LRWRP_Design_Report_Chapter_2.pdf

PDF 4 MB Posted

Attached to
HEADWORKS and INFLUENT METER IMPROVEMENTS PROJECT
Solicitation number
2025-RFP-015DW
Issued by
Santa Barbara County, Long Beach City, California

About this file

This is a preliminary design report for the Lompoc Regional Water Reclamation Plant (LRWRP) Upgrade Project, prepared by the City of Lompoc in California. The document details a comprehensive wastewater treatment infrastructure modernization initiative that includes headworks improvements, secondary treatment facilities, metals removal capabilities, effluent filters, ultraviolet disinfection systems, solids handling facilities, instrumentation and controls, and miscellaneous yard piping improvements. The project encompasses multiple treatment process areas designated as TM01 through TM10, with construction planned for a two-year period with an estimated completion date of May 2008. A mandatory pre-bid job walk is scheduled for May 14, 2025, with engineering proposals due by June 30, 2025, at 3:00 pm, and all proposals remaining valid for 90 calendar days after bid opening.

The anticipated construction bid price for the project is $41,836,000, with an additional $6,000,000 allocation for engineering and construction management services, bringing the total project cost to $47,836,000. This represents a 24 percent cost reduction compared to the September 2002 Master Plan alternative, yielding potential savings of approximately $15 million. The cost estimate includes labor at 3.75 percent, materials and subcontractors at 83.15 percent, with additional provisions for markups, escalation to mid-point construction, contractor general conditions, construction contingency, insurance coverage, and performance bonds. The project builds upon previous master planning efforts and is part of a phased modernization approach for the facility, which currently serves approximately 9,000 sewer connections with an average dry weather flow capacity of 5.0 MGD. Compensation for the selected consulting firm will be based on approved actual time and materials costs not to exceed the agreed-upon fee, with progress-based payments contingent upon task completion.

View the file

Other files

File Type Posted
LRWRP_Design_Report_Chapter_10.pdf PDF
LRWRP_Design_Report_Chapter_8.pdf PDF
LRWRP_Design_Report_Chapter_3.pdf PDF
LRWRP_Design_Report_Chapter_7.pdf PDF
LRWRP_Design_Report_Chapter_8.pdf PDF
LRWRP_Design_Report_Chapter_9.pdf PDF
LRWRP_Design_Report_Chapter_3.pdf PDF
LRWRP_Design_Report_Chapter_4.pdf PDF
LRWRP_Design_Report_TOC.pdf PDF
LRWRP_Design_Report_Cover_Page.pdf PDF
Lompoc_Salts_Mgt_Plan_010611.pdf PDF
LRWRP_Design_Report_Chapter_3.pdf PDF
LRWRP_Design_Report_Chapter_4.pdf PDF
LRWRP_Design_Report_Chapter_5.pdf PDF
LRWRP_Design_Report_TOC.pdf PDF
LRWRP_Design_Report_Chapter_9.pdf PDF
LRWRP_Design_Report_Cover_Page.pdf PDF
Lompoc_Salts_Mgt_Plan_010611.pdf PDF
LRWRP_Design_Report_Chapter_10.pdf PDF
LRWRP_Design_Report_Appendix_D.pdf PDF
LRWRP_Design_Report_Appendix_E.pdf PDF
LRWRP_Design_Report_Appendix_A.pdf PDF
LRWRP_Design_Report_Chapter_1.pdf PDF
Vol.II_Appendices.pdf PDF
LRWRP_Design_Report_Appendix_D.pdf PDF
LRWRP_Design_Report_Chapter_1.pdf PDF
Lompoc_Wastewater_Master_Plan_Volume_II_-_Appendices.pdf PDF
Vol.II_Appendices.pdf PDF
LRWRP_Design_Report_Chapter_1.pdf PDF
LRWRP_Design_Report_Chapter_2.pdf PDF
Lompoc_Wastewater_Master_Plan_Volume_I_-_Report.pdf PDF
LRWRP_Design_Report_Appendix_F.pdf PDF
LRWRP_Design_Report_Chapter_2.pdf PDF
Vol.I_MasterPlan.pdf PDF
LRWRP_Design_Report_Appendix_F.pdf PDF
Vol.I_MasterPlan.pdf PDF
LRWRP_Design_Report_Appendix_A.pdf PDF
LRWRP_Design_Report_Appendix_C.pdf PDF
LRWRP_Design_Report_Appendix_F.pdf PDF
Lompoc_Wastewater_Master_Plan.pdf PDF
Lompoc_Wastewater_Master_Plan_Volume_III_-_Executive_Summary.pdf PDF
LRWRP_Design_Report_Appendix_B.pdf PDF
LRWRP_Design_Report_Appendix_C.pdf PDF
LRWRP_Design_Report_Appendix_D.pdf PDF
LRWRP_Design_Report_Appendix_E.pdf PDF
Consultant_Services_Agreement_2025.doc DOC document
Consultant_Services_Agreement_2025.doc DOC document
Consultant_Services_Agreement_2025.doc DOC document
INDEMNITY_AND_INSURANCE_REQUIREMENTS.docx DOCX document
INDEMNITY_AND_INSURANCE_REQUIREMENTS.docx DOCX document
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CHAPTER 2

