This document is a Notice of Intent/Annual Requirements Synopsis for a Multiple Award Construction Basic Ordering Agreement (MACB) for Tinker Air Force Base (TAFB). The BOA program will provide a broad range of construction, repair, and maintenance services for real property, including 35% Design-Build, 100% Design-Build, and Construction Only services. The competitive acquisition approach includes set-asides for small businesses on projects up to $25M, with full and open competition for projects over $25M, using NAICS Code 236210 with a $45M size standard.
The procurement will follow a two-phase process: Phase One involves an annual BOA Invitation for contractors to submit proposals and become BOA holders, with no-cost agreements valid for up to five years. Phase Two will involve competitive Order Proposal Requests (OPRs) issued to qualified BOA holders. The synopsis includes an extensive list of specific construction projects at TAFB, ranging from small repairs like replacing deteriorated steps to larger renovations such as restroom renovations, with project magnitudes varying from $25,000 to $5,000,000. Each project requires contractors to provide labor, materials, equipment, and incidentals while conforming to various technical specifications and standards.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2026 MACBOA FA813726R0004 RFI Round 2.docx | DOCX document | |
| 2026 MACBOA FA813726R0004 RFIs.docx | DOCX document | |
| 2020 TAFB Facility Standard.pdf | ||
| 2025 TAFB Mechanical Standard_Signed.pdf | ||
| 2025 TAFB Electrical Standards - Signed.pdf | ||
| Solicitation - FA813726R0004.pdf | ||
| Statement of Work 26 May 2021.pdf | ||
| Experience Matrix.pdf | ||
| SECTION A Executive Summary.docx | DOCX document | |
| MACB Provision and Clause Matrix.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOTICE OF INTENT/ANNUAL REQUIREMENTS SYNOPSIS
COMPETITIVE MULTIPLE AWARD CONSTRUCTION BASIC ORDERING AGREEMENT (BOA) (MACB)
This notice is for the Tinker Air Force Base (TAFB) Multiple Award Construction Basic Ordering Agreement (BOA) Program to provide a broad range of construction, repair, and maintenance of real property. The BOA program will include: 35% Design-Build, 100% Design-Build and Construction Only services at TAFB, OK.
This competitive acquisition approach will set-aside, for small businesses, Order Proposal Requests (OPRs) with a magnitude of construction less than or equal to $25M and on a full and open basis for OPR(s) with a magnitude of construction more than $25M. The North American Industry Classification System (NAICS) Code is 236210 Industrial Building Construction with corresponding annual size standard of $45,000,000.
As Identified in the BOA Source Sought Synopsis, the TAFB will procure all BOA requirements utilizing a phased procurement process outlined below:
Phase One- Competition for BOA Holders: Basic Ordering Agreement Invitation will be released at least once a year to allow interested contractors an opportunity to submit a proposal for evaluation to obtain an executed BOA. The Government will execute no-cost BOAs to offerors who are deemed responsible in accordance with (IAW) the FAR Part 9, as supplemented, whose proposal conforms to the BOA Invitation requirements (to include all stated terms, conditions, representations, certifications, and all other information required by Instructions to Offerors and is assessed based on the evaluation factors and subfactors to be responsive, responsible, and qualified to the Government. The Government seeks to issue BOAs to offerors that gives the Air Force the greatest confidence they will best meet the requirements.
The BOAs will be valid for a period of up to five (5) years beginning from the effective date of the initial BOA execution. An annual synopsis for requirements falling under the scope of the MACB program will be released in sam.gov. The annual synopsis covers requirements related to Construction Services that are within the scope of, and designated for, the MACB program and that emerge within the year after the annual synopsis is published. The Government will not conduct a separate BOA synopsis for any such emergent requirement prior to issuing the applicable competitive OPR(s) Phase Two- Competitive Requirement/Order Process within BOA Holder Pool: The Procuring Contracting Officer (PCO) will issue competitive OPRs for specific requirements falling under the scope of the MACB program. An offeror must be a qualified BOA holder as of the closing date of an OPR. The Government will confirm that an offeror is a qualified BOA holder by checking the effective date of an offerors BOA. All OPR(s) will result in order contracts. NOTE: The annual BOA Invitation may be the only opportunity contractors will have to obtain an executed BOA in order to propose on OPRs issued within the year; additional BOA proposals may not be solicited, accepted, and may not be executed, at any time other than during the annual BOA RFP, even for those emergent requirements not specifically identified in the annual synopsis. Therefore, if a contractor desires to participate in ANY future BOA OPR that may arise within the year, it is imperative that the contractor submit a proposal in response to the annual BOA Invitation.
A one-time Pre-BOA Invitation Conference teleconference will be conducted at Tinker AFB, OK. The exact date, time, and location of the Pre-BOA Invitation Conference will be provided on this post at a later date. Registration will be necessary, and all required information and details will be detailed here on sam.gov. Further, a formal BOA Invitation with supporting documents will be posted following to the pre-solicitation conference, thereby providing offerors the opportunity to thoroughly review and understand the requirement prior to proposal submission.
IMPORTANT NOTICE: Offerors are required to complete their registration in the System for Award Management (SAM) database via the website https://www.sam.gov. Offerors are strongly recommended to review their information in SAM to validate that it is current and up to date. Failure to register in SAM makes an offeror ineligible for BOA Issuance and award of DoD contracts IAW FAR 4.1102 registered in SAM database (http://www.sam.gov/).
