue. The design includes demolition of existing air handling units, installation of new air handlers, chilled water piping, control valves, and associated mechanical components across multiple building levels.

The project involves seven new air handling units, each rated at 42.3 tons with a flow rate of 101 GPM, connected to a 6-inch chilled water supply and return system. The design includes specific routing instructions for piping, careful coordination with existing building structures, and provisions for minimal disruption to the facility. The mechanical design by Olsson engineering firm includes detailed specifications for valve types, actuators, and connection methods, with careful attention to maintaining access for maintenance and adhering to existing building constraints. The project appears to be funded by the City of Oklahoma City and the Myriad Gardens Foundation, with the work to be performed by a mechanical contractor selected through the bidding process.

View the file

Other files

File Type Posted
MB-1791 Bidding Documents.pdf PDF
Anti Noncollusion Affidavit.pdf PDF
Business Relationship Affidavit.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

!F

I

RJ, I I'>' I

t==

- I I /J ai;::;,7__

- I i llv, oa f'i-- If=' r------ I - /J ''"'- "'J IIn

I 1--, ,, ,Y' I - V ...._

I '" !l.,,J; -- I 'JY wµ,o ;:/' I ··-" I..J'v) ll,-K I [<, 7 I,.-{.n N

I\ ..

1/, '" il--,,, 7:~·n r.2, ')I I/ I

- tr 'ff '--, I'.. I'-.

I'.:! h -v I L- I , f.t I J . - - /1 -

1:1{.,,_ r--- - r � I -- ·+,1 � � i'-rr I,... 1--r' ,J

/_V s ..______ ,___ .. £ -- w,itt, / ff:

PROJECT Thf' City nf lOC ... IION 1n-1 .. 1u,111;, f'il.1

'\ l':l ., x,� I/ .

�--J :.,,--I \ + 11�r--.. I -------

WA 03

1,,-' r----.. I I"--.-

,. 1Rs j I=

FFII,.

-- :-,._ L �� - C---

I I I I l

I .___I-

( I J WARD◄ I -

J l r'r - -,_ �L � I ...._ i

I ---•� � ';>'!,-:.f I - I

I � h �'7 �u - I

I _j

MB-1791

MYRIAD GARDENS CHILLED

WATER INSTALLATION

Arc

ADG B

920W .

Oklahoma Cit 405.232.

301 W RENO AVE

OKLAHOMA CITY, OK 73102

AUGUST 4, 2025

ISSUED FOR BID

Owner

MYRIAD GARDENS FOUNDATION

301 W RENO AVENUE

OKLAHOMA CITY. OK 73102

405.445.7080

MEP

OLSSON

11600 BROADWAY EXTENSION. SUITE 300

OKLAHOMA CITY. OK 73114

405.242.6600

The City of

OKLAHOMA CITY

Public Works Department

DAVID HOLT

COUNCIL MEMBERS

BRADLEY CARTER

JAMES COOPER

Katrina Avers

TODD STONE

MATT HINKLE

JOBETH HAMON

Camal Pennington

MARK K. STONECIPHER

CRAIG FREEMAN

DEBBIE MILLER, P.E.

SHEET INDEX

Mayor

Ward1 Ward2 Ward3 Ward4 Ward5 Ward6 Ward7 Ward8

City Manager

Director Public Works/City Engineer

ONE CALL UTILITY LOCATION NUMBER

840-5032

1-800-522-6543

PREPARED BY

Anlhony J. Blatt

This number is to be uwd fQr information on the location of all uOOerground ublitiu. Contact this number and other number$ $peeifi•d in the plaM prior to any excavation.

REGISTERED PROFESSIONAL ARCHITECT

NO 3765

RECOMMENDED FOR APPROVAL

� INEER A_ DA�/�u

APPROVED AS FINAL PLANS

MAYOR DATE

DATE

CTNO.

i�========================�========================================================================�============================�

28'

31.1

CCDDEE

PROVIDE 48"WX72"H STEEL SCREENS

ON STEEL POSTS EMBEDDED IN 24"

DIAMETER BY 36" DEEP CONCRETE

FOOTING PER MANUFACTUERE

INSTRUCTIONS. BASIS OF DESIGN OF

METAL PANEL SHALL BE A 'REVAMP

PANEL' - PATTERN "POPPY FIELD",

COLOR TBD. COORDINATE EXACT

LOCATION WITH ARCHITECT PRIOR

TO INSTALLATION

CHILLED WATER LINES TO PENETRATE

EXISTING ACRYLITE ACRYILIC MULTI-SKIN

PANEL. CUT PANEL PER MANUFACTURER

INSTRUCTIONS. PROVIDE OPENING 3/4"

LARGER THAN PENETRATING PIPES.

PROVIDE 1/2" WIDE ALUMINUM CHANNEL

SIMILAR TO EXISTING ALUMINUM

CHANNELS TO WRAP CIRCULAR OPENING

AND ATTACH PER PANEL MANUFACTURER

INSTRUCTIONS. SEAL ALUMINUM

CHANNEL TO PIPE WITH COMMERCIAL

GRADE NON-SAG SILCONE SEALANT.

A .1

CHILLED WATER LINES TO PENETRATE EXISTING ACRYLITE

ACRYILIC MULTI-SKIN PANEL. CUT PANEL PER

MANUFACTURER INSTRUCTIONS. PROVIDE OPENING 3/4"

LARGER THAN PENETRATING PIPES. PROVIDE 1/2" WIDE

ALUMINUM CHANNEL SIMILAR TO EXISTING ALUMINUM

CHANNELS TO WRAP CIRCULAR OPENING AND ATTACH PER

PANEL MANUFACTURER INSTRUCTIONS. SEAL ALUMINUM

CHANNEL TO PIPE WITH COMMERCIAL GRADE NON-SAG

SILCONE SEALANT.

PROVIDE 48"WX72"H STEEL SCREENS ON

STEEL POSTS EMBEDDED IN 24" DIAMETER BY

36" DEEP CONCRETE FOOTING PER

MANUFACTUERE INSTRUCTIONS. BASIS OF

DESIGN OF METAL PANEL SHALL BE A

'REVAMP PANEL' - PATTERN "POPPY FIELD",

COLOR TBD. COORDINATE EXACT

LOCATION WITH ARCHITECT PRIOR TO

INSTALLATION

4' - 0"

C

ONST RUCT ION

CON

STR

U C

T I O

N

REV

IEW

S E T

THIS

DOCUMENT IS

PRELIMINARY IN

NATURE AND IS NOT

A FINAL, SIGNED

AND SEALED

DOCUMENT

N O

T

FO

R

NOT FOR

SE T

R E

V

IE

W

Date:

ADGB Project:

Sheet No.

Revisions:

C o p y ri g h t

A D

G B

LA

TT

P

C

920 W. Main St.

Oklahoma City, OK 73106

Phone-Edmond: 405.340.8552

Web: www.adgblatt.com

101 S. Broadway, Suite 200

Edmond, OK 73034

Phone-OKC: 405.232.5700

/4

/2

:0

:3

A M

A2.1

PARTIAL FIRST

FLOOR PLAN &

NORTH ELEVATION

23-113

08/04/2025

M B

-1

M Y

R

IA

D G

A R

D E N

S C

H

IL

LE

D

W A

TE

R

I N

S

TA

LL

A

TI

O

N

301 W. Reno Ave, Oklahoma City, OK 73102

IS

S U

E D

F O

R B

ID

NORTH

1/4" = 1'-0"

PARTIAL FIRST FLOOR PLAN

1/4" = 1'-0"

NORTH ELEVATION

ACCESS

KW

V

SD

KITCHEN WASTE

VENT

SOIL OR WASTE

STORM DRAIN

DOMESTIC COLD WATER

DOMESTIC HOT WATER (120°F)

140°F

DOMESTIC HOT WATER RETURN

DOMESTIC HOT WATER (140°F)

CD

RL

RS

CONDENSATE DRAIN

REFRIGERANT LIQUID

REFRIGERANT SUCTION (GAS)

RISER UP (ELBOW)

RISER DOWN (ELBOW)

TEE UP

TEE DOWN

TOP CONNECTION

SIDE CONNECTION

GATE VALVE

BALL VALVE

BOTTOM CONNECTION

CHECK VALVE

BUTTERFLY VALVE

GLOBE VALVE

PRESSURE REDUCING VALVE

CONTROL VALVE, 2 WAY

PLUG VALVE

RISE OR DROP

SS

CONTROL VALVE, 3 WAY

WCO

FCO

FPHB

CLEANOUT, FLOOR

STRAINER, "Y" TYPE

CLEANOUT, WALL

REDUCER, ECCENTRIC

BACKFLOW PREVENTION DEVICE

REDUCER, CONCENTRIC

CAP

FPWH

FD

RD

SD

FREEZE PROOF WALL HYDRANT

FLOW IN DIRECTION OF ARROW

FLOOR DRAIN

ROOF DRAIN

SHOWER DRAIN

SLOPE PIPE, RISE (R) DROP (D)

FREEZE PROOF HOSE BIBB, OR

FIRE DEPARTMENT CONNECTION

DHWR

DHW

DCW

OSD OVERFLOW STORM DRAIN

HWS HEATING WATER SUPPLY

HWR HEATING WATER RETURN

G NATURAL GAS

CHWS CHILLED WATER SUPPLY

CHWR CHILLED WATER RETURN

CWS CONDENSER WATER SUPPLY

CWR CONDENSER WATER RETURN

ORD OVERFLOW ROOF DRAIN

REFER TO ASHRAE FUNDAMENTALS CHAPTER 37 FOR ADDITIONAL ABBREVIATIONS USED.

