No.
| Reference |
| Question |
| Response |
| 57. |
| Solicitation page 73, List of Attachments |
| Does the Government intend to provide a template for Attachment 4 as stated in the List of Attachments? If not, please provide the elements the Offeror should include, such as billet number, position title, labor category, on site/off site. |
| No. The Offeror shall take their prepared Attachment 3 and populate the spreadsheet with their proposed on-site and off-site labor rates for each labor position and submit this spreadsheet as Attachment 4. |
| 58. |
| Solicitation page 106, Instructions to Offerors, First Paragraph |
| Will the Government please confirm that the first paragraph under General Proposal Preparations Instructions should be revised to four (4) volumes vice five (5) volumes? |
| Yes, the first paragraph under General Proposal Preparation Instructions will be amended to change the number of volumes to four. See Amendment 1. |
| 59. |
| Solicitation page 106, Instructions to Offerors, Table. |
| Will the Government consider allowing the Offeror to decide the best way to present their slides/presentation in Volume I without putting page limits on Sub-Factors, provided the total slide count does not exceed 50 slides and meets the submission requirements? |
| No, the slide limits will not be changed. |
| 60. |
| Solicitation page 106, Instructions to Offerors, Table. |
| Will the Government consider moving the Total Compensation Plan requirement in the table from Volume IV to Volume III to coincide with Proposal Submission Requirements (Paragraph: Factor 4 – Price, 4.1 Sub-Factor 1 - Labor Hour Rates)? |
| No, the Total Compensation Plan requirement will remain in Volume 4. See Amendment 1. |
| 61. |
| Solicitation page 107, Instructions to Offerors, Paragraph H. |
| Will the Government please confirm that paragraph H should state “No pricing information shall appear in Volumes 1, 2 or 4” since Volume 3 is the pricing Volume? |
| Yes, paragraph H will be amended. See Amendment 1. |
| 62. |
| Solicitation page 108, Instructions to Offerors, Paragraph K. |
| Will the Government please verify if (i) title page, (ii) table of contents, and (iii) list of tables and figures are required for all volumes including Volume 1? If so, are they in addition to the pages allocated for each Volume? |
| The sentence discussing the title page, table of contents and list of tables and figures will be deleted from paragraph K. See Amendment 1. |
| 63. |
| Solicitation page 110, Instructions to Offerors, Factor 1: Sub-Factor 2. |
| This Solicitation was not released as a GSA MOBIS procurement; therefore wouldn’t the use of MOBIS Labor Categories be inappropriate for Offerors to use in their proposal? Will the Government consider removing references to MOBIS Labor Categories and use Position Titles only, such as those in the attachment 3 notes (Survivability Engineer, Survivability Analyst, Level A Logistician, Level B Logistician, and Level C Logistician)? If so, will the Government provide an updated Attachment 3? |
| The Government will remove the term “MOBIS” from the labor categories listed in Attachment 3. The Government will not provide additional postion categories, except for those already listed in Attachment 3 (Survivability Engineer, Survivability Analyst, Level C Logistician, Level B Logistician, and Level A Logistician). It will be left to the offeror to propose their own labor postions or equivalent postions, in Attachment 3, that support each task area described in the General Scope SOW and Task Order One SOW. See Amendment 1. |
| 64. |
| Solicitation page 110, Instructions to Offerors, Factor 1: Sub-Factor 2. |
| Will the Government please confirm that item #2 should reference the Labor Category List (Solicitation Attachment 3) in the first and last sentences vice (Solicitation Attachment 1)? |
| Yes, the reference to Attachment 1 should be Attachment 3 and will be amended. See Amendment 1. |
| 65. |
| Solicitation page 114, Instructions to Offerors, Submission/Delivery of Proposal. |
| Will the Government define how many copies of each volume (paper and CD) the Government requests to be submitted if the Offeror plans to hand deliver their proposal? |
| The Offeror shall deliver one (1) hard copy of each volume and one CD’s or DVD’s. See Amendment 1. |
| 66. |
| Solicitation page 114, Instructions to Offerors, Proposal Submission Requirements, Factor 4, Sub-Factor 1, Item 2. |
| Will the Government provide the quantity of total compensation plans each subcontractor should provide in their sealed package? |
| Each subcontractor shall submit one copy of their Total Compensation Plan in the sealed envelope. See Amendment 1. |
| 67. |
| Solicitation page 120, Proposal Evaluation, Paragraph 3, Adjectival Ratings. |
| Will the Government please define the adjectival ratings for Factors 1, 2, 3, and their associated sub-factors, similar to what was provided in the draft RFP? |
| The adjectival ratings are in accordance with Defense Procurement and Acquisition Policy Memorandum entitled Department of Defdense Source Selection Procedures dated March 4, 2011. This memorandum can be found at http://www.acq.osd.mil/dpap/. |
| 68. |
| Solicitation, Attachment 1, MRAP IDIQ Task Order 1, throughout. |