DISCLAIMER: The information being requested does not constitute a commitment on the part of the government to award a contract, nor to pay for any costs incurred as a result in replying to this notice. This notice should not be construed as a commitment by the government for any purpose.
ANNUAL SYNOPSIS:
An Annual BOA Synopsis is hereby published as follows:
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR CRACKS IN OUTSIDE BRICK WALLS AT B3001 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated to be less than $25,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to INSTALL SPACE HVAC SYSTEM FOR RM 143, B1130 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated to be less than $25,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to CONNECT A/C ALARM IN S. VAULT TO CE ALARM PANEL at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated to be less than $25,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR POWER PLANT SUPPORT GENERATOR B3001 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $500,000 and $1,000,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to RENOVATE RESTROOMS, B117 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $500,000 and $1,000,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR HVAC SYSTEM, B976 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $500,000 and $1,000,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to RENOVATE CUSTOMER BATHROOMS TO COMPLY WITH ADA STANDARDS, B6001 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $500,000 and $1,000,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPLACE EXTERIOR WINDOWS, B416, DOOR 21 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $250,000 and $500,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPLACE INSTALL ADA ELEVATOR IN B510 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $250,000 and $500,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to RENOVATE B3705, ROOM 11 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $250,000 and $500,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR FIRE SUPPRESSION SYSTEM, MECH ROOMS, B1 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $250,000 and $500,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR OVERHEAD DOORS FIRE STATION, B989 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $250,000 and $500,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR WOMENS SHOWERS B6004 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $250,000 and $500,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR ATFP, BLDG 1083 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $250,000 and $500,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR ROOF, B285 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $250,000 and $500,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR MENS & WOMENS RESTROOMS IN 552 ACW HQS, B280 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $250,000 and $500,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to RENOVATE FIRE SUPPRESSION SYSTEM FOR AFFF REMOVAL, B809 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $250,000 and $500,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPLACE GENERATORS, MULTI FACILITIES at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $250,000 and $500,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPLACE ROOF, B38 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $25,000 and $100,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPLACE DETERIORATED STEPS, B3001, DOOR G at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $25,000 and $100,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPLACE ROOF B62515 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $25,000 and $100,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR & REPLACE STANDBY GENERATOR FOR B117 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $25,000 and $100,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to WIDEN SHOULDERS OF TAXIWAY C at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $25,000 and $100,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPLACE GENERATOR TANK, B42 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $25,000 and $100,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR ROOF B1156 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $25,000 and $100,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR EMER STOP SWITCHES-HYDRANT SYSTEM, B260 & B230 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $25,000 and $100,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to INSTALL MASS NOTIFICATION SYSTEM, COURT HOUSE B1014 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $25,000 and $100,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR GENERATOR & AUTOMATIC TRANSFER, B928 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $25,000 and $100,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR GENERATOR & AUTOMATIC TRANSFER, B942 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $25,000 and $100,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPLACE GENERATOR, B988 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $100,000 and $250,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPLACE ADA TURNSTILE, B230 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $100,000 and $250,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR BASKETBALL COURT, B5520 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $100,000 and $250,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPLACE EDGING ALONG TAXIWAY AND APRON EDGES at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $100,000 and $250,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR ROOF, B4001 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $100,000 and $250,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPLACE #2 3000 GAL & #2 2000 GAL AIR STORAGE TANKS at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $100,000 and $250,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPLACE HASP LOCKS W/DOOR LOCKS ON ALL MECH ROOMS at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $100,000 and $250,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPLACE HOIST SYSTEM AWAC AGE SHOP, B220 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $100,000 and $250,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR BY RESEALING ALL EXTERIOR TILT-UP CONSTRUCTION PANELS, B296 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $100,000 and $250,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR STRUCTURAL DISPLACEMENTS, B989 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $100,000 and $250,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR MANHOLE COVERS, B1083 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $100,000 and $250,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR ROOF, B1036 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $100,000 and $250,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR ROOF, B7042 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Task Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $100,000 and $250,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPLACE FENCE TIES AND OUTRIGGERS, B11500 Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $100,000 and $250,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR CONCRETE VAULT & DIESEL FUEL TANK, B240 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $100,000 and $250,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPLACE DUCTWORK, B6002 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $100,000 and $250,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR GENERATOR FOR LIFT STATION, B22125 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $100,000 and $250,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to RENOVATE RESTROOMS, B6004 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $1,000,000 and $5,000,000.
The contractor shall provide all labor, tools, material, equipment, testing, personal protective equipment, transportation and other incidentals necessary to REPAIR ROOF, B5929 at Tinker Air Force Base (TAFB), Oklahoma. The contractor shall be responsible for insuring all construction services under this contract are in accordance with (IAW) the terms and conditions outlined in the Basic Ordering Agreement (BOA); And conform to all specifications including but not limited to appropriate UFCs, UFGS, NFPA, TAFB Standards, TAFB Specifications, the overarching BOA Statement of Work (SOW), and Order SOW. As prescribed by FAR 36.204 and DFARS 236.204 the magnitude of construction for this project is estimated between $1,000,000 and $5,000,000.