This is an Invitation for Bid (IFB) document prepared by RRMM Architects on behalf of Lunenburg County Public Schools for construction of a baseball field at Lunenburg Middle School located at 583 Tomlinson Road, Victoria, Virginia. The project encompasses excavation, earthwork preparation including infield dirt and grass seed, fencing, dugouts, concrete walkways, bleachers, and utilities for future concessions and scoreboard installations. A non-mandatory pre-bid conference is scheduled for Wednesday, March 25, 2026, at 3:30 p.m. at the project site, with bidders encouraged to attend. Sealed bids must be submitted to Paul Caley, Director of Facilities, by 2:00 p.m. on Thursday, April 16, 2026, at the School Board Office in Kenbridge, Virginia. The last day for submitting pre-bid questions is 5:00 p.m. on April 2, 2026, directed to Jeff Harris at RRMM Architects. Substantial completion is required by October 1, 2026, with final completion by November 6, 2026. Work shall commence within ten working days of contract execution or the Notice-to-Proceed.
Bids are submitted on a lump-sum basis with a required bid bond of five percent of the total bid amount. The successful bidder must furnish performance and payment bonds each equal to 100 percent of the contract price. Retainage is set at five percent of earned amounts until 50 percent of contract value is reached, after which retainage may be reduced per general conditions. Monthly progress payments of 95 percent of earned labor and materials are made after certification by the Architect, with the final five percent retained. Liquidated damages are assessed at $500.00 per calendar day for failure to achieve the final completion date, though time extensions may be granted for abnormal inclement weather or supply chain delays upon proper documentation. One bid alternate is offered for installation of a 4-foot chain link fence around the perimeter, and a $15,000 contingency allowance is included for unforeseen conditions. Construction documents are available electronically through eVA—Virginia's eProcurement Marketplace beginning March 20, 2026. Bidders are required to register as Virginia contractors and comply with nondiscrimination and drug-free workplace requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| LCPS MS BASEBALL Drawings.pdf | ||
| 000100 - IFB LMS Baseball.pdf | ||
| State Law Addendum.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
LUNENBURG
COUNTY
PUBLIC
SCHOOLS
LUNENBURG MIDDLE SCHOOL
BASEBALL FIELD
VOLUME 1 OF 1
PREPARED BY
RRMM ARCHITECTS
ARCHITECTURE ■ PLANNING ■ INTERIORS
CHESAPEAKE, VIRGINIA
NITSCH ENGINEERING
CIVIL CONSULTANT
RICHMOND, VIRGINIA
THOMPSON CONSULTING ENGINEERS
PLUMBING ■ MECHANICAL ■ ELECTRICAL CONSULTANT
NEWPORT NEWS, VIRGINIA
MARCH 20, 2026
THIS PAGE INTENTIONALLY LEFT BLANK
LUNENBURG MIDDLE SCHOOL BASEBALL FIELD
LUNENBURG COUNTY PUBLIC SCHOOLS RRMM PROJECT NO. 24132-02
PROJECT DIRECTORY 1
PROJECT DIRECTORY
OWNER: Lunenburg County Public Schools 1009 Main Street Kenbridge, VA 23944 Phone: (434) 676-2467 Fax: (434) 676-1000 Owner’s Representative: Paul Caley
ARCHITECT: RRMM Architects 1317 Executive Boulevard, Suite 200 Chesapeake, Virginia 23320 Project Manager: Jeff Harris, Architect Phone: (757) 622-2828 Fax: (757) 622-2430 E-Mail: jharris@rrmm.com
CIVIL ENGINEER: Nitsch Engineering, Inc.