ADJ ADJUSTABLE

AFF ABOVE FINISHED FLOOR

AI ANALOG INPUT

ALT ALTERNATE

AO ANALOG OUTPUT

APD AIR PRESSURE DROP

ARCH ARCHITECT

ATC AUTOMATIC TEMPERATURE CONTROL

BAS BUILDING AUTOMATION SYSTEM

BI BINARY INPUT

BLDG BUILDING

BMS BUILDING MANAGEMENT SYSTEM

BO BINARY OUTPUT

BOD BOTTOM OF DUCT

BOI BOTTOM OF INSULATION

BOP BOTTOM OF PIPE

CF CUBIC FEET

CFM CUBIC FEET PER MINUTE

CFCI CONTRACTOR FURNISHED, CONTRACTOR INSTALLED

CI CAST IRON

CL CENTER LINE

CLG CEILING

CORR CORRIDOR

CTRL CONTROL

CU COPPER

CUP CENTRAL UTILITY PLANT

DCV DEMAND CONTROL VENTILATION

DDC DIRECT DIGITAL CONTROL

DEG (°) DEGREE

DEMO DEMOLITION / DEMOLISH

DI DIGITAL INPUT

DIA OR Ø DIAMETER

DIV DIVISION

DN DOWN

DO DIGITAL OUTPUT

DP DEW POINT TEMPERATURE

DTL DETAIL

DWG DRAWING

DWV DRAIN, WASTE, AND VENT

EA EXHAUST AIR

EAT ENTERING AIR TEMPERATURE

ECON ECONOMIZER

EFF EFFICIENCY

ELEC ELECTRIC

ELEV ELEVATION

EMCS ENERGY MANAGEMENT AND CONTROL SYSTEM

EMS ENERGY MANAGEMENT SYSTEM

ESP EXTERNAL STATIC PRESSURE

EST ESTIMATE

EWT ENTERING WATER TEMPERATURE

FC FAIL CLOSED

FFA FROM FLOOR ABOVE

FFB FROM FLOOR BELOW

FIP FAIL IN PLACE

FLA FULL LOAD AMPS

FLR FLOOR

FO FAIL OPEN

FPM FEET PER MINUTE

FPS FEET PER SECOND

GAL GALLON

GPH GALLONS PER HOUR

GPM GALLONS PER MINUTE

HP HORSEPOWER

HR HOUR

HT HIGH (HEIGHT)

HTG HEATING

HVAC HEATING, VENTILATING, AND AIR-CONDITIONING

HW HOT WATER

I/O INPUT / OUTPUT

ISO ISOMETRIC

KW KILOWATT

KWH KILOWATT HOUR

LAT LEAVING AIR TEMPERATURE

LBS POUNDS

LF LINEAR FEET (FOOT)

LWT LEAVING WATER TEMPERATURE

MAINT MAINTENANCE

MAU MAKE-UP AIR UNIT

MAX MAXIMUM

MBH THOUSAND BTU PER HOUR

MCA MINIMUM CIRCUIT AMPACITY

MECH MECHANICAL

MFG MANUFACTURING

MFR MANUFACTURER

MIN MINIMUM

MOCP MAXIMUM OVER CURRENT PROTECTION

MTG MOUNTING

N/A NOT APPLICABLE

NC NOISE CRITERIA / NORMALLY CLOSED

NEG NEGATIVE

NG NATURAL GAS

NO NUMBER / NORMALLY OPEN

NPSH NET POSITIVE SUCTION HEAD

NPSHA NET POSITIVE SUCTION HEAD AVAILABLE

NPSHR NET POSITIVE SUCTION HEAD REQUIRED

NTS NOT TO SCALE

OA OUTSIDE AIR

OC ON CENTER

OFCI OWNER FURNISHED, CONTRACTOR INSTALLED

PH OR Φ PHASE

POS POSITIVE

PSI POUNDS PER SQUARE INCH

PSIA PSI ABSOLUTE

PSIG PSI GAUGE

QTY QUANTITY

RA RETURN AIR

RF RELIEF AIR

REF REFERENCE

REQ'D REQUIRED

RS REFRIGERANT SUCTION (GAS)

RL REFRIGERANT LIQUID

RPM REVOLUTIONS PER MINUTE

SA SUPPLY AIR

SAT SUPPLY AIR TEMPERATURE

SF SQUARE FEET

SP STATIC PRESSURE

SPEC SPECIFICATION

SS STAINLESS STEEL

STD STANDARD

STRU STRUCTURAL

TDH TOTAL DYNAMIC HEAD

TEMP TEMPERATURE

TFA TO FLOOR ABOVE

TFB TO FLOOR BELOW

TFD TO FLOOR DRAIN

THRU THROUGH

TOA TEMPERED OUTDOOR AIR

TSTAT THERMOSTAT

TSP TOTAL STATIC PRESSURE

TYP TYPICAL

UNO UNLESS NOTED OTHERWISE

VAV VARIABLE AIR VOLUME

VTR VENT THROUGH ROOF

W/ WITH

W/O WITHOUT

WB WET BULB TEMPERATURE

W.C. WATER COLUMN

ABBREVIATIONS

(5) A/200

GRILLES, REGISTERS, & DIFFUSERS:

SYSTEMS ABBREVIATIONS

SYMBOL DESCRIPTION

S(#) STEAM - (#) PSI

LPC LP STEAM CONDENSATE (<=15 PSIG)

HPC HP STEAM CONDENSATE (>15 PSIG)

FOS FUEL OIL SUPPLY

FOR FUEL OIL RETURN

PC PUMPED STEAM CONDENSATE

BLIND FLANGE

FLANGE JOINT

UNION (THREADED)

PIPING AND FLOW DIAGRAM SYMBOLS

SYMBOL DESCRIPTION

THERMOMETER, INDUSTRIAL STYLE

P PRESSURE GAUGE AND VALVE

PUMP SUCTION DIFFUSER

PUMP

AIR / DIRT SEPARATOR

SAFETY RELIEF VALVE

CALIBRATED MANUAL BALANCING VALVE

WITH INTEGRAL TEST PORTS

AUTOMATIC FLOW LIMITING VALVEA

AUTOMATIC AIR VENT

MANUAL AIR VENTMAV

FDC

R

STEAM TRAP

EXTENT OF DEMOLITION

DEMOLISH BEYOND

CONNECT TO EXISTING

RENOVATION SYMBOLS

SYMBOL DESCRIPTION

DUCT / EQUIPMENT / PIPING TO BE REMOVED

NEW DUCT / EQUIPMENT / PIPING TO BE

PROVIDED

EXISTING TO REMAIN

CONTROL DEVICE SYMBOLS FOR FLOORPLANS

SYMBOL DESCRIPTION

WALL MOUNTED DEVICES:

C = CONTROLLER

CO2 = CARBON DIOXIDE TRANSMITTER

CO = CARBON MONOXIDE TRANSMITTER

EPB = EMERGENCY PUSH BUTTON SWITCH

HS = ZONE HUMIDITY SENSOR

H = ZONE HUMIDISTAT

OCC = OCCUPANCY SENSOR

REF = ZONE REFRIGERANT SENSOR

RPM = ROOM PRESSURE MONITOR

TS = ZONE TEMPERATURE SENSOR

T = ZONE THERMOSTAT

DUCT / EQUIP. / PIPE MOUNTED DEVICES:

AFMS = AIRFLOW MEASUREMENT STATION

FM = FLOW METER

SPT = DUCT STATIC PRESSURE

TRANSMITTER

HVAC SYMBOLS

SYMBOL DESCRIPTION

SUPPLY AIR

RETURN AIR

EXHAUST AIR

RECTANGULAR DUCT12"/12"

12"Ø ROUND DUCT

FLAT OVAL DUCT24"X12"Ø

BREAK LINE (CONTINUATION)

DAMPER TYPES:

(NO LABEL) = MANUAL BALANCING

DAMPER

FD = FIRE DAMPER

SD = SMOKE DAMPER

FSD = COMBINATION FIRE/SMOKE DAMPER

CD = MOTORIZED CONTROL DAMPER

BD = BACKDRAFT DAMPER

ALL DAMPERS EXCEPT MANUAL

BALANCING DAMPER SHALL HAVE

ADJACENT ACCESS PANEL FOR

MAINTENANCE.

90 DEGREE ROUND RADIUS ELBOW,

STAMPED, HORIZONTAL

90 DEGREE RECTANGULAR MITERED

ELBOW W/ TURNING VANES UP

90 DEGREE ROUND / FLAT OVAL ELBOW

DOWN

90 DEGREE ROUND / FLAT OVAL RADIUS

ELBOW, 5 GORE, HORIZONTAL

90 DEGREE RECTANGULAR RADIUS ELBOW

UP

45 DEGREE ROUND / FLAT OVAL RADIUS

ELBOW, 3 GORE, HORIZONTAL

90 DEGREE ROUND / FLAT OVAL ELBOW UP

90 DEGREE RECTANGULAR MITERED

ELBOW W/ TURNING VANES, HORIZONTAL

PROVIDE ACCESS PANEL UPSTREAM OF

TURNING VANES FOR MAINTENACE.

LO LOSS TEE (SHOE SADDLE TAP)

Ø

HIGH EFFICIENCY TAKE-OFF (HETO)

Ø

BEVELED TAP

45° LATERAL SADDLE TAP

Ø

FLEX DUCT

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

16.

17.

18.

19.

20.

21.

22.

23.

24.

25.

26.

27.

28.

29.

30.

31.

32.

33.

34.

35.

36.

37.

PROVIDE ALL MATERIALS AND EQUIPMENT AND PERFORM ALL LABOR REQUIRED TO

INSTALL COMPLETE AND OPERABLE MECHANICAL SYSTEMS AS INDICATED ON THE

DRAWINGS, AND AS SPECIFIED AND REQUIRED BY CODE.

CONTRACT DOCUMENT DRAWINGS ARE DIAGRAMMATIC AND ARE INTENDED TO

CONVEY SCOPE AND GENERAL ARRANGEMENT ONLY. DRAWINGS DO NOT SHOW ALL

MINOR ITEMS THAT MUST BE INSTALLED.

