Q A_No.2.docx

DOCX document 16 KB Posted

Attached to
Appliances Federal contract opportunity
Solicitation number
M67400-16-T-0037
Issued by
United States Marine Corps

View the file

Other files for this federal contract opportunity

Other files attached to Appliances, newest first.
File Type Posted
Q A_No._3.docx DOCX document
M67400-16-T-0037-0003.docx DOCX document
M67400-16-T-0037-0002.docx DOCX document
M67400-16-T-0037-0001.docx DOCX document
Q A.docx DOCX document
M67400-16-T-0037.docx DOCX document
Attachment_1Room_Layout.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

M67400-16-T-0037 Appliances

Q&A No2.

Question 1: With regard to the installation.... For CLIN 0001-0006

· Will these appliances need to be delivered to a government warehouse or would these need to be installed immediately at time of delivery?

Answer: As stated on page 26 of the solicitation, Installation should be completed within 30 days of arrival. It is contractor’s responsibility to store the items untill installation.

· Do we need to provide trucks and loading/ unloading lift equipment.

Answer: Yes, You need to provide trucks and loading/ unloading lift equipment

· Is there a service elevator in the building?

Answer: Yes, there is an elevator in each building, expect for the 2 story duty building which contains 5 sleeping room

· What is the time frame for this project?

Answer: The building should be ready for installation October 2016 – November 2016