1700 Summit Ave, Suite 100
Richmond, VA 23230 Project Manager: Kellen Johnson Phone: (804) 781-3083 E-Mail: kjohnson@nitscheng.com
PLUMBING, MECHANICAL, Thompson Consulting Engineers ELECTRICAL ENGINEER: 4411 Cox Road Glen Allen, VA 23060
Project Manager: Keith Dignan Phone: (804) 373-5052 E-mail: kdignan@tceva.com
END OF SECTION 000002
mailto:jharris@rrmm.com
PROJECT DIRECTORY 2
TABLE OF CONTENTS 000005 - 1
TABLE OF CONTENTS
VOLUME 1/1
BIDDING INFORMATION
GENERAL CONDITIONS AND FORMS
000002 PROJECT DIRECTORY
000005 TABLE OF CONTENTS
000100 IFB 26-LMS INVITATION FOR BID
000200 INSTRUCTION TO BIDDERS
000300 BID FORM
A310 BID BOND (AIA DOCUMENT A310)
000500 SAMPLE AGREEMENT
A201 GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION
(AIA DOCUMENT A201)
000800 SUPPLEMENTAL CONDITIONS
A305 CONTRACTOR’S QUALIFICATION STATEMENT
(AIA DOCUMENT A305) and EXHIBITS A-E
000860 PRE-BID QUESTION FORM
SPECIFICATIONS
DIVISION 1 - GENERAL REQUIREMENTS
011000 SUMMARY
012100 ALLOWANCES
012300 ALTERNATES
012500 SUBSTITUTION PROCEDURES
012600 CONTRACT MODIFICATIONS PROCEDURES
012900 PAYMENT PROCEDURES
013100 PROJECT MANAGEMENT AND COORDINATION
013200 CONSTRUCTION PROGRESS DOCUMENTATION
013300 SUBMITTAL PROCEDURES
014000 QUALITY REQUIREMENTS
014100 SPECIAL INSPECTIONS
014200 REFERENCES
015000 TEMPORARY FACILITIES AND CONTROLS
016000 PRODUCT REQUIREMENTS
017300 EXECUTION
017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
017700 CLOSEOUT PROCEDURES
017823 OPERATION AND MAINTENANCE DATA
017839 PROJECT RECORD DOCUMENTS
TABLE OF CONTENTS 000005 - 2
DIVISION 2 – EXISTING CONDITIONS
THIS DIVISION NOT USED
DIVISION 3 - CONCRETE
THIS DIVISION NOT USED
DIVISION 4 – MASONRY
THIS DIVISION NOT USED
DIVISION 5 - METALS
THIS DIVISION NOT USED
DIVISION 6 - WOOD AND PLASTIC
THIS DIVISION NOT USED
DIVISION 7 - THERMAL AND MOISTURE PROTECTION
THIS DIVISION NOT USED
DIVISION 8 - DOORS AND WINDOWS
THIS DIVISION NOT USED
DIVISION 9 - FINISHES
THIS DIVISION NOT USED
DIVISION 10 - SPECIALTIES
THIS DIVISION NOT USED
DIVISION 11 - EQUIPMENT
THIS DIVISION NOT USED
TABLE OF CONTENTS 000005 - 3
DIVISION 12 - FURNISHINGS
THIS DIVISION NOT USED
DIVISION 13 - SPECIAL CONSTRUCTION
THIS DIVISION NOT USED
DIVISION 14 - CONVEYING SYSTEMS
THIS DIVISION NOT USED
DIVISION 21 – FIRE PROTECTION
THIS DIVISION NOT USED
DIVISION 22 – PLUMBING
THIS DIVISION NOT USED
DIVISION 23 – HEATING, VENTILATING AND AIR CONDITIONING
THIS DIVISION NOT USED
DIVISION 25 – AUTOMATION SYSTEM COMMISSIONING
THIS DIVISION NOT USED
DIVISION 26 – ELECTRICAL
THIS DIVISION NOT USED
DIVISION 27 – COMMUNICATION EQUIPMENT
THIS DIVISION NOT USED
DIVISION 28 – SECURITY SYSTEMS
THIS DIVISION NOT USED
DIVISION 31 – EARTHWORK
311000 SITE CLEARING
312000 EARTHWORK
TABLE OF CONTENTS 000005 - 4
DIVISION 32 – EXTERIOR IMPROVEMENTS
320523 CEMENT AND CONCRETE FOR EXTERIOR IMPROVEMENTS
321216 ASPHALT PAVING
DIVISION 33 – UTILITIES
331010 WATER UTILITIES
333000 SANITARY SEWERAGE UTILITIES
334000 STORMWATER DRAINAGE UTILITIES
END OF TABLE OF CONTENTS
INVITATION TO BID ITB - 1
INVITATION TO BID # 26-LMS
Date: March 20, 2026
Owner: Lunenburg County School Board
User: Lunenburg County Public Schools
Architect: RRMM Architects
Project: Lunenburg Middle School Baseball Field
Lunenburg County Public Schools Bid #26-LMS
Lunenburg County Public Schools is soliciting lump sum, sealed bids for the Lunenburg Middle
School Baseball Field Project. The project is located at 583 Tomlinson Rd, Victoria, Virginia 23974.
The project scope of work encompasses excavation, earthwork preparation of the baseball field including infield dirt and grass seed, fencing, dugouts, concrete walkways, bleachers, and utilities for future concessions and scoreboard installations.
All bids must be submitted in a sealed envelope or package clearly marked “Bid #26 - LMS
Lunenburg Middle School Baseball Field”, including the due date and time. All bids shall be received in the School Board Office, on or before 2:00 PM., Thursday, April 16, 2026 and delivered to:
Paul Caley
Director of Facilities
Lunenburg County Public Schools
1009 Main Street
Kenbridge, VA 23944
Bids shall be publicly opened and read aloud at the above stated date, time and location. Any bid received after the time designated above will be returned unopened.
Any award resulting from this solicitation will be issued to the successful offeror in writing and will be posted on eVA - Virginia's eProcurement Marketplace and the Lunenburg County School
Board’s website.
A non-mandatory Pre-Bid Conference will be held on Wednesday, March 25, 2026, at 3:30pm at the project site. Bidders are encouraged to attend.
A bid bond is required. Procedures for submitting a bid, claiming an error, withdrawal of bids, and other pertinent information are contained in the contract documents. The procedure for withdrawal of bids shall be in accordance with the Instructions to Bidders and Section 2.2-4330, Code of Virginia.
