M6700421Q1027 Q and A Part 1.pdf

PDF 413 KB Posted

Attached to
Network and Cabling Projects Federal contract opportunity
Solicitation number
M6700421Q1027
Issued by
United States Marine Corps

View the file

Other files for this federal contract opportunity

Other files attached to Network and Cabling Projects, newest first.
File Type Posted
M6700421Q1027 Amendment 0002.pdf PDF
Site Visit Roster (Redacted).pdf PDF
M6700421Q1027 Q and A Part 2.pdf PDF
M6700421Q1027 Q and A Site Visit.pdf PDF
M6700421Q1027 Amendment 0001.pdf PDF
B351-24x36.pdf PDF
450_HighBayWarehouse - 1ST FLOOR - 42x30.pdf PDF
450_HighBayWarehouse - 2ND FLOOR - 42x30.pdf PDF
B-861T-24x36.pdf PDF
B-390-24x36.pdf PDF
B-361-24x36.pdf PDF
B-454-24x36.pdf PDF
M6700421Q1027.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

M6700421Q1027

Network and Cabling Projects

Questions and Answers

Part 1

1. Question: Would the Government please specify what footage is required for each CLINN?

Answer: Each person will have the opportunity to measure the areas at the site visit.

Contractors are responsible for bringing their own measuring wheels or measuring tools.

2. Question: Are floor plan drawings and drawings that show buildings available so we can calculate cable distances?

3. Question: Are there any approximate distances for the locations described in the SOW section

1.4.9 to help accurately quote a price?

4. Question: I was curious if there are any prints that are to scale so we can get the accurate footages?

Answer: Floor plan drawings for each building are posted.

5. Question: Will you sponsor a Facility clearance? Also, there seems to be a contradiction in the following statements:

1.6.6.2 Security Clearances. This contract does not require the contractor to possess a Secret

Facility Security Clearance, however all contractor personnel are subject to background checks prior to entry

4.2 Secret Facility Clearance: The contractor shall possess and maintain a SECRET security clearance from the Defense Security Service. The contractor’s employees, performing work in support of this contract shall have been granted a SECRET facility clearance from the Defense

Industrial Security Clearance Office.

Answer: Amendment 0001 to the solicitation has been issued to remove the requirement for a

Secret Facility Clearance. Section 4.2 is struck from the Performance Work Statement. Refer to the attached amendment. In addition, Contractors are not required to have a secret clearance.

The background check is required for base access.