PROJECT COST AND SCHEDULE

Preliminary Estimate of Probable Construction Cost

Table 2.1-1 presents a preliminary estimate of the probable construction cost for the LRWRP Upgrade Project. At this time, the anticipated bid price is $41,836,000.

Table 2.1-1. Preliminary Estimate of Probable Construction Cost

Category Percent Amount, $ Labor 3.75% 1,001,430 Material Subcontractor Equipment o h e r 83.15% 22,178,815 Net Costs 26,672,801

Labor Mark-up Material Mark-up Subcontractor Mark-up Equipment Mark-up Sales tax (material) Sales tax (equipment) Building Permits hiaterial Shipping & Handling Worker's Travel/Subsistence Subtotal

Escalation to midpoint Labor Escalation to midpoint Material Escalation to midpoint Subs, equip. 8.71% 2,018,332 Subtotal 2,323,202

Contractor General Conditions Start-up, training, 08ch.I Subtotal Construction Contingency Subtotal Earthquake Insurance Bldg Risk, Liability Auto Ins.

Subtotal Performance Bond Payment Bond 1 .0O0/o 3011802 Subtotal 11,655,587

Total Estimate

P:\-l'rolects\126517 - LOWOC\\XP\Project-Report\1033979 Preliminary D e s i p Report Final.doc February 2005

Project Cost and Schedule 2-2 r Table 2.1-2 presents a summary breakdown of the anticipated bid price by process area. A detailed breakdown of the anticipated bid price by process area and the basis of the estimate are included in Appendix B.

Table 2.1-2. Summary Breakdown of Anticipated Bid Price by Process Area

Item

TMOl

TM02

TM03

'I'M04

TM05

TM06

TM07

'TM09

TMlO

Headworks Improvements (Alt "B") Secondary Treatment Facilities Metals Removal Facilities Effluent Filters Ultraviolet Disinfection Solids Handling Facilities (Base Option) Instrumentation and Controls Miscellaneous Improvements/Boiler Allowances Yard Piping

Grand Total

Total

Recommended Project Cost

The cost of the recommended project includes the construction cost and an allowance of $6,000,000 for engineering and construction management. The total project cost therefore, is $47,836,000 as summarized below:

Anticipated Bid Price:

Engineering & Construction Management Costs:

Project Cost

Cost Comparison

Table 2.3-1 presents a comparison of the cost of the project recommended in this report with the cost of the project recommended in the September 2002 Master Plan.

P:\-Projects\126517 - LOhPOC\\XP\Project-Report\Iil33979 Preliminar). Desgn Report Find.doc February 2005

Project Cost and Schedule 2-3

Table 2.3-1. Cost Comparison

Recommended Master Plan Description Project Cost, 9/2002 (ENR: 6589) ENR Adjustment, 12/2004 (ENR: 7312) Project Cost at mid-construction point, 5/2007

Station. Slud~e Lapoons and Dred~e) I 1

(8.71 '10 escalation projected by ENR) Additional Improvements (Influent Pumping

Project ($)

N/A N/A

47,836,000

The project recommended in this report can be constructed for 24 percent less than the project recommended in the Master Plan. This represents a potential savings of about $1 5 million.

9/2002 ($) 50,279,333 55,796,400 60,656,000

Included Above ppppp --

Project Cost

Project Schedule

2,000,000

The project schedule for the design and construction of the L R W Upgrade Project is included in Chapter 2. This schedule is slightly modified to reflect changes in scope of work since June 23, 2004. This schedule still assumes construction period of two years. The project completion date has been moved from April to May 2008.

47,836,000

I?\-l'rojects\l26517 - LOhfl'OC\\T'P\Project~RePort\1Il.33979 Preliminary Design Report Finaldoc

62,656,000

February 2005

File details come from the government source that posted it. Updated .