Bidders shall be required to comply with the provisions of Section 2.2-4311, Code of Virginia, in regard to nondiscrimination in employment. The owner reserves the right to reject any or all bids.
This procurement is being conducted in compliance and under the laws found in the Virginia Public
Procurement Act. Any mention of brand names is to denote the quality in which the public body is looking to obtain. Substitutions will be allowed with pre-authorization.
https://eva.virginia.gov/index.html
INVITATION TO BID ITB - 2
The last day to submit pre-bid questions shall be 5:00 PM on April 2, 2026.
Questions, in writing, may be directed to: Jeff Harris of RRMM Architects at 1317 Executive Boulevard, Suite 200, Chesapeake, Virginia 23320, Phone (757) 622-2828, Email:
jharris@rrmm.com with a copy to Paul Caley at paul.caley@k12lcps.org.
Construction Documents, including Project Specifications and Drawings, will be available electronically for download beginning March 20, 2026 from: eVA - Virginia's eProcurement
Marketplace
Bidder's attention is directed to the requirements of Title 54, Chapter 7, of the Code of Virginia pertaining to registration of Contractors. Lunenburg County Public Schools is an Equal Opportunity
Employer
END OF INVITATION TO BID
mailto:paul.caley@k12lcps.org
INSTRUCTIONS TO BIDDERS 000200 - 1
SECTION 000213 - INSTRUCTIONS TO BIDDERS
1. DRAWINGS AND SPECIFICATIONS:
Construction Documents, including Project Specifications and Drawings, will be available electronically for download beginning March 20, 2026 from: eVA - Virginia's eProcurement
Marketplace. Should the specifications of conditions fail to exist in this document, the Code of
Virginia shall dictate those terms.
2. BIDS:
Before submitting a bid, each bidder shall carefully examine the drawings, specifications and other Contract Documents; read and understand the bidding documents and his bid; shall visit the site of the work; shall fully inform himself as to all existing conditions and limitations; and shall include in the bid the cost of all labor, supervision, items, materials, systems, and equipment described and included in the Contract Documents without exceptions.
3. CONTRACT AND BONDS
Each bid shall be accompanied by a bid security in the form of a Bid Bond, a cashier’s check, or a certified check in the amount of five percent (5%) of the total bid, made payable to the Lunenburg
County School Board. This Bid Bond, cashier’s check, or certified check pledges that the bidder will enter into a Contract with the Owner on the terms stated in the Bid and will furnish bonds covering faithful performance of the Contract and payment of all obligations arising there under.
Should the bidder refuse to enter into such a Contract or fail to furnish such bonds, the amount of the bid security shall be forfeited to the Owner as liquidated damages, not as a penalty.
Surety Bonds shall be written on AIA Document A310, Bid Bond, and the attorney-in-fact who executes the bond on behalf of the surety shall affix to the bond a certified and current copy of the power of attorney.
All bonds shall be written by sureties or insurance companies licensed to do business in the
Commonwealth of Virginia. Other bid bond forms will be acceptable if in the same format as
AIA Document A310, Bid Bond.
The Contract agreement will be on a form similar to that which is bound in the specifications. The completion date of construction shall be as indicated in the bid document. The successful bidder, simultaneously with the execution of the Contract agreement, shall be required to furnish a performance bond and a payment bond in an amount equal to one hundred percent (100%) of the
Contract price, said bonds shall be secured from a surety company licensed to do business in the
Commonwealth of Virginia and acceptable to the Suffolk City School Board.
4. QUALIFICATION OF CONTRACTORS
The apparent lowest bidder shall deliver to the Owner within seventy-two (72) hours (not including Saturday, Sunday, or State Holidays) from the initial submission for bids, for review, a completed Contractors Qualification Statement using AIA Document A305, 2020 Edition and associated Exhibits A-E (copies are included after the Supplementary General Conditions).
INSTRUCTIONS TO BIDDERS 000200 - 2
Bidders are required to submit with the bid evidence of proper and current certificates of contractors’ registration in Virginia.
5. LISTING OF SUBCONTRACTORS
The experience and responsibility of subcontractors may have bearing on the choice of a contractor by the Owner.
If required by the Owner, the apparent two low bidders for each project, shall deliver to the
Owner within seventy-two (72) hours (not including Saturday, Sunday or State Holidays) for review the following information:
a. Provide a list of the work to be performed by the bidder with his own forces.
b. Provide the proprietary names and the suppliers of the principal parts (items, systems, materials, and equipment) proposed for the work.
c. Provide a list of the names of the subcontractors to be employed for each of the principal parts of the work, copies of their agreements, and their corresponding dollar amounts.
d. Provide a list of references and/or past projects for individual subcontractors performing a principal part of the work. This requirement applies to subcontractors at any tier.
Principal part shall mean a subcontract dollar value in excess of $10,000.00.
The bidder will be required to establish the reliability and responsibility of the proposed subcontractors, manufactures, and suppliers who shall furnish and perform the work described in the specifications to the satisfaction of the Architect and the Owner.