THE LOCATIONS OF ALL ITEMS SHOWN ON THE DRAWINGS OR CALLED FOR IN THE

SPECIFICATIONS THAT ARE NOT DEFINITELY FIXED BY DIMENSIONS ARE

APPROXIMATE ONLY. THE EXACT LOCATIONS NECESSARY TO SECURE THE BEST

CONDITIONS AND RESULTS MUST BE DETERMINED BY THE PROJECT SITE

CONDITIONS AND SHALL HAVE THE APPROVAL OF THE ENGINEER BEFORE BEING

INSTALLED.

ALL REQUIRED OFFSETS FOR DUCT AND PIPING ARE NOT SHOWN ON THE

DRAWINGS. REQUIRED OFFSETS SHALL BE DETERMINED BY CONTRACTOR DURING

THE SHOP DRAWING STAGE AND SHALL NOT BE AN ADDITIONAL COST TO THE

OWNER.

PLAN AND SECTION DRAWINGS DO NOT SHOW ALL REQUIRED BRANCH PIPING OR

VALVES AND ACCESSORIES. REFER TO FLOW DIAGRAMS, DETAILS, AND PROJECT

SPECIFICATIONS FOR REQUIRED PIPING, VALVES, AND ACCESSORIES.

SHOP DRAWINGS SHALL BE SUBMITTED TO ENGINEER FOR REVIEW FOR ALL

DUCTWORK, PIPING, CONTROLS, ETC. PRIOR TO ANY WORK STARTING.

ALL DEMOLISHED MATERIALS SHALL BE OFFERED TO THE OWNER FOR FIRST RIGHT

OF REFUSAL IN ACCORDANCE WITH THE PROJECT SPECIFICATIONS. ANY MATERIAL

NOT SELECTED BY THE OWNER SHALL BE REMOVED FROM THE PROPERTY AND

DISPOSED OF IN ACCORDANCE WITH LOCAL LAWS AND REGULATIONS.

INSTALL ALL MECHANICAL EQUIPMENT AND APPURTENANCES IN ACCCORDANCE

WITH MANUFACTURERS RECOMMENDATIONS, CONTRACT DOCUMENTS, AND

APPLICABLE CODES AND REGULATIONS.

PROVIDE VIBRATION ISOLATION AND FLEXIBLE CONNECTIONS FOR ALL MECHANICAL

EQUIPMENT TO PREVENT TRANSMISSION OF VIBRATION TO BUILDING STRUCTURE

AND ASSOCIATED DUCT / PIPING SYSTEMS.

COORDINATE CONSTRUCTION OF ALL MECHANICAL WORK WITH OTHER DISCIPLINES

SHOWN ON OTHER CONTRACT DOCUMENT DRAWINGS.

COORDINATE WITH GENERAL CONTRACTOR TO PROVIDE ACCESS PANELS FOR

INSTALLATION IN WALLS AND CEILINGS, WHERE REQUIRED, TO PERMIT SERVICE

ACCESS FOR DAMPERS, VALVES, SMOKE DETECTORS, TURNING VANES, AND OTHER

CONCEALED MECHANICAL EQUIPMENT. ACCESS PANELS SHALL BE TURNED OVER TO

THE GENERAL CONTRACTOR FOR INSTALLATION. NOTIFY ENGINEER FOR ADDITIONAL

ACCESS PANELS NOT SHOWN ON PLANS FOR APPORVAL PRIOR TO INSTALLATION.

ALL DUCT SIZES INDICATED REPRESENT INSIDE CLEAR DIMENSIONS. CONTRACTOR

SHALL ADJUST SHEET METAL SIZE TO ACCOUNT FOR LINER THICKNESS WHEN LINER

IS REQUIRED PER THE CONTRACT DOCUMENTS.

MODIFY ROUTING OF DUCTING AND PIPING AT EQUIPMENT CONNECTION POINTS

FROM THAT SHOWN TO MATCH ACTUAL LOCATION OF CONNECTION POINTS FOR

SPECIFIC EQUIPMENT PURCHASED.

PIPING, DUCTWORK, AND EQUIPMENT HANGERS AND SUPPORTS SHALL NOT

INTERFERE WITH OPERATION AND MAINTENANCE OF EQUIPMENT.

PROVIDE HINGED ACCESS DOORS IN DUCTWORK TO PROVIDE ACCESS FOR ALL

SMOKE DETECTORS, FIRE DAMPERS, SMOKE DAMPERS, BACKDRAFT DAMPERS,

COILS, UPSTREAM OF TURNING VANES, AND OTHER ITEMS LOCATED IN THE

DUCTWORK THAT REQUIRE SERVICE AND / OR INSPECTION. MINIMUM ACCESS

PANEL SIZES SHALL BE 6"x6" FOR DUCT DIMENSIONS 12 INCH AND LESS, 12"x12" FOR DUCT DIMENSIONS 14 INCH - 24 INCH, AND 18"x18" FOR DUCT DIMENSIONS GREATER

THAN 26 INCH.

LOCATE ALL MECHANICAL EQUIPMENT FOR UNOBSTRUCTED ACCESS TO UNIT

ACCESS PANELS, CONTROLS, AND VALVING.

RUNS OF FLEXIBLE DUCTWORK SHALL BE LIMITED TO 3 FT IN LENGTH AND SHALL BE

LIMITED TO GRILLES, REGISTER, AND DIFFUSER CONNECTIONS TO ASSOCIATED

BRANCH DUCTS.

ALL 90° MITERED ELBOWS SHALL BE PROVIDED WITH TURNING VANES. TURNING

VANES SHALL BE DOUBLE WALL.

UNLESS NOTED OTHERWISE, LOCATE ALL ROOM THERMOSTATS AND OTHER WALL

MOUNTED CONTROL DEVICES 4'-0" AFF. NOTIFY THE ENGINEER OF ANY ROOMS

WHERE THE SPECIFIED LOCATION CANNOT BE MAINTAINED OR WHERE THERE IS A

QUESTION ON LOCATION.

LOCATE ALL TEMPERATURE, PRESSURE, AND FLOW MEASURING DEVICES IN

ACCESSIBLE LOCATIONS WITH THE STRAIGHT SECTION OF DUCT / PIPE UP-AND-

DOWNSTREAM OF DEVICE AS RECOMMENDED BY MANUFACTURER. NOTIFY

ENGINEER OF ANY DEVICES WHOSE PROPOSED LOCATION DOES NOT MEET THE

MANUFACTURERS MINIMUM REQUIREMENTS.

INSTALL PIPING SO ALL VALVES, PIPING SPECIALTIES, AND OTHER APPURTENANCES

REQUIRING ACCESS ARE ACCESSIBLE.

ALL SERVICE ISOLATION VALVES SHALL BE SUITABLE FOR DEAD END SERVICE AND

INSTALLED SUCH THAT THE VALVE WILL REMAIN IN SERVICE WHEN EQUIPMENT

PIPING IS BEING EVACUATED OR REMOVED.

ALL HYDRONIC EQUIPMENT SHALL BE PROVIDED WITH TEST PORTS FOR TESTING,

ADJUSTING, AND BALANCING.

GENERAL CONTRACTOR SHALL COORDINATE ALL TRADES TO ENSURE ALL

MATERIALS INSTALLED WITHIN A RETURN AIR PLENUM ARE PLENUM RATED.

ALL GRILLES, REGISTERS, AND DIFFUSER LOCATIONS SHALL BE COORDINATED WITH

ARCHITECTS REFLECTED CEILING PLAN.

FRESH AIR INTAKES SHALL BE A MINIMUM OF 10 FT AWAY FROM CONTAMINATION

SOURCES. THIS INCLUDES PLUMBING VENTS, EXHAUST FANS, AND COOLING TOWER

PLUMES.

ALL CONTROL WIRE AND CONDUIT SHALL COMPLY WITH THE NATIONAL ELECTRIC

CODE AND DIVISION 26 SPECIFICATION.

CONTRACTOR SHALL VERIFY DEPTH, SIZE, LOCATION OF ALL EXISTING UTILITIES IN

FIELD BEFORE STARTING WORK.

SOIL AND WASTE PIPE SHALL SLOPE 2% (1/4 INCH PER FT) MINIMUM, UNLESS NOTED

OTHERWISE. CONDENSATE DRAIN AND STORM DRAIN PIPING SHALL SLOPE 1% (1/8

INCH PER FT) MINIMUM, UNLESS NOTED OTHERWISE.

ALL EQUIPMENT LOCATED IN MECHANICAL ROOMS SHALL BE PROVIDED WITH A 4

INCH THICK HOUSEKEEPING PAD. PAD SHALL EXTEND MINIMUM OF 6 INCHES BEYOND

EDGES OF EQUIPMENT.

ALL BRANCH DUCTS TO GRILLES AND DIFFUSERS SHALL BE PROVIDED WITH MANUAL

BALANCING DAMPERS. WHERE DUCT IS EXTERNALLY INSULATED, THE DAMPER

SHALL BE PROVIDED WITH A HANDLE EXTENSION TO CLEAR THE INSULATION.

ALL RATED WALL, FLOOR, PARTITION, CEILING, AND SHAFT DUCT PENETRATIONS

SHALL BE PROVIDED WITH AN APPROPRIATE LIFE SAFETY DAMPER TO MAINTAIN THE

RATING OF THE ASSEMBLY IN ACCORDANCE WITH LOCAL CODES AND REGULATIONS.

COORDINATE WITH ARCHITECTURAL PLANS FOR LOCATIONS OF RATED WALL'S AND

WALL CONSTRUCTION.

ALL DOMESTIC HOT WATER RETURN BRANCHES SHALL EXTEND TO FIXTURE.

CONNECTIONS IN EXCESS OF 12 INCHES FROM THE FAUCET CONNECTION WILL NOT

BE ALLOWED.

ALL PIPING BELOW AMBIENT TEMPERATURE SHALL BE PROVIDED WITH INSULATION

TO PREVENT CONDENSATION. INSULATION SHALL BE 1/2 INCH THICK MINIMUM OR AS

INDICATED IN SPECIFICATIONS.

