About this file
Additional Q As and SubCLIN description changes
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit_2_PSpec.docx | DOCX document | |
| Amendment0004.docx | DOCX document | |
| Amendment0003.docx | DOCX document | |
| Exhibit_2_PSpec_5_24_2016.docx | DOCX document | |
| Amendment_0001.docx | DOCX document | |
| RFP.docx | DOCX document | |
| Exhibit_2_PSpec_5_2_2016.docx | DOCX document | |
| Exhibit_3_-_CDRLs.docx | DOCX document | |
| Exhibit_4_Past_Performance_Quest.rtf | RTF text file | |
| Exhibit_1_Final_SOW_4_29_2016.docx | DOCX document | |
| QA_Amendment0001.docx | DOCX document | |
| RFP.docx | DOCX document | |
| Attachment_4_Past_Performance_Questionnaire.rtf | RTF text file | |
| Attachment_3_CDRLs.docx | DOCX document | |
| Attachment_2_Final_ABC_Pspec.docx | DOCX document | |
| Attachment_1-final_ABC_SOW.docx | DOCX document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
M67854-16-R-5009
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
ADDITIONAL QUESTION & ANSWERS
Solicitation M67854-16-R-5009 Q&A Advanced Battery Charger (ABC)
Q1. In order to accurately estimate shipping costs, can you please provide the actual addresses for the 5 cities listed in Section F - Deliveries or Performance?
A1. The Government does not have the exact addresses in the cities at this time.
Q2. CLIN 0003AD name description calls the BB-287A/U Adapter, we believe it should read BB-2847A/U Adapter. Please confirm?
A2. It should read BB-2847A/U. The RFP will be changed to reflect this correction
Q3. Section F - Deliveries of Performance in the RFP states "Thereafter, the ABC systems and associated adapters shall be delivered at a production rate of 150 per month with delivery schedule specified on each individual delivery order". Does the 150 per month for the "associated adapters" actually refer to the complete Common Adapter Kits (Common Adapter Case plus Common Adapters) or just the individually priced adapters?
A3. The 150 "associated adapters" refers to the adapters and cases to support 150 complete Common Adapter Kits.
Q4. While reviewing the different max quantities of the common adapters for CLIN 0002AB vs the other common adapter CLINs, we're trying to determine how many of each will be the minimum quantity necessary to meet the Performance Specification and how they will be packed in the common adapter kit case. Do you anticipate the common adapters to always be ordered in equal quantities and kitted in the common adapter case at the same time?
A4. Common Adapter Kits will always be ordered as complete kits as specified in the Performance Specification. Adapters may also be ordered separate from the common adapter kit, in which case they will not be required to be packaged in the common adapter kit but may be shipped separately in bulk packaging.
The following have been deleted:
QUESTION AND ANSWERS
SECTION B - SUPPLIES OR SERVICES AND PRICES
SUBCLIN 0003AD
The CLIN description has changed from BB-287A/U Adapter to BB-2847A/U Adapter.
SUBCLIN 0203AJ
The CLIN description has changed from Conformal Wearable Battery Adapter to AN/PRC-154 Radio Battery Adapter.
The CLIN extended description has changed from:
IAW SOW & Performance Specification. POP: 24-36 months after contract award. Contract Quantity Minimum 1- Maximum 200
To:
IAW SOW & Performance Specification. POP: 24-36 months after contract award. Contract Quantity Minimum 1- Maximum 20.
SUBCLIN 0203AK
The CLIN description has changed from AAA size NiMH batteries Adapter to CR-123 Adapter.
SUBCLIN 0203AL is added as follows:
| ITEM NO |
| SUPPLIES/SERVICES |
| MAX QUANTITY |
| UNIT |
| UNIT PRICE |
| MAX AMOUNT |
0203AL
AAA size NiMH batteries Adapter
FFP
IAW SOW & Performance Specification. POP: 24-36 months after contract award. Contract Quantity Minimum 1- Maximum 200 FOB: Destination
MAX
NET AMT
SECTION E - INSPECTION AND ACCEPTANCE
The following Acceptance/Inspection Schedule was added for SUBCLIN 0203AL:
| INSPECT AT |
| INSPECT BY |
| ACCEPT AT |
| ACCEPT BY |
| Origin |
| Government |
| Destination |
| Government |
(End of Summary of Changes) image1.wmf