These lists shall be binding upon the Contractor; however, the Owner has the right to reject any or all subcontractors which the Architect and the Owner determines to be unqualified to do the work. Owner may withhold awarding a contract to any particular bidder if the Owner considers one or more of the proposed contractors to be unqualified.
6. INTERPRETATIONS OF PLANS AND SPECIFICATIONS
If any person contemplating the submission of a bid for the proposed Contract is in doubt as to the true meaning of any part of the drawings, specifications or other proposed contract documents, he/she may submit a written request to RRMM Architects, Attention: Melanie
Weatherford, 1317 Executive Blvd, Suite 200, Chesapeake, VA, 23320; telephone number (757)
622-2828. The request must be submitted on the project Pre-Bid question form and e-mailed to all of the addresses indicated on the form. The Pre-Bid Question Form is included after the Supplementary General Conditions for use by bidders when submitting questions.
Questions submitted in any other format will not receive a response. Requests must be in writing and received no later than seven (7) working days prior to the date of the bid opening, for an interpretation thereof. The person submitting the request will be responsible for its prompt delivery. Any interpretation of the proposed documents will be made only by addendum. The
Owner and the Architect will not be responsible for any other explanations or interpretations of the proposed documents.
INSTRUCTIONS TO BIDDERS 000200 - 3
7. ADDENDA OR BULLETINS
Addenda or bulletins will be issued on the eVA - Virginia's eProcurement Marketplace. Any addendum or bulletin issued during the time of bidding shall become part of the documents provided to the bidders for the preparation of the bid, shall be covered in the bid, and shall be made a part of the Contract. No addenda will be issued later than four (4) days prior to the date for receipt of bids except an addendum, if necessary, postponing the date for receipt of bids or withdrawing the request for bids. Awards shall be posted at the school division’s office and on the school division website.
8. RIGHT TO NEGOTIATE
The Owner reserves the right to negotiate with the lowest responsive and responsible Bidder(s) to obtain a Contract price with funds available to the Owner whenever such low bid exceeds the
Owner’s availability of funds for the work.
9. AWARD OF CONTRACT
The Owner intends to award this contract in writing to the lowest responsive and responsible bidder(s) provided the bids have been submitted in accordance with the requirements of the bid and contract documents, Virginia procurement regulations, is judged to be reasonable, and does not exceed the funds available. The Notice of Award(s) will be posted on eVA - Virginia's eProcurement Marketplace and the Lunenburg County School Board’s website.
The Owner reserves the right to award the project based on the lowest responsible Base Bid received and any combination of alternates thereof and, that the Owner determines to be in the best interest of the Owner.
The Owner reserves the right to waive any informality in any bid or in the bidding. The accepted bidder(s) shall assist and cooperate with the Owner in preparing a formal Contract Agreement and within five (5) days following its presentation shall sign and deliver four (4) complete sets of
Contract Agreement documents to the Owner, including but not limited to: the Agreement, the
Performance Bond, Payment Bond, Hold Harmless Agreement, and all necessary Certificates of
Insurance.
The successful bidder(s), upon failure or refusal to enter in the Contract and/or to furnish the required Performance Bond, Payment Bond, and other required documents within the time specified, shall pay to the Owner as liquidated damages, an amount equal to the bid guarantee deposited with the bid or a portion thereof equal to the difference between the bid security and the next highest acceptable bid.
10. TIME IS OF THE ESSENCE
Time is of the essence for this Contract.
11. RESPONSIBLE BIDDER
The Owner reserves the right to award each individual school project based on the lowest responsible Base Bid received or any combination thereof and, that the Owner determines to be in the best interest of the Owner. In determining the “lowest responsible bidder(s)” Lunenburg
County Schools may consider the following:
https://eva.virginia.gov/index.html
INSTRUCTIONS TO BIDDERS 000200 - 4
a. Past performances of the contractor and subcontractors that indicate their ability to complete this project (includes organization, equipment available and any other indicators).
b. Whether the bidder can perform the contract or provide the service promptly, or within the time specified, without delay.
c. Quality of products used and adherence to bid specifications.
d. The sufficiency of financial resources and the ability of bidder to perform the contract.
e. The previous and existing compliance by the bidder with laws and ordinances.
f. The quality of performance of previous contracts or services.
In addition, the Owner reserves the right to reject any or all bids or to negotiate with the low bidder(s) in the case of insufficient funds.
12. COST BREAKDOWN
The Contractor shall, before starting his work, submit to the Owner and Architect the cost of various segments of the work according to construction activity, the total amount equaling the
Contract price. This breakdown shall be used as the basis for the payment of estimates as stated in the Contract Documents.
13. RIGHT TO REJECT BIDS
The Owner reserves the right to reject any or all bids, in whole or in part; to waive informalities;
and/or to delete items prior to making an award; whenever it may be deemed by the Owner to be in their best interest.