ALL PIPING PENETRATIONS OF FINISHED SURFACES SHALL BE PROVIDED WITH AN

ESCUTCHEON FOR CLEAN APPEARANCE.

ROOF MOUNTED EQUIPMENT WITHIN 10 FT OF ROOF EDGES SHALL BE PROVIDED

WITH A GUARD RAIL AT THE ROOF EDGE IN ACCORDANCE WITH IBC.

ALL UNDERFLOOR WORK SHALL BE COORDINATED WITH FOUNDATION, FOOTINGS,

GRADE BEAMS, ETC. REFER TO STRUCTURAL PLANS. UNDERFLOOR PIPING SHALL

NOT PENETRATE STRUCTURAL MEMBERS WITHOUT APPROVAL FROM THE

STRUCTURAL ENGINEER.

GENERAL PROJECT NOTES

AC AIR COMPRESSOR

ADS COMBINATION AIR / DIRT SEPARATOR

AFMS AIRFLOW MEASURING STATION

AHU AIR HANDLING UNIT

AS AIR SEPARATOR

AST ABOVEGROUND STORAGE TANK

BLR BOILER

BBH BASEBOARD HEATER

BCU BLOWER COIL UNIT

BDD BACKDRAFT DAMPER

BT BUFFER TANK

CAV CONSTANT VOLUME TERMINAL UNIT

CC COOLING COIL

CD CONTROL DAMPER

CDP CONDENSATE PUMP

CH CHILLER

CHWP CHILLED WATER PUMP

CP CIRCULATING PUMP

CR STEAM CONDENSATE RECEIVER

CRAC COMPUTER ROOM AIR-CONDITIONING UNIT

CT COOLING TOWER

CV CONTROL VALVE

CWP CONDENSER WATER PUMP

DAT DEAREATOR TANK

DCV DOUBLE CHECK VALVE

DHWP DOMESTIC HOT WATER LOOP PUMP

DN DOWNSPOUT NOZZLE (LAMB'S TONGUE)

DOAS DEDICATED OUTDOOR AIR UNIT

DT FUEL OIL DAY TANK

DWH DOMESTIC WATER HEATER

EAV EXHAUST AIR VENTURI VALVE

EF EXHAUST FAN

ERV ENERGY RECOVERY VENTILATOR

EWC ELECTRIC WATER COOLER

FCU FAN COIL UNIT

FCO FLOOR CLEAN OUT

FD FIRE DAMPER OR FLOOR DRAIN

FF FILTER FEEDER

FM FLOW METER

FPVAV FAN POWERED VAV TERMINAL UNIT

FS FLOOR SINK

FSD COMBINATION FIRE/SMOKE DAMPER

FT FLASH TANK

FWD FOOD WASTE DISPOSAL (GARBAGE DISPOSAL)

FWP BOILER FEED WATER PUMP

GEN GENERATOR

GI GREASE INTERCEPTOR

GMU GLYCOL MAKE-UP UNIT

GSHP GROUND SOURCE HEAT PUMP

GV GRAVITY VENTILATOR

HB HOSE BIBB

HC HEATING COIL

HT HEAT TRACE

HWP HEATING WATER PUMP

HX HEAT EXCHANGER

IDU SPLIT SYSTEM INDOOR UNIT

KS KITCHEN SINK (MULTI COMPARTMENT SINK)

LAV LAVATORY

LV LOUVER

MAV MAKE-UP AIR VENTURI VALVE

MAU MAKE-UP AIR UNIT

MS MOP SINK

PCHP PRIMARY CHILLED WATER PUMP

PRV PRESSURE REDUCING (REGULATING) VALVE

ODU SPLIT SYSTEM OUTDOOR UNIT

ORD OVERFLOW ROOF DRAIN

RAF RETURN AIR FAN

RD ROOF DRAIN

REG GAS REGULATOR

RF RELIEF FAN

RH ROOF HYDRANT

RO RO WATER TREATMENT SYSTEM

RPZ RPZ BACKFLOW PREVENTER

RRU REFRIGERANT RECOVERY UNIT

RTU PACKAGED ROOFTOP UNIT

S SINK

SCHP SECONDARY CHILLED WATER PUMP

SCP STEAM CONDENSATE PUMP

SD SMOKE DAMPER OR SHOWER DRAIN

SEP SEWAGE EJECTOR PUMP

SF SUPPLY FAN

SI SOLIDS INTERCEPTOR

SP SUMP PUMP

SRV SAFETY RELIEF VALVE

ST STEAM TRAP

SUT SURGE TANK

TCHP TERTIARY CHILLED WATER PUMP

TD TRENCH DRAIN

TMV THERMOSTATIC MIXING VALVE

TP TRAP PRIMER

U URINAL

UH UNIT HEATER

US UTILITY SINK

UST UNDERGROUND STORAGE TANK

VAV VARIABLE VOLUME TERMINAL UNIT

VFD VARIABLE FREQUENCY DRIVE

WC WATER CLOSET

WCO WALL CLEAN OUT

WF WATER FILTRATION SYSTEM

WH WALL HYDRANT

WM WATER METER

WS WATER SOFTENER SYSTEM

WSB WATER SUPPLY BOX

WSHP WATER SOURCE HEAT PUMP

XFRP TRANSFER PUMP

XT EXPANSION TANK

EQUIPMENT DESIGNATIONS

NPW NON-POTABLE WATER

CF CHEMICAL FEED

BD BLOWDOWN

CBD CONTINOUS BLOWDOWN

CA COMPRESSED AIR

N

O

NITROGEN

MEDICAL AIR

OXYGEN

A

WAGD WASTE ANESTHESIA GAS DISPOSAL

MEDICAL GAS ABBREVIATIONS

SYMBOL DESCRIPTION

VAC MEDICAL VACUUM

M-301

AIR FLOW (CFM)

DEVICE TAG. REF TO SCHEDULE.

MECHANICAL CALLOUTS

SECTION / DETAIL:

DTL NO.

SHEET NO. WHERE DETAIL

OR SECTION IS DRAWN

KEYNOTES:

1 KEYNOTE NO.

QTY.

SW SOFTENED WATER

RO RO WATER

DI DI WATER

FW BOILER FEED WATER

DUCT SIZE:

ALL DIMENSIONS ARE IN INCHES

UNLESS NOTED OTHERWISE

90 DEGREE RECTANGULAR MITERED

ELBOW W/ TURNING VANES DOWN

90 DEGREE RECTANGULAR RADIUS ELBOW

DOWN

FIRE SPRINKLERF

EXPANSION TANK

COPYRIGHT 2025 OLSSON ALL RIGHTS RESERVED.

THIS DRAWING IS PROPERTY OF OLSSON. ANY MODIFICATION OR USE OF THIS DRAWING

WITHOUT EXPRESS WRITTEN AUTHORIZATION OF OLSSON IS PROHIBITED.

DC# 24155 / OLSSON# 025-00948SHEET SIZE: 30X42

OK COA #: 2483 EXPIRES 2027-06-30

Date:

ADGB Project:

Sheet No.

Revisions:

C op yr ig ht A

D G

B

LA

TT

, P

C

920 W. Main St.

Oklahoma City, OK 73106

Phone-Edmond: 405.340.8552 Web: www.adgblatt.com

101 S. Broadway, Suite 200 Edmond, OK 73034 Phone-OKC: 405.232.5700

8/ 4/

:2

7:

P M

M-001

MECHANICAL

LEGEND,

ABBREVIATIONS,

AND NOTES

23-113

AUGUST 04, 2025

M B-

M

YR

IA

D

G A

RD

EN

S C

HI

LL

ED

W

A

TE

R

IN

ST

A

LL

A

TIO

N

301 W. Reno Ave, Oklahoma City, OK 73102

IS

SU

ED

F

O R

BI

D

08/04/2025

SUMMARY OF MECHANICAL WORK:

1.

A.

2.

A.

3.

A.

4.

A.

5.

A.

B.

6.

A.

7.

A.

8.

A.

B.

A.

B.

C.

D.

E.

A.

B.

A.

SUMMARY OF WORK

THE WORK COVERED BY THESE DOCUMENTS CONSISTS OF FURNISHING ALL LABOR, MATERIAL AND EQUIPMENT IN PERFORMING ALL OPERATIONS NECESSARY FOR THE INSTALLATION OF THE MECHANICAL SYSTEMS DESIGNATED ON THE DRAWINGS AND/OR DESCRIBED HEREIN. ANY INCIDENTAL WORK NOT SHOWN OR SPECIFIED, BUT WHICH CAN BE PRESUMED AS BELONGING TO, OR DEEMED NECESSARY FOR, THE SATISFACTORY COMPLETION OF THE VARIOUS SYSTEMS, SHALL BE INCLUDED. THE WORK SHALL BE COORDINATED WITH THE REQUIREMENTS OF THE SPECIFICATIONS (WHERE APPLICABLE) AND WITH ALL OF THE DRAWINGS FOR THE ENTIRE PROJECT. THE WORK SHALL BE ACCOMPLISHED ON SUCH A SCHEDULE AND IN SUCH A MANNER AS NOT TO DELAY OR

INTERFERE WITH OTHER CONSTRUCTION.

VISITING THE SITE

THE CONTRACTOR SHALL VISIT THE SITE TO FAMILIARIZE HIMSELF WITH THE CONDITIONS TO BE MET, AS NO EXTRAS WILL BE ALLOWED TO COVER WORK WHICH THE CONTRACTOR DID NOT INCLUDE IN HIS BID DUE TO HIS FAILURE TO INFORM HIMSELF OF THE

CONDITION AT THE SITE.