| For those personnel located in Stafford, VA will travel to Aberdeen Test Center (ATC) at Aberdeen Proving Ground (APG), MD; Dahlgren Naval Surface Warfare Center (NSWC), Virginia; Nevada Automotive Test Center (NATC), Nevada; Army Research Lab (ARL-Adelphi, MD); Yuma Test Center (YTC), AZ; SPAWAR in Charleston, SC; US Army TACOM in Warren, MI; Marine Corps Logistics Base Albany, GA; and other various CONUS and OCONUS locations be allowable as an ODC? |
| Travel is an allowable charge to other locations other than the primary place of performance designated in a Task Order. |
| 69. |
| Solicitation, Attachment 1, MRAP IDIQ Task Order 1, paragraph 5 (Other Program Requirements) sub-paragraph c. |
| Will the government please confirm the Period of Performance stated in Attachment 1 (12 September 2012 through 11 September 2013)? With the due date of 7 September 2012 provided for proposals, it seems unlikely that this would be an accurate start date, and for pricing purposes, we would prefer to have a more accurate start date. |
| The period of performance for Task Order #1 is 28 September 2012 through 27 September 2013. Task Order #1 will be revised. See Amendment 1. |
| 70. |
| Solicitation, Attachment 1, MRAP IDIQ Task Order 1, SOW. |
| There are two paragraphs labeled 2.e., the first is titled Test and Evaluation, and the second titled International Programs. Should International Programs be titled 2.f. or 3? |
| The second paragraph 2.e. will be renumbered to paragraph f. See Amendment 1. |
| 71. |
| Solicitation, Attachment 9, DRFP Q&A, Question 41 and Answer provided to Question 17. |
| Will the government please provide the plug number referenced for travel? |
| The following figures are to be used for travel/ODC: |
CLIN 0002: $82,861 CLIN 0003: $1,101,890 CLIN 0005: $5,929
CLIN 0006: $79,056 CLIN 0008AA: $5,000 CLIN 0008AB: $3,000
CLIN 0008AC: $10,000 CLIN 0008AD: $5,000 CLIN 1002: $24,061
CLIN 1003: $320,823 CLIN 1005: $1,744 CLIN 1006: $23,259
CLIN 1008AA: $5,000 CLIN 1008AB: $3,000 CLIN 1008AC: $10,000
CLIN 1008AD: $5,000CLIN 2002: $9,146 CLIN 2003: $121,954
CLIN 2005AA: $5,000 CLIN 2005AB: $3,000 CLIN 2005AC: $10,000
CLIN 2005AD: $5,000
| 72. |
| Solicitation page 106, table which identifies the volumes and page limits. |
| Please clarify if the page limits, which is identified as xx Slides is really meant for the Oral Presentations or should it reflect xx Pages. |
| The page limits are meant for both the Oral Presentations and the written proposa to be submitted. |
| 73. |
| Solicitation page 106 and 107, table which identifies the volumes and page limits. |
| The table identifies Volume IV as the Price Volume. However, on page 107, item H reflects that no price information shall be included in Volumes I – IV. Please provide clarification. It is believed that as a result of the volumes being consolidated that this statement was missed and should actually reflect Volumes I – III. |
| See answer to question #61. |
| 74. |
| Solicitation, Attachment 4. |
| The Solicitation identifies an Attachment 4; however, Attachment 4 has not been posted. When will this Attachment be made available to the bidders? |
| See answer to question #57. |
| 75. |
| Solicitation, Attachment 3. |
| Are the labor category descriptions included in this Attachment all that are available? If not, when will the rest of the descriptions be made available to the bidders? |
| Offerors are directed to Factor1: Sub-Factor 2: Personnel Magagement. |
Offerors are given the opportunity to submit additional labor categories if necessary to achieve successful performance of any or all task areas. Any additional proposed labor categories shall be added directly to Solicitation Attachment 3 and shall include a labor category title, define responsibilities, identify minimum education level, and address minimum experience required.
| 76. |
| Ordering Period |
| Please clarify that no task order will be awarded in Option Year 2 other than at the time of Option Exercise. What shall we assume the period of performance for Task Order #1? Shall we assume a Task Order will not exceed a 12 month period of performance? |
| A Task Order may be awarded at any time after the base period is extended as a result of an option being exercised. . |
The period of performance for Task Order #1 is 28 September 2012 through 27 September 2013. Task Order #1 will be revised. See Amendment 1.
A period of performance will be specified in each Task Order which should not exceed 12 months; however, any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order.
| 77. |
| Solicitation page 114, Instructions of Offerors, Proposal Submission Requirements, Factor 4, Sub-Factor 1, Item 2. |
| In the last sentence of this section, the Government states “Offerors are instructed to inform their subcontractors are to submit their total compensation plan(s) in a separately sealed envelope directly to the Government.” However, one of our subcontractors was notified that this was not the preferred method of submission. Please advise if the guidance in the Solicitation is valid, or if the Government prefers that the subcontractors submit to the Offeror and then the Offeror submits all subcontractor sealed packages with its own proposal submission. |
| See answer to question #66. |