14. BID BOND OR CHECKS OF SUCCESSFUL BIDDERS
Bid Bond or Checks submitted by the successful bidder will be returned upon acceptance of the
100% performance bond and separate 100% payment bond. Checks from other bidders, not previously forfeited, will be returned as soon as it is determined that the bids represented by the checks will receive no further consideration by the Owner.
15. REVISIONS TO BID
Handwritten or typed notes on the envelope containing the bid will not be accepted as authorized modifications to the Bid Form included herein. The bid amount indicated on the Bid Form will be the only data considered.
16. WITHDRAWAL OF BIDS
Bids may be withdrawn by written or telegraphic request received from bidders prior to the time fixed for the bid opening. Telegraphic requests must be received by the Owner in written form before the bid opening. Negligence on the part of the bidder in preparing the bid confers no right for the withdrawal of the bid after it has been opened except as permitted in Section 2.2-4330 of the Code of Virginia as outlined below.
A bidder may withdraw his bid from consideration if the price bid was substantially lower than the other bids due solely to a mistake in the bid, provided the bid was submitted in good faith, and the mistake was a clerical mistake as opposed to a judgment mistake, and was actually due to an unintentional arithmetic error or an unintentional omission of a quantity of work, labor or
INSTRUCTIONS TO BIDDERS 000200 - 5
material made directly in the compilation of a bid, whereby the unintentional arithmetic error or unintentional omission can be clearly shown by objective evidence drawn from inspection of original work papers, documents and materials used in the preparation of the bid sought to be withdrawn.
The bidder must give notice in writing of his claim of right to withdraw his bid within two (2) business days after the conclusion of the bid opening procedure. This notice to the Owner must be accompanied with his original work papers, documents, and materials used in the preparation of the bid. Such work papers shall be delivered to the Owner by the bidder in person or by registered mail.
Such mistake shall be proved only from the original work papers, documents, and materials delivered to the Owner as required herein.
Failure of bidder to submit his original work papers, documents, and materials used in the preparations of this bid at the time, date and place required, shall constitute a waiver of bidders’ right to claim a mistake in his bid.
No bid shall be withdrawn under this section when the result would be the awarding of the
Contract on another bid of the same bidder.
No bidder who is permitted to withdraw a bid shall for compensation, supply any material or labor to or perform any subcontract or other work agreement for the person or firm to whom the
Contract is awarded or otherwise benefit directly or indirectly from the performance of the
Project for which the withdrawn bid was submitted.
If the bid is withdrawn under authority of this section, the next lowest responsive and responsible bidder shall be deemed to be the low bidder on the Project.
When the procedure set forth in the paragraphs above is utilized, original work papers, documents, and materials used in the preparation of the bid must be submitted in an envelope or package separate and apart from the envelope containing the bid marked clearly as to the contents.
END OF INSTRUCTIONS TO BIDDERS
INSTRUCTIONS TO BIDDERS 000200 - 6
BID FORM BF - 1
26-LMS LUNENBURG MIDDLE SCHOOL BASEBALL FIELD
BID FORM
This bid is for the Lunenburg Middle School Baseball Field for Lunenburg County Public Schools, Kenbridge, VA
Each bidder shall submit their bid on this form. Submit one (1) copies of this form completed and with original signatures.
To: Paul Caley
Director of Facilities
Lunenburg County Public Schools
From: ______________________________________________________ (Name)
(Address)
Having carefully examined the bid documents including the Invitation to Bid, Instructions to Bidders, Specifications, Drawings, Terms of Agreement and Addenda (if any) prepared by the architect, entitled:
Lunenburg Middle School Baseball Field as well as the premises and conditions affecting the work, the undersigned proposes to furnish all labor, supervision, materials, equipment, and services necessary to perform all the work in accordance with the contract documents for the following lump sum amount.
The Owner will consider any request made by the Contractor to extend the Contractor’s time for performance of the work and may grant reasonable time extensions when delays in the
Contractor’s work performance are directly caused by supply chain delays, if the Contractor has provided the Owner with (i) reasonable notice in advance that its work is being impacted by supply chain delays; (ii) adequate verification to support the Contractor’s claim; and (iii) written certification that any delay in its performance of this Contract is beyond the
Contractor’s control and not the result of actions or any failure to act by the Contractor.
BASE BID
The Lump Sum Base Bid price for the entire work in this package, including any allowances and unit prices, completed within the time limits and in accordance with the contract documents is:
___________________________________________________________________________ Dollars (Words) (Figures)
BID FORM BF - 2
ADDITIVE BID ALTERNATES:
Bid Alternate No. 1: Provide all work associated installation of the 4’ fence along the perimeter of the project as noted in the civil plans.
___________________________________________________________________________ Dollars (Words)
ADDENDA:
The above stated bid is based on the Contract Documents and the following additional addenda issued subsequent to the release of the drawings and specifications for bids. (List all addenda with dates, if issued. If no addenda are issued, write the word “none”.)