DRAWINGS

THE DRAWINGS AND SPECIFICATIONS COVER THE EXTENT AND GENERAL ARRANGEMENT OF THE VARIOUS SYSTEMS, SUBJECT TO THE INDIVIDUAL CHARACTERISTICS OF THE MECHANICAL EQUIPMENT WITH REGARD TO SIZE, INTERNAL ARRANGEMENT, CONNECTIONS, ETC. THE EXACT LOCATION AND INSTALLATION OF THE METERS FOR UTILITIES SHALL CONFORM TO THE APPLICABLE REQUIREMENTS OF THE LOCAL UTILITIES. THE MECHANICAL DRAWINGS ARE DIAGRAMMATICAL ONLY AND ARE NOT INTENDED TO INCLUDE ALL OF THE DETAILS OR DIMENSIONS SHOWN ON THE OTHER DIVISIONS OF THIS PROJECT, AND CONVERSELY THE SAME.

HOWEVER, EACH DRAWING IS INTENDED TO SUPPLEMENT THE OTHERS AND INTERPRETATION OF THE DRAWINGS SHALL BE SUCH THAT THE ARCHITECTURAL, STRUCTURAL, MECHANICAL AND ELECTRICAL DETAILS ARE INCLUDED ON ALL OF THE VARIOUS DRAWINGS. WHERE NO FIGURES OR DIMENSIONS ARE NOTED, THE DRAWINGS SHALL BE ACCURATELY FOLLOWED. EXCEPTIONS TO, OR CONFLICTS BETWEEN, THE DRAWINGS, SPECIFICATIONS, AND OR INTERPRETATION OF THE IMPLIED INTENT OF THE DESIGN SHALL BE BROUGHT TO THE ARCHITECT'S ATTENTION 10 DAYS PRIOR TO BID OPENING. IF THESE ARE NOT DISCLOSED PRIOR TO THIS TIME, THE CONTRACTOR SHALL RESOLVE THESE CONFLICTS TO THE ARCHITECT'S SATISFACTION AT NO INCREASE IN CONTRACT COST.

COORDINATION

THE WORK OF THE MECHANICAL AND PLUMBING SPECIFICATIONS SHALL BE COORDINATED WITH THE REQUIREMENTS OF THE OTHER TRADES AND WITH ALL OF THE WORK FOR THE ENTIRE PROJECT. ALL WORK SHALL BE ACCOMPLISHED ON SUCH A SCHEDULE AND IN

SUCH A MANNER AS NOT TO DELAY OR INTERFERE WITH OTHER CONSTRUCTION WORK.

ORDINANCES, PERMITS, METERS AND UTILITIES

THE CONTRACTOR SHALL PROCURE ALL NECESSARY PERMITS OR LICENSES TO CARRY OUT HIS WORK; THE LAWFUL FEES THEREFORE SHALL BE PAID BY THE CONTRACTOR. HE SHALL ALSO OBTAIN THE NECESSARY CERTIFICATES OF APPROVAL, THE COST OF WHICH SHALL BE INCLUDED BY THE CONTRACTOR. THE CONTRACTOR SHALL PAY ALL FEES REQUIRED FOR THE CONNECTION OF

WATER, GAS AND SEWER LINES (AND METER FEES) TO UTILITY COMPANY MAINS.

THE CONTRACTOR SHALL COMPLY WITH ALL LOCAL, STATE AND NATIONAL CODES, INCLUDING APPLICABLE ASME AND NFPA

REQUIREMENTS, AND LOCAL UTILITY COMPANY REQUIREMENTS.

WARRANTY

THE CONTRACTOR SHALL WARRANTY ALL EQUIPMENT AND THE INSTALLATION THEREOF FROM DEFECT FOR A PERIOD OF ONE YEAR AFTER FINAL ACCEPTANCE OF THE BUILDING (UNLESS NOTED OTHERWISE FOR A SPECIFIC ITEM OF EQUIPMENT OR INDICATED

OTHERWISE IN THE GENERAL OR SUPPLEMENTAL CONDITIONS).

LOCATION OF PIPES, DUCTS, ETC.

THE LOCATION OF ALL PIPES, DUCTS, OUTLETS, EQUIPMENT, ETC., SHOWN ON THE DRAWINGS INDICATE THE GENERAL INTENT AND ARRANGEMENT ONLY, AND UNDERSTOOD TO BE SUBJECT TO SUCH REVISION AS MAY BE FOUND NECESSARY OR DESIRABLE AT THE TIME THE WORK IS INSTALLED. ALL SUCH OFFSETS OR REROUTING OF PIPES AND DUCTWORK SHALL BE MADE WHERE REQUIRED TO CLEAR OBSTRUCTIONS, PROVIDED THAT SUCH WORK IS PROPERLY COORDINATED WITH ALL OTHER WORK AND THAT THERE BE NO IMPAIRMENT OF SYSTEM OPERATION AS A RESULT, AND AT NO INCREASE IN CONTRACT COST. GENERALLY, ALL OUTLETS SHALL BE PROPERLY LOCATED FOR THE PURPOSE FOR WHICH THEY ARE INTENDED, OR CENTERED IN ROOMS, PANELS OR FINISHED WORK, AND SHALL NOT INTERFERE WITH OUTLETS OR EQUIPMENT OF OTHER TRADES AND SHALL MEET THE DIMENSIONS OR SCALE DRAWING OF THE ARCHITECT. REFER TO ARCHITECTURAL REFLECTED CEILING PLANS AND DETAILS FOR EXACT LOCATIONS. IN CASES OF CONFLICT, THE SHEETMETAL WORK SHALL TAKE PRECEDENCE, BUT SHALL ALSO BE RESPONSIBLE FOR PRIOR

COORDINATION WITH ALL OTHER TRADES.

QUALITY ASSURANCE

THE INSTALLATION OF ALL WORK IS TO BE DONE IN STRICT ACCORDANCE WITH ALL APPLICABLE LOCAL ORDINANCES AND STATE STATUTES. IN CASE OF CONFLICT, THE CODE HAVING IMMEDIATE JURISDICTION IS TO GOVERN. THE METHODS TO BE USED IN THE INSTALLATION OF THE EQUIPMENT AND MATERIALS MUST MEET OR EXCEED THESE REQUIREMENTS OF THE GOVERNING CODES AND STANDARDS. WHERE THE APPLICATION OF A STANDARD OR CODE APPEARS TO BE IN CONFLICT WITH THE REQUIREMENTS OF THE

CONTRACT DOCUMENTS, CODE COMPLIANCE WILL GOVERN.

EXCEPT AS NOTED OTHERWISE, THE LATEST EDITION OF THE FOLLOWING CODES AND STANDARDS WILL GOVERN:

--- LOCAL PLUMBING AND MECHANICAL CODE

AABA ASSOCIATED AIR BALANCE COUNCIL

AMCA AIR MOVING AND CONDITIONING ASSOCIATION

ANSI AMERICAN NATIONAL STANDARDS INSTITUTE (SUCCESSOR TO ASASI AND ASA)

ARI AIR CONDITIONING AND REFRIGERATION INSTITUTE

ASHRAE AMERICAN SOCIETY OF HEATING, REFRIGERATING, AND AIR CONDITIONING ENGINEERS.

ASME AMERICAN SOCIETY OF MECHANICAL ENGINEERS

ASTM AMERICAN SOCIETY OF TESTING AND MATERIALS

AWS AMERICAN WELDING SOCIETY

AWWA AMERICAN WATER WORKS ASSOCIATION

CISPI CAST IRON SOIL PIPE INSTITUTE

CTI COOLING TOWER INSTITUTE

FM FACTORY MUTUAL ENGINEERING COMPANY

FS FEDERAL SPECIFICATIONS

MSS MANUFACTURER'S STANDARDIZATION SOCIETY OF THE VALVE AND FITTING INDUSTRY

NEC NATIONAL ELECTRICAL CODE BY NFPA

NEMA NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION

NFPA NATIONAL FIRE PROTECTION ASSOCIATION

OSHA OCCUPATIONAL SAFETY AND HEALTH ASSOCIATION

PDI PLUMBING AND DRAINAGE INSTITUTE

SMACNA SHEET METAL AND AIR CONDITIONING CONTRACTORS NATIONAL ASSOCIATION

9. UTILITY CONNECTIONS

ASCERTAIN FROM THE UTILITY DEPARTMENT OF UTILITY COMPANY THE EXACT AMOUNT OF WORK REQUIRED IN CONNECTION OF UTILITIES. WORK REQUIRED WHICH IS NOT PROVIDED BY THE UTILITY DEPARTMENT OR COMPANY SHALL BE PROVIDED BY THE

CONTRACTOR, UNLESS INDICATED OTHERWISE.

VERIFY THE LOCATION AND DEPTH OF ALL UTILITIES AND CALL TO THE ATTENTION OF THE OWNER ANY DISCREPANCIES WHICH

INVOLVE ADDITIONAL WORK BEFORE SIGNING THE CONTRACT.

AFTER THE CONTRACT IS SIGNED, ANY ADDITIONAL WORK REQUIRED FOR THE COMPLETE AND WORKING JOB SHALL BE PROVIDED

AT NO ADDITIONAL COST TO THE OWNER, UNLESS INDICATED OTHERWISE.

LOCATIONS, DEPTHS, SIZES, CAPACITIES, ETC., OF THE UTILITY LINES SHALL BE VERIFIED BY THE CONTRACTOR PRIOR TO DOING ANY OTHER WORK ON PIPING SYSTEMS WHICH ARE TO CONNECT TO SUCH UTILITY LINES. ANY WORK RENDERED UNUSABLE BY FAILURE

TO COMPLY WITH THIS PROVISION SHALL BE REPLACED AT NO COST TO THE OWNER.

UTILITIES AS MENTIONED IN THIS DIVISION OF THE SPECIFICATIONS SHALL INCLUDE WATER, SEWER, GAS AND OTHER PIPING

SYSTEMS NECESSARY TO THE OPERATION OF NEW OR EXISTING SYSTEMS AND EQUIPMENT.

10. LAYING OUT OF THE WORK

LAY OUT WORK ON THE PREMISES AND MAKE PROPER PROVISIONS TO COORDINATE WITH OTHER TRADES. THE EXACT LOCATION OF EACH ITEM SHALL BE DETERMINED BY REFERENCE TO THE GENERAL PLANS, BY MEASUREMENTS AT THE BUILDING AND IN COOPERATION WITH OTHER CONTRACTORS. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ACCURATELY LOCATING ALL

OPENINGS FOR DUCTS, PIPES, ETC., AND ACCESS DOORS REQUIRED.

