Liquidated Damages signed.pdf
PDF 126 KB Posted
- Solicitation number
- 36C24425R0006
About this file
This document is a Liquidated Damages Formulation Memo related to Solicitation Number 36C24425R0006 to Replace Building 37 Multi-Stack Heat Pump at the Lebanon VA Medical Center.
The memo outlines the estimated liquidated damages for VISN 4 Contracting, Engineering, and Legal reviews as well as Facility Engineering in the event of inexcusable delay, totaling $605.92 per calendar day. The purpose of the liquidated damages is compensatory, and the government retains the right to seek actual damages. The formulation of the liquidated damages is in accordance with FAR 36.206. The solicitation requires design-build services to replace the failing multi-stack heat pumps in Building 37, including replacing piping, wiring, controls, and installing new heat pumps on a concrete pad. The project schedule requires design submittals and construction completion within 280 days of the notice to proceed. The solicitation also includes requirements for site investigations, construction period services, and project phasing to minimize impacts to the medical center operations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24425R0006 0002.docx | DOCX document | |
| EXHIBIT E Past Performance Questionnaire.docx | DOCX document | |
| Site Visit Sign In Sheet.pdf | ||
| P07 SCA2015-4231 7.22.24 reupload.pdf | ||
| 36C24425R0006 0001.docx | DOCX document | |
| P07 SCA2015-4231 7.22.24.pdf | ||
| 013526 Lebanon Safety Requirements Spec 20240516.docx | DOCX document | |
| 010000 Lebanon General Requirements Spec.docx | DOCX document | |
| P07 PA20240093 7.19.24.pdf | ||
| SOW - 595-25-102 Replace Multi-Stack Building 37 - DB.docx | DOCX document | |
| HVAC Controls - J and A Distech Controls signed redacted.pdf | ||
| 230923 HVAC Controls Specification.docx | DOCX document | |
| 36C24425R0006_1.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Liquidation Damages Formulation Memo
Solicitation Number: 36C24425R0006
Replace Building 37 Multi-Stack Heat Pump
All Civilian wage rates are based upon the General Schedule Locality Pay Table (Pittsburgh-New Castle-
Weirton, PA-OH-WV) effective January 1, 2024 for Contracting and Project Engineer and FMS Manager.
1. Estimated liquidated damages for VISN 4 Contracting, Engineering, and Legal reviews per day of inexcusable delay:
CLASSIFICATION GRADE RATE HOURS TOTAL HOURLY RATE
Contracting Officer
Supervisor GS-14 / 5 $68.83 1 Hours $68.83
Contract Specialist
GS-13 / 5
GS-011 / 1
$58.25
$36.06
1 Hour
4 Hours
$58.25
$144.25
Legal Officer GS-14 / 4 $66.81 1 Hour $66.81
TOTAL PER
DAY
$338.14
2. Estimated liquidated damages for Facility Engineering (COR/COTR) per day of inexcusable delay:
CLASSIFICATION GRADE RATE HOURS TOTAL HOURLY RATE
Construction Manager GS-13 / 5 $58.25 2 Hours $116.50
Project Engineer GS-12 / 6 $50.42 3 Hours $151.28
TOTAL PER DAY
$267.78
Grand Total Per Day $ 605.92
3. The Contractor shall pay liquidated damages to the Government in the amount of $605.92 for each calendar day of delay until the work is completed or accepted. The aforementioned costs were derived based upon historical trends associated with the time required of the parties to perform the additional contract administration which has not been completed by the Contractor within the specified time. The purpose of Liquidated Damages is compensatory only. The government retains the right to seek actual damages so far as they are distinguishable and separate from the Contractor failing to complete the work within the time specified in the contract.
4. The formulation of Liquidated Damages as detailed above are in accordance with Federal Acquisition
Regulation 36.206 and will be assessed for each calendar day required to complete the construction work on this project past the scheduled completion date.
Elijah McIntosh
| 2024-10-21T11:41:49-0400 | |
| ELIJAH MCINTOSH |
File details come from the government source that posted it. Updated .