Addenda # _____ Date _____________ Addenda # _____ Date _____________
Addenda # _____ Date _____________ Addenda # _____ Date _____________
TIME OF COMPLETION:
Work at the site(s) shall commence within ten (10) working days following the execution of the contract or the Notice-To-Proceed. The Owner anticipates the Award of these contract(s) or the issuance of the Notice-Of-Award on or before April 16, 2026. All work shall be substantially complete and finally complete as follows:
Substantial Completion: October 1, 2026
100% Final Completion (all phases): November 6, 2026
The Owner will consider any request made by the Contractor to extend the Contractor’s time for performance of the work and may grant time reasonable time extensions when delays in the
Contractor’s work performance are directly caused by supply chain delays, if the Contractor has provided the Owner with (i) reasonable notice in advance that its work is being impacted by supply chain delays; (ii) adequate verification to support the Contractor’s claim; and (iii) written certification that any delay in its performance of this Contract is beyond the Contractor’s control and not the result of actions or any failure to act by the Contractor.
PROFIT AND OVERHEAD FOR CHANGE ORDERS:
Change Orders initiated per Article 9 of the General Conditions shall be executed on the basis of the cost of the work, plus a percentage of the work, according to the percentages indicated in Articles
9.3.4.2.1 and 9.3.4.2.2 of the General Conditions.
OTHER:
If notified of the acceptance of this bid(s), the undersigned agrees to execute and deliver to the owner the Contract and Contractor’s Bonds within ten (10) calendar days from the date of notification and, to faithfully and properly complete the work with the best interest of the Owner, the safety of the public, and in accordance with first class workmanship.
BID FORM BF - 3
The undersigned agrees that the Owner may retain five percent (5%) of the Contract amount as specified in the Sample Agreement/Agreement.
BID SECURITY:
Attached hereto is a cashiers check, certified check, or Bid Bond (AIA Document A310 or from a
Surety Company authorized to do business in the Commonwealth of Virginia and acceptable to the
Owner), none of which shall be less than five percent (5%) of the principle bid amount, and made payable to Lunenburg County School Board.
The undersigned agrees, if awarded the Contract, to comply with all provisions regarding commencement, performance, completion, and acceptance of the work described in the above-mentioned specifications and drawings, construction contract, and as stipulated in this proposal. The undersigned further agrees, if awarded this contract, to execute and deliver Performance and Labor and Material Payment bonds each in an amount equal to one hundred percent (100%) of the Contract
Price. In case of bidders failure to execute the Contract, provide a performance bond, or to commence the work, the check or bid bond shall be paid as liquidated damages for such failure; otherwise the check or bid bond accompanying the proposal will be returned to the Undersigned.
LIQUIDATED DAMAGES:
The Bidder acknowledges and agrees to the liquidated damages specified in the Sample
Agreement/Agreement. Bidder also acknowledges that time is of the essence and that work to be performed by others and/or use of the school is restrained by the timely completion of the work within this contract.
Contractor’s work performance are directly caused by supply chain delays, if the Contractor has provided the Owner with (i) reasonable notice in advance that its work is being impacted by supply chain delays; (ii) adequate verification to support the Contractor’s claim; and (iii) written certification that any delay in its performance of this Contract is beyond the Contractor’s control and
BID FORM SIGNATURE(S):
The Undersigned declares that this firm is (check one):
❑ A Corporation organized and existing under the laws of _____________________________.
❑ A Partnership consisting of ____________________________________________________.
❑ A sole Proprietorship.
❑ Other _____________________________________________________________________.
Virginia State Corporation Commission ID #________________________________________
It is agreed, that the Undersigned has complied with and/or will comply with all requirements concerning licensing and with all other Local, State, and National laws and that no legal requirement has been, or will be, violated in making or accepting this proposal, in awarding the contract to him, and/or in the prosecution of the work required therein.
The Undersigned declares that the person, or persons, signing this proposal is/are fully authorized to sign the proposal on behalf of the firm listed and to fully bind their firm listed to all the conditions and provisions thereof. It is agreed that no person, persons, or company other that the firm listed below or as otherwise indicated hereinafter has any interest whatsoever in this proposal of the
BID FORM BF - 4
Contract that may be entered into as a result thereof and that in all respects the proposal is legal, fair, and submitted in good faith without collusion or fraud.
Respectfully submitted this _______ day of _____________, 2024.
(Name of Firm)
(Address)
______________________________________________________ Affix Seal
Telephone (____)______________ Fax (____)________________
Email address __________________________________________
Registered Virginia Contractor #: _____________________ ( Please attach a copy of the registration)
By: _______________________________________________ (Signature)
Name: _______________________________________________ (Printed)
Title: _______________________________________________ Affix Seal (Printed)
END OF BID FORM
Lunenburg County Public Schools 1009 Main Street
26-LMS
SAMPLE AGREEMENT SA - 1
Sample Agreement
Lunenburg County School Board
IFB # 26-LMS
THIS AGREEMENT, made and entered into this day of _________, 2026 by and between the Lunenburg County School Board, (hereinafter called the Owner), whose address is 1009
Main St, Kenbridge, VA 23944 and ________________________________________ (hereinafter called the Contractor), whose address is .