CONTRACTOR SHALL BE RESPONSIBLE FOR PROVIDING OWNER ACCEPTABLE ACCESS TO ALL AREAS ON EQUIPMENT. DEVICE CONTROLS MANUAL ADJUSTMENT DEVICES, GAUGES AND OTHER MISCELLANEOUS ITEMS SHALL BE EASILY VISIBLE AND ADJUSTABLE

FROM THE DEVICE CONTROL SIDE OF THE UNIT.

11. MECHANICAL COORDINATION

THE INSTALLER OF MECHANICAL WORK IS TO CAREFULLY EXAMINE ALL MECHANICAL, ELECTRICAL, STRUCTURAL, ARCHITECTURAL AND OTHER CONTRACT DRAWINGS BEFORE BEGINNING THE WORK. REPORT ANY APPARENT CONFLICTS, ERRORS, OMISSIONS, OR AMBIGUITIES IN THE CONTRACT DOCUMENTS TO THE OWNER FOR INTERPRETATION OR EXPLANATION BEFORE PERFORMING THE WORK. THE WORK IS TO BE DONE BY CRAFTSMEN SKILLED IN EACH TRADE UNDER THE SUPERVISION OF A FOREMAN WHO IS

EXPERIENCED IN ALL PHASES OF THE WORK REQUIRED BY THIS DIVISION.

B.

C.

D.

E.

F.

IN GENERAL, DRAWINGS FOR THE WORK ARE DIAGRAMMATIC EXCEPT WHERE ITEMS ARE SPECIFICALLY LOCATED BY DIMENSION. THE DRAWINGS SHOW THE LOCATION OF PLUMBING FIXTURES, REFRIGERATION, AIR CONDITIONING, HEATING AND OTHER EQUIPMENT. WHERE CONDITIONS NECESSITATE A REARRANGEMENT OF ANY MECHANICAL EQUIPMENT, THE CONTRACTOR IS TO PREPARE AND SUBMIT FOR APPROVAL SCALED (NO SMALLER THAN 1/4" = 1'-0") DRAWINGS SHOWING HE PROPOSED REARRANGEMENT.

THE MECHANICAL WORK IS TO BE CAREFULLY COORDINATED WITH THE WORK SHOWN ON THE ELECTRICAL, STRUCTURAL, ARCHITECTURAL, AND OTHER DRAWINGS IN ORDER TO AVOID CONFLICTS IN SPACE REQUIREMENTS FOR THE EQUIPMENT INSTALLED. PLAN THE WORK SO THAT ALL EQUIPMENT, VALVES, PIPING AND SPECIALTIES ARE INSTALLED IN SUCH A MANNER AS TO BE ACCESSIBLE FOR MAINTENANCE. IN ORDER TO ACCOMPLISH THIS, MINOR DEVIATIONS FROM THE DRAWINGS DUE TO ARCHITECTURAL DETAILS AND JOB CONDITIONS WILL BE PERMITTED WHEN REQUESTED. PROVIDE ALL OFFSETS AS REQUIRED IN THE PIPING AND DUCTWORK IN ORDER TO PRODUCE A NEAT AND

FUNCTIONAL ARRANGEMENT.

AFTER APPROVAL OF THE MAJOR ITEMS OF EQUIPMENT, IF SUCH EQUIPMENT DIFFERS DIMENSIONALLY FROM THAT SHOWN ON THE DRAWINGS, BEFORE PROCEEDING WITH ANY PART OF THE WORK, THE CONTRACTOR IS TO PREPARE AND SUBMIT FOR APPROVAL FIELD AND SHOP DRAWINGS SHOWING PROPERLY DIMENSIONED LAYOUTS OF THE EQUIPMENT WITHIN THE ALLOTTED SPACES. THESE DRAWINGS ARE TO SHOW THE EXACT LOCATION AND DETAILS OF ALL PIPING. EQUIPMENT THAT WILL NOT FIT INTO THE ALLOTTED SPACE WITH CLEARANCE

COMMENSURABLE TO THESE SHOWN ON THE DRAWINGS WILL NOT BE CONSIDERED.

ALL WORK IS TO BE SCHEDULED, PLANNED AND EXECUTED SO AS NOT TO INTERFERE WITH OR DELAY THE WORK OF ANY OTHER

CONTRACTOR.

IF, AFTER ANY OF THE WORK IS INSTALLED, AND THE ARCHITECTURAL, MECHANICAL, ELECTRICAL, OR STRUCTURAL DESIGN CANNOT BE FOLLOWED IN ACCORDANCE WITH THE DRAWINGS, THE CONTRACTOR WILL, AT HIS OWN EXPENSE, MAKE SUCH CHANGES AS DIRECTED BY THE OWNER IN THE WORK HEREUNDER AS WILL PERMIT THE PROPER INSTALLATION OF ALL OTHER WORK AS SHOWN ON THE DRAWINGS.

COPYRIGHT 2025 OLSSON ALL RIGHTS RESERVED.

THIS DRAWING IS PROPERTY OF OLSSON. ANY MODIFICATION OR USE OF THIS DRAWING

WITHOUT EXPRESS WRITTEN AUTHORIZATION OF OLSSON IS PROHIBITED.

DC# 24155 / OLSSON# 025-00948SHEET SIZE: 30X42

OK COA #: 2483 EXPIRES 2027-06-30

Date:

ADGB Project:

Sheet No.

Revisions:

C op yr ig ht A

D G

B

LA

TT

, P

C

920 W. Main St.

Oklahoma City, OK 73106

Phone-Edmond: 405.340.8552 Web: www.adgblatt.com

101 S. Broadway, Suite 200 Edmond, OK 73034 Phone-OKC: 405.232.5700

8/ 4/

:2

7:

P M

M-002

MECHANICAL

LEGEND,

ABBREVIATION,

AND NOTES

23-113

AUGUST 04, 2025

M B-

M

YR

IA

D

G A

RD

EN

S C

HI

LL

ED

W

A

TE

R

IN

ST

A

LL

A

TIO

N

301 W. Reno Ave, Oklahoma City, OK 73102

IS

SU

ED

F

O R

BI

D

28' 29 30 31 32

Y

Z

AA

BB

CC

DD

EE

AHU-02 AHU-01

AHU-04 AHU-03

AHU-06 AHU-05

UH-1

AHU-08 AHU-07

AHU-10 AHU-09

UH-2

01 M-102

COPYRIGHT 2025 OLSSON ALL RIGHTS RESERVED.

THIS DRAWING IS PROPERTY OF OLSSON. ANY MODIFICATION OR USE OF THIS DRAWING

WITHOUT EXPRESS WRITTEN AUTHORIZATION OF OLSSON IS PROHIBITED.

DC# 24155 / OLSSON# 025-00948SHEET SIZE: 30X42

OK COA #: 2483 EXPIRES 2027-06-30

Date:

ADGB Project:

Sheet No.

Revisions:

C op yr ig ht A

D G

B

LA

TT

, P

C

920 W. Main St.

Oklahoma City, OK 73106

Phone-Edmond: 405.340.8552 Web: www.adgblatt.com

101 S. Broadway, Suite 200 Edmond, OK 73034 Phone-OKC: 405.232.5700

8/ 4/

:2

7:

P M

M-101

DEMOLITION PLAN

- BASEMENT

NORTH

23-113

AUGUST 04, 2025

M B-

M

YR

IA

D

G A

RD

EN

S C

HI

LL

ED

W

A

TE

R

IN

ST

A

LL

A

TIO

N

301 W. Reno Ave, Oklahoma City, OK 73102

IS

SU

ED

F

O R

BI

D

1/4" = 1'-0"01 BASEMENT MECHANICAL ROOM DEMOLITION- NORTH

A.

B.

C.

GENERAL SHEET NOTES:

DEMOLISH AND REMOVE EXISTING AIR HANDLERS

INDICATED. REMOVE ALL ACCESSORIES AND

APPURTENANCES. DEMOLISH EXISTING

DUCTWORK AS REQUIRED TO INSTALL AND

CONNECT TO NEW AIR HANDLING UNITS.

NO EQUIPMENT OR MATERIALS SHALL BE

ABANDONED IN PLACE.

FOR AIR HANDLERS TO BE DEMOLISHED, REMOVE

EXISTING HEATING WATER PIPING BACK TO

EXISTING BRANCH ISOLATION VALVES. PREP FOR

NEW PIPING INSTALLATION.

Q

R

S

T

U

V

W

X

AHU-10 AHU-09

AHU-12 AHU-11

AHU-14

AHU-13

AHU-15AHU-16

AHU-18 AHU-17

AHU-19AHU-20

EXISTING RETURN

AIR TUNNEL FROM

CONSERVATORY

EXISTING RETURN

AIR TUNNEL FROM

CONSERVATORY

UH-3

EXISTING ELECTRICAL MCCEXISTING ELECTRICAL MCC

3"ø F

01 M-101

COPYRIGHT 2025 OLSSON ALL RIGHTS RESERVED.

THIS DRAWING IS PROPERTY OF OLSSON. ANY MODIFICATION OR USE OF THIS DRAWING

WITHOUT EXPRESS WRITTEN AUTHORIZATION OF OLSSON IS PROHIBITED.

DC# 24155 / OLSSON# 025-00948SHEET SIZE: 30X42

OK COA #: 2483 EXPIRES 2027-06-30

Date:

ADGB Project:

Sheet No.

