Technical-Exhibit-2: Deliverables.

DELIVERABLE
PWS PARA
FREQUENCY
NO OF COPIES
SUBMIT TO
Quality Control Program
4.2.
Within 30 calendar days after contract award and within 7 working days when changes are made thereafter
1
KO/COR
License & Certificate
1.7.
With Proposal Submittal
1
KO/COR
Personnel Qualification
1.7.
With Proposal Submittal
1
KO/COR
Driver’s License
1.9.
Within 7 calendar days after contract award
1
COR
Safety Plan
2.4.8.
Within 10 calendar days after contract award
1
COR
AT Level I Training Certificate
1.11.1.
Within 30 calendar days of contract award
1
COR
iWATCH Training Certificate
1.11.3.
Within 14 calendar days of contract award
1
COR
Daily Report
5.1.2.
Daily/0830 hrs
1
COR
Organization Chart
1.7.5
10 calendar days after award
1
COR
Contractor sample badge
1.10
When work is performed and submitted for approval within 5 calendar days
2
COR
Accident reports
2.2.5.1.
Within 30 minutes of the incident
As req
KO/COR
Completed Service Orders
5.5.1.3.
By every Monday 0900 hours
1
COR
Sampling and analysis of treated water report
5.2.2.
By every day, monthly, quarterly, and annually IAW para 5.2.2.3.
1
COR & Env Div
Sampling and analysis of Waste Water report
5.3.2.
At least every month
1
COR & Env Div
Daily check/activity list shown on page 3 of "Maintenance-FOS-Cp-Carroll_Technical-Exhibit-4
5.3.7
Every day
1
COR & O&M, and Env Div
Corrective action/plan of WTP & WWTP
5.1.3
As needed
1
COR & O&M, and Env Div

File details come from the government source that posted it. Updated .