WITNESSETH: WHEREAS, the Owner intends to contract the construction of Lunenburg Middle
School Baseball Field. The project is located at 583 Tomlinson Road, Victoria, VA 23974.
WHEREAS, the Contractor agrees to perform the work for the sum herein stated.
NOW THEREFORE, the Owner and the Contractor agree as set forth below.
ARTICLE 1. SCOPE OF WORK
The work to be performed shall be in accordance with IFB #26-LMS and all related Contract
Documents prepared by RRMM Architects dated March 20, 2026, and entitled “Lunenburg Middle
School Baseball Field”. The Contractor agrees to furnish all labor, materials, equipment and supervision to complete the work as required in the Contract Documents, which are hereby made a part of this contract by reference. It is understood and agreed by the parties hereto that all work shall be performed as required in IFB #26-LMS and related Contract Documents and shall be subject to inspection and approval by the Owner or its authorized representative. The relationship of the
Contractor to the Owner hereunder is that of an independent Contractor. The Contract Documents are defined in the General Conditions and are incorporated herein by reference.
ARTICLE 2. TIME OF COMPLETION
The Contractor shall commence the work promptly upon the date established in the Notice of Award or Notice to Proceed. The Contractor shall achieve all the times and dates shown on the bid form, which are incorporated herein by reference and made a part of this Contract as though fully set forth herein. All work shall be completed as follows:
Substantial Completion October 1, 2026
100% Final Completion: November 6, 2026
ARTICLE 3. CONTRACT SUM
The Owner agrees to pay, and the Contractor agrees to accept in full performance of this Contract, the sum of , ($_________________________) which sum also includes:
A) The cost of a 100% Performance Bond and a 100% Payment Bond, said bonds having been posted by the Contractor pursuant to laws of the Commonwealth of Virginia;
B) All work included in bid Addenda Number(s) ____________.
SAMPLE AGREEMENT SA - 2
C) All Deductive and Additive Bid Alternates accepted by the Owner, which include #’s:
ARTICLE 4. PAYMENT
The Owner agrees to pay the Contractor as the work progresses, but not more frequently than once each month after the date of the Notice of Award or Notice to Proceed, and only after fully complying with the General Conditions and completion of an acceptable Certificate of Payment for the work performed during the preceding calendar month, ninety-five percent (95%) of the value of the labor performed and, subject to the requirements of the General Conditions, ninety-five percent (95%) of the value of materials furnished in place or on-site.
The Contractor shall supply such evidence of labor performed and materials furnished, as the Owner may desire, at time of request for the Certificate of Payment of account. Materials for which payment has been made cannot be removed from job site.
Retainage Reduction – Five percent (5%) of the earned amount shall be retained from each monthly payment until fifty percent (50%) of the dollar amount of the Contract has been earned. During the last fifty percent (50%) of the Contract, retainage may be reduced pursuant to applicable provisions of the General Conditions.
A payment clause that obligates a contractor on a construction contract to be liable for the entire amount owed to any subcontractor with which it contracts. Such contractor shall not be liable for amounts otherwise reducible due to the subcontractor's noncompliance with the terms of the contract.
However, in the event that the contractor withholds all or a part of the amount promised to the subcontractor under the contract, the contractor shall notify the subcontractor, in writing, of his intention to withhold all or a part of the subcontractor's payment with the reason for nonpayment.
Payment by the party contracting with the contractor shall not be a condition precedent to payment to any lower-tier subcontractor, regardless of that contractor receiving payment for amounts owed to that contractor. Any provision in a contract contrary to this section shall be unenforceable.
ARTICLE 5. INDEBTEDNESS
Before final payment is made, the Contractor must submit evidence in the form of a final waiver of lien or claim to the Owner that all payrolls, materials bills, subcontracts and outstanding indebtedness in connection with the work have been paid or what arrangements have been made for their payment.
Payment will be made without unnecessary delay and after receipt of such evidence as mentioned above and final acceptance of the work by the Owner.
ARTICLE 6. ADDITIONAL WORK
It is understood and agreed by the parties hereto that no money will be paid to the Contractor for any additional labor or materials furnished unless a new contract in writing or a modification hereto for such additional materials or labor has been executed by the Owner and Contractor. The Owner specifically reserves the right to modify or amend this Contract and the total sum due hereunder either by enlarging or restricting the scope of work.
SAMPLE AGREEMENT SA - 3
ARTICLE 7. ACCEPTANCE
The work shall be inspected for acceptance by the Architect promptly upon receipt of notice from the
Contractor that the work is complete and ready for inspection.
ARTICLE 8. DISPUTES PERTAINING TO PAYMENT FOR WORK
Should disputes arise regarding the value of any work done, or any work omitted, or of any extra work which said Contractor may be required to perform, or respecting any other elements involved in this Contract, said dispute shall be brought to the attention of the Program Manager who will endeavor to settle matters. If he/she is unsuccessful, the dispute will be brought to the attention of the
Lunenburg County School Board and their decision shall be final and conclusive.
ARTICLE 9. TERMINATION FOR BREACH, ETC.