Revisions:

C op yr ig ht A

D G

B

LA

TT

, P

C

920 W. Main St.

Oklahoma City, OK 73106

Phone-Edmond: 405.340.8552 Web: www.adgblatt.com

101 S. Broadway, Suite 200 Edmond, OK 73034 Phone-OKC: 405.232.5700

8/ 4/

:2

7:

P M

M-102

DEMOLITION PLAN

- BASEMENT SOUTH

23-113

AUGUST 04, 2025

M B-

M

YR

IA

D

G A

RD

EN

S C

HI

LL

ED

W

A

TE

R

IN

ST

A

LL

A

TIO

N

301 W. Reno Ave, Oklahoma City, OK 73102

IS

SU

ED

F

O R

BI

D

1/4" = 1'-0"01 BASEMENT MECHANICAL ROOM DEMOLITION - SOUTH

A.

B.

C.

GENERAL SHEET NOTES:

DEMOLISH AND REMOVE EXISTING AIR HANDLERS

INDICATED. REMOVE ALL ACCESSORIES AND

APPURTENANCES. DEMOLISH EXISTING

DUCTWORK AS REQUIRED TO INSTALL AND

CONNECT TO NEW AIR HANDLING UNITS.

NO EQUIPMENT OR MATERIALS SHALL BE

ABANDONED IN PLACE.

FOR AIR HANDLERS TO BE DEMOLISHED, REMOVE

EXISTING HEATING WATER PIPING BACK TO

EXISTING BRANCH ISOLATION VALVES. PREP FOR

NEW PIPING INSTALLATION.

Y

Z

AA

BB

CC

DD

EE

AHU-02 AHU-01

AHU-05

UH-1

AHU-08

AHU-10 AHU-09

UH-2

AHU-07

AHU-06

AHU-04

AHU-03

6" ø

C H

W S

6" ø

C H

W R

8"ø CHWS

8"ø CHWR

01 M-302

7 8

LOCATE NEW CHWS/R PIPING

NEAR THIS STRUT LOCATION

FOR STRUCTURAL SUPPORT.

COPYRIGHT 2025 OLSSON ALL RIGHTS RESERVED.

THIS DRAWING IS PROPERTY OF OLSSON. ANY MODIFICATION OR USE OF THIS DRAWING

WITHOUT EXPRESS WRITTEN AUTHORIZATION OF OLSSON IS PROHIBITED.

DC# 24155 / OLSSON# 025-00948SHEET SIZE: 30X42

OK COA #: 2483 EXPIRES 2027-06-30

Date:

ADGB Project:

Sheet No.

Revisions:

C op yr ig ht A

D G

B

LA

TT

, P

C

920 W. Main St.

Oklahoma City, OK 73106

Phone-Edmond: 405.340.8552 Web: www.adgblatt.com

101 S. Broadway, Suite 200 Edmond, OK 73034 Phone-OKC: 405.232.5700

8/ 4/

:2

7:

P M

M-301

HVAC PIPING

PLAN - BASEMENT

NORTH

23-113

AUGUST 04, 2025

M B-

M

YR

IA

D

G A

RD

EN

S C

HI

LL

ED

W

A

TE

R

IN

ST

A

LL

A

TIO

N

301 W. Reno Ave, Oklahoma City, OK 73102

IS

SU

ED

F

O R

BI

D

1/4" = 1'-0"01 BASEMENT MECHANICAL ROOM - NORTH

A.

B.

C.

D.

E.

F.

G.

H.

I.

J.

GENERAL NOTES:

NEW AIR HANDLING UNITS HAVE BEEN PRE-

PURCHASED BY OWNER THROUGH MC.

COORDINATE ALL PIPE AND DUCT INSTALLATION

WITH FINAL EQUIPMENT CONNECTIONS.

INSTALL EQUIPMENT AND MATERIALS TO ALLOW

FOR MAINTENANCE ACCESS AND SERVICE

CLEARANCE WHERE REQUIRED BY

MANUFACTURER.

WHEN ROUTING NEW CHILLED WATER PIPING,

MAINTAIN MINIMUM 6'-0" FOR HEADROOM.

EXISTING HEATING WATER PIPING NOT SHOWN.

PROVIDE NEW HEATING WATER PIPING AS

REQUIRED AND CONNECT TO NEW AIR

HANDLERS. REFER TO DETAIL 1 / M-501.

EXISTING HVAC DUCTWORK NOT SHOWN.

CONNECT NEW AIR HANDLING UNITS TO EXISTING

DUCTWORK. PROVIDE FLEXIBLE CONNECTORS AT

DUCT CONNECTIONS.

PROVIDE MOUNTING SUPPORTS FOR AIR

HANDLING UNITS SIMILAR TO EXISTING UNITS

USING SQUARE TUBE STRUCTURAL STEEL.

FOR EXISTING AIR HANDLERS TO REMAIN,

EXISTING HEATING WATER IS ALREADY

CONNECTED. ONLY CHILLED WATER

CONNECTIONS ARE IN SCOPE OF WORK.

FOR EXISTING TO REMAIN AHU'S, PREVIOUS

DESIGN INFO INDICATES 2.5" COIL CONNECTION

SIZE. CONTRACTOR TO VERIFY.

CONTRACTOR SHALL NOT CUT OR CORE

THROUGH ANY STRUCTURAL MEMBERS OF THE

EXISTING BUILDING, INCLUDING BUT NOT LIMITED

TO WALLS, COLUMNS, BEAMS, SLAB, OR STRUTS.

NOTIFY ENGINEER OF MAJOR DEVIATIONS OF

PIPE ROUTING TO EVALUATE STRUCTURAL

IMPACTS.

NO. KEYED NOTES:

1. ROUTE NEW NEW 8"Ø CHWS AND CHWR PIPING

THROUGH WEST WALL AND UP THROUGH RETURN

GRATE IN FLOOR.

2. INSTALL NEW UTILITY METER IN THIS APPROXIMATE

LOCATION. METER IS FURNISHED BY OTHERS,

INSTALLED IN PIPING BY MC.

3. EXISTING SPRINKLER PIPING.

4. ROUTE CHWS/R PIPING UP HIGH TIGHT TO CONDUIT

MOUNTED ON UNDERSIDE OF DECK ABOVE.

5. ROUTE NEW CHILLED WATER PIPING LOW APPROX. 12"

AFF UNDER EXISTING RA DUCTWORK SERVING AHU-02.

6. ROUTE NEW CHILLED WATER PIPING UP HIGH TIGHT

TO CEILING.

7. MODIFY EXISTING RETURN AIR DUCTWORK

CONNECTING TO AHU-04 TO ALLOW ROOM FOR NEW

CHILLED WATER PIPING AND UTILITY METER.

8. PROVIDE MANUAL AIR VENTS IN THIS APPROXIMATE

LOCATION.

Q

R

S

T

U

V

W

X AHU-10 AHU-09

AHU-12

AHU-14

AHU-17

AHU-20

EXISTING RETURN

AIR TUNNEL FROM

CONSERVATORY

EXISTING RETURN

AIR TUNNEL FROM

CONSERVATORY

UH-3

EXISTING ELECTRICAL MCCEXISTING ELECTRICAL MCC

3"ø F

AHU-19

AHU-18

AHU-15AHU-16

AHU-13

AHU-11

01 M-301

6"ø CHWS 6"ø CHWS 6"ø CHWR6"ø CHWR

4"ø CHWS 4"ø CHWR

4"ø CHWR 4"ø CHWS

4"ø CHWR 4"ø CHWS

4"ø CHWR 4"ø CHWS

1/4" = 1'-0"01 BASEMENT MECHANICAL ROOM - SOUTH

COPYRIGHT 2025 OLSSON ALL RIGHTS RESERVED.

THIS DRAWING IS PROPERTY OF OLSSON. ANY MODIFICATION OR USE OF THIS DRAWING

WITHOUT EXPRESS WRITTEN AUTHORIZATION OF OLSSON IS PROHIBITED.

DC# 24155 / OLSSON# 025-00948SHEET SIZE: 30X42

OK COA #: 2483 EXPIRES 2027-06-30

Date:

ADGB Project:

Sheet No.

Revisions:

C op yr ig ht A

D G

B

LA

TT

, P

C

920 W. Main St.

Oklahoma City, OK 73106

Phone-Edmond: 405.340.8552 Web: www.adgblatt.com

101 S. Broadway, Suite 200 Edmond, OK 73034 Phone-OKC: 405.232.5700

8/ 4/

:2

7:

P M

M-302

HVAC PIPING

PLAN - BASEMENT

SOUTH

23-113

AUGUST 04, 2025

M B-

M

YR

IA

D

G A

RD

EN

S C

HI

LL

ED

W

A

TE

R

IN

ST

A

LL

A

TIO

N

301 W. Reno Ave, Oklahoma City, OK 73102

IS

SU

ED

F

O R

BI

D

NO. KEYED NOTES:

1. ROUTE CHWS/R PIPING AROUND EXISTING DDC

CABINET.

2. ROUTE CHWS/R PIPING DOWN UNDERNEATH

STUCTURAL BEAM TO LOWER CEILING AREA.

3 PROVIDE 1" END OF LINE BYPASS WITH AUTOFLOW

LIMITING VALVE.

A.

B.

C.

D.

E.

F.

G.

H.

I.

J.

GENERAL NOTES:

NEW AIR HANDLING UNITS HAVE BEEN PRE-

PURCHASED BY OWNER THROUGH MC.

COORDINATE ALL PIPE AND DUCT INSTALLATION

WITH FINAL EQUIPMENT CONNECTIONS.

INSTALL EQUIPMENT AND MATERIALS TO ALLOW

FOR MAINTENANCE ACCESS AND SERVICE

CLEARANCE WHERE REQUIRED BY

MANUFACTURER.

WHEN ROUTING NEW CHILLED WATER PIPING,

MAINTAIN MINIMUM 6'-0" FOR HEADROOM.

EXISTING HEATING WATER PIPING NOT SHOWN.

PROVIDE NEW HEATING WATER PIPING AS

REQUIRED AND CONNECT TO NEW AIR

HANDLERS. REFER TO DETAIL 1 / M-501.

EXISTING HVAC DUCTWORK NOT SHOWN.