If the Contractor shall be adjudged bankrupt, or if he should make a general assignment for the benefit of his creditors, or if a receiver should be appointed on account of his insolvency, or if he or any of his subcontractors violate any of the provisions of this Contract, the Owner may serve written notice upon him of its intention to terminate said Contract; and unless, within ten (10) days after the serving of such notice, such violation shall cease, the Owner then may take over the work and prosecute same to completion by contract or by any other method it may deem advisable for the account and at the expense of the Contractor. The Owner may take possession of and utilize in completing the work, such materials, equipment, and any other property belonging to the Contractor as may be on the site of the work and necessary therefore. The Owner may, at any time upon ten (10) days written notice to the Contractor, terminate (without prejudice to any right or remedy of the
Owner) the whole or any portion of the work for the convenience of the Owner.
ARTICLE 10. OWNER’S RIGHT TO WITHHOLD CERTAIN AMOUNT AND MAKE
APPLICATION THEREOF
The Owner may withhold from payment to the Contractor such an amount or amounts as, in the
Owner’s sole judgment, may be necessary to pay just claims against the Contractor or any subcontractor for labor and services rendered and materials furnished in and about the work. The
Owner may apply such withheld amounts on the payment of such claims in its sole discretion. In so doing, the Owner shall be deemed the agent of the Contractor and payments so made by the Owner shall be made by the Owner under the terms of the Contract and in good faith and no liability whatsoever shall attach to the Owner for having made such payments. Such payments may be made without prior determination by the Owner of the validity of any claim or claims.
ARTICLE 11. LIABILITY AND INDEMNIFICATION
The Contractor agrees that it shall at all times protect and indemnify and save harmless, the
Lunenburg County School Board and all institutions, agencies, departments, authorities and instrumentalities of the School Board and any member of the School Board or of their boards or commissions or any of the elected or appointed officers or any of their employees or authorized volunteers as described in the General Conditions of the project specifications which are included herein by reference, from any and all claims, damages of every kind and nature made, rendered or incurred by or in behalf of any person or corporation whatsoever, including the parties hereto and
SAMPLE AGREEMENT SA - 4
their employees that may arise, that occur or grow out of any acts, actions, work or other activity done by the said Contractor in the performance and execution of this Contract.
ARTICILE 12. SUBCONTRACTOR
No part of this Contract shall be sublet by the Contractor without prior written approval of the Owner.
ARTICLE 13. LIQUIDATED DAMAGES
Should the Contractor fail to Finally Complete the work on or before the Contract Completion Date for any and all completion dates, referred to in Article 2 hereof, the Contractor shall pay to the Owner the sum of $500.00 for each consecutive calendar day that terms of the Contract remain unfulfilled as defined in Article 9, Section 9.11 of the Supplementary General Conditions of the Construction
Contract.
Contractor’s work performance are directly caused by supply chain delays, if the Contractor has provided the Owner with (i) reasonable notice in advance that its work is being impacted by supply chain delays; (ii) adequate verification to support the Contractor’s claim; and (iii) written certification that any delay in its performance of this Contract is beyond the Contractor’s control and
ARTICLE 14, NONDISCRIMINATION
During the performance of this contract, the contractor agrees as follows:
a. The contractor will not discriminate against any employee or applicant for employment because of race, religion, color, sex, national origin, age, disability, or any other basis prohibited by state law relating to discrimination in employment, except where there is a bona fide occupational qualification reasonably necessary to the normal operation of the contractor. The contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices setting forth the provisions of this nondiscrimination clause.
b. The contractor, in all solicitations or advertisements for employees placed by or on behalf of the contractor, will state that such contractor is an equal opportunity employer.
c. Notices, advertisements and solicitations placed in accordance with federal law, rule or regulation shall be deemed sufficient for the purpose of meeting the requirements of this section.
The contractor will include the provisions of the foregoing paragraphs a, b and c in every subcontract or purchase order of over $10,000, so that the provisions will be binding upon each subcontractor or vendor.
Lunenburg County Public Schools does not discriminate against faith-based organizations.
SAMPLE AGREEMENT SA - 5
ARTICLE 15, DRUG FREE WORKPLACE
During the performance of this contract, the contractor agrees to:
a. Provide a drug-free workplace for the contractor’s employees,
b. Post in conspicuous places, available to employees and applicants for employment, a statement notifying employees that the unlawful manufacture, sale, distribution, dispensation, possession or use of a controlled substance or marijuana is prohibited in the contractor’s work place and specifying the actions that will be taken against employees for violations of such prohibition,
c. State in all solicitations or advertisements for employees placed by or on behalf of the contractor that the contractor maintains a drug-free work place,
d. Include the provisions of the foregoing clauses in every subcontract or purchase order of over $10, 000 so that the provisions will be binding upon each subcontractor or vendor.
ARTICLE 16, CONTRACTOR/EMPLOYEE BACKGROUND CERTIFICATION
Upon award, the contractor and any employee who will have direct contact with students shall provide certification that (i) he has not been convicted of a felony or any offense involving the sexual molestation or physical or sexual abuse