CONNECT NEW AIR HANDLING UNITS TO

EXISTING DUCTWORK. PROVIDE FLEXIBLE

CONNECTORS AT DUCT CONNECTIONS.

PROVIDE MOUNTING SUPPORTS FOR AIR

HANDLING UNITS SIMILAR TO EXISTING UNITS

USING SQUARE TUBE STRUCTURAL STEEL.

FOR EXISTING AIR HANDLERS TO REMAIN,

EXISTING HEATING WATER IS ALREADY

CONNECTED. ONLY CHILLED WATER

CONNECTIONS ARE IN SCOPE OF WORK.

FOR EXISTING TO REMAIN AHU'S, PREVIOUS

DESIGN INFO INDICATES 2.5" COIL CONNECTION

SIZE. CONTRACTOR TO VERIFY.

CONTRACTOR SHALL NOT CUT OR CORE

THROUGH ANY STRUCTURAL MEMBERS OF THE

EXISTING BUILDING, INCLUDING BUT NOT LIMITED

TO WALLS, COLUMNS, BEAMS, SLAB, OR STRUTS.

NOTIFY ENGINEER OF MAJOR DEVIATIONS OF

PIPE ROUTING TO EVALUATE STRUCTURAL

IMPACTS.

MAV

COIL DESIGNATION A B

TYP. AHU CHW COIL

TYP. AHU HW COIL

3" 2-1/2"

2-1/2" 2"

RETURN

SUPPLY

"D"

"A"

MAV

C

2-1/2"

2"

D

3"

2-1/2"

"B"

"C"

"B"

"C"

P/T PORT

UNION OR FLANGE CONNECTION

3/4" DRAIN VALVE

BUTTERFLY VALVE

ECCENTRIC REDUCER

CONCENTRIC REDUCER

TWO-WAY PRESSURE INDEPENDENT

CONTROL VALVE. REFER TO

SCHEDULES FOR VALVE.

3/4" CAPPED TEE FOR FLUSHING

THERMOMETER

NOTE:

NEW HEATING WATER PIPING & CONNECTIONS ONLY APPLICABLE TO

NEW AIR HANDLING UNITS.

P

1/4"

1/4"

COPYRIGHT 2025 OLSSON ALL RIGHTS RESERVED.

THIS DRAWING IS PROPERTY OF OLSSON. ANY MODIFICATION OR USE OF THIS DRAWING

WITHOUT EXPRESS WRITTEN AUTHORIZATION OF OLSSON IS PROHIBITED.

DC# 24155 / OLSSON# 025-00948SHEET SIZE: 30X42

OK COA #: 2483 EXPIRES 2027-06-30

Date:

ADGB Project:

Sheet No.

Revisions:

C op yr ig ht A

D G

B

LA

TT

, P

C

920 W. Main St.

Oklahoma City, OK 73106

Phone-Edmond: 405.340.8552 Web: www.adgblatt.com

101 S. Broadway, Suite 200 Edmond, OK 73034 Phone-OKC: 405.232.5700

8/ 4/

:2

7:

P M

M-501

MECHANICAL

DETAILS AND

SCHEDULES

23-113

AUGUST 04, 2025

M B-

M

YR

IA

D

G A

RD

EN

S C

HI

LL

ED

W

A

TE

R

IN

ST

A

LL

A

TIO

N

301 W. Reno Ave, Oklahoma City, OK 73102

IS

SU

ED

F

O R

BI

D

NTS1 COIL CONNECTION DETAIL (AHU STACKED COIL - TWO WAY)

CONTROL VALVE SCHEDULE

MARK SERVES FLUID CONFIGURATION SIZE TYPE

DESIGN FLOW

(GPM)

MAX PRESSURE

DIFF (PSID) CHARACTERISTIC

ACTUATOR INFORMATION BASIS OF DESIGN

NOTESACTUATOR TYPE FAILSAFE VOLTAGE MANUFACTURER VALVE ACTUATOR

AHU CHW VALVE CHILLED WATER WATER - 55°F TWO-WAY 2-1/2" PICV 101 116 EQUAL PERCENTAGE MODULATING - PROPORTIONAL FC 24V BRAY SSM-250-A-L-102 GASEX24-450 1,3 AHU HW VALVE HEATING WATER WATER - 170°F TWO-WAY 2" PICV 55 58 EQUAL PERCENTAGE MODULATING - PROPORTIONAL FIP 24V BRAY SS-2-N-S-56.1 PAM24-27 2,3

1.

2.

3.

NOTES:

VALVE IS TYPICAL FOR ALL AHU CHILLED WATER COILS.

VALVE IS TYPICAL FOR ALL AHU HEATING WATER COILS. ONLY PROVIDE VALVES FOR AIR HANDLERS BEING REPLACED.

FAILSAFE NOMENCLATURE: FO = FAIL OPEN, FC = FAIL CLOSED, FIP = FAIL IN PLACE.

P

8" CHWS

8" CHWR

AHU-01

42.3 TONS

101 GPM

AHU-02

42.3 TONS

101 GPM

AHU-03

42.3 TONS

101 GPM

AHU-04

42.3 TONS

101 GPM

AHU-05

42.3 TONS

101 GPM

AHU-06

42.3 TONS

101 GPM

AHU-07

42.3 TONS

101 GPM

AHU-08

42.3 TONS

101 GPM

AHU-09

42.3 TONS

101 GPM

AHU-10

42.3 TONS

101 GPM

AHU-11

42.3 TONS

101 GPM

AHU-12

42.3 TONS

101 GPM

AHU-13

42.3 TONS

101 GPM

AHU-14

42.3 TONS

101 GPM

AHU-15

42.3 TONS

101 GPM

AHU-16

42.3 TONS

101 GPM

AHU-17

42.3 TONS

101 GPM

AHU-18

42.3 TONS

101 GPM

AHU-19

42.3 TONS

101 GPM

AHU-20

42.3 TONS

101 GPM

BYPASS VALVE

8"

M

MIN. 5 FT LENGTH

MIN. 2 1/2 FT LENGTH

8 FT

MIN

6"

3"

3"

3"

3"

8"

8"

8"

8"

8"

6" CHWR

6" CHWS

6" CHWR

6" CHWS

4"

4"

4"

4"

GROUND LEVEL

BASEMENT LEVEL

PENETRATE EXISTING

GREENHOUSE PLASTIC

WINDOW MATERIAL.

COORDINATE WITH

ARCHITECT FOR

PENETRATION

REQUIREMENTS.

ROUTE NEW PIPING

THROUGH EXISTING

RETURN AIR FLOOR GRATE.

EXISTING

GREENHOUSE

CRYSTAL BRIDGE

WEST RETURN

AIR TUNNEL

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

3"

MAV

MAV

MAV

MAV

8" C

H W

S

8" C

H W

R

A

COPYRIGHT 2025 OLSSON ALL RIGHTS RESERVED.

THIS DRAWING IS PROPERTY OF OLSSON. ANY MODIFICATION OR USE OF THIS DRAWING

WITHOUT EXPRESS WRITTEN AUTHORIZATION OF OLSSON IS PROHIBITED.

DC# 24155 / OLSSON# 025-00948SHEET SIZE: 30X42

OK COA #: 2483 EXPIRES 2027-06-30

Date:

ADGB Project:

Sheet No.

Revisions:

C op yr ig ht A

D G

B

LA

TT

, P

C

920 W. Main St.

Oklahoma City, OK 73106

Phone-Edmond: 405.340.8552 Web: www.adgblatt.com

101 S. Broadway, Suite 200 Edmond, OK 73034 Phone-OKC: 405.232.5700

8/ 4/

:2

7:

P M

M-601

CHILLED WATER

PIPING DIAGRAM

23-113

AUGUST 04, 2025

M B-

M

YR

IA

D

G A

RD

EN

S C

HI

LL

ED

W

A

TE

R

IN

ST

A

LL

A

TIO

N

301 W. Reno Ave, Oklahoma City, OK 73102

IS

SU

ED

F

O R

BI

D

NTS1 CHILLED WATER PIPING SCHEMATIC

A.

B.

C.

GENERAL NOTES:

REFER TO TYPICAL AHU COIL CONNECTION DETAIL

1/M-501 FOR ALL COMPONENTS BETWEEN AHU

COIL'S AND ISOLATION VALVES.

PREVIOUS DESIGN INFORMATION INDICATE

EXISTING AHU CHILLED WATER COIL

CONNECTIONS TO BE 2.5" FLANGE. CONTRACTOR

TO FIELD VERIFY.

CONTRACTOR SHALL NOT CUT OR CORE

THROUGH ANY STRUCTURAL MEMBERS OF THE

EXISTING BUILDING, INCLUDING BUT NOT LIMITED

TO WALLS, COLUMNS, BEAMS, SLAB, OR STRUTS.

NO. KEYED NOTES:

1. CHILLED WATER CUSTOMER CONNECTION. CONNECT

NEW CHILLED WATER PIPING TO EXISTING PIPING BY

UTILITY SUPPLIER.

2. PENETRATE RETURN AIR TUNNEL IN NORTHWEST

CORNER THROUGH WEST GYP WALL.

3. PROVIDE TWO THERMAL WELLS IN PIPING. WELLS

SHALL HAVE A 3/4 INCH THREADOLET AND BE 6" - 12"

APART.

4. PROVIDE 1" AUTOFLOW LIMITING VALVE. VALVE SHALL

BE SET AT 10 GPM.

M-001-MECHANICAL LEGEND, ABBREVIATIONS, AND NOTES
M-002-MECHANICAL LEGEND, ABBREVIATION, AND NOTES
M-101-DEMOLITION PLAN - BASEMENT NORTH
M-102-DEMOLITION PLAN - BASEMENT SOUTH
M-301-HVAC PIPING PLAN - BASEMENT NORTH
M-302-HVAC PIPING PLAN - BASEMENT SOUTH
M-501-MECHANICAL DETAILS AND SCHEDULES
M-601-CHILLED WATER PIPING DIAGRAM

File details come from the government source that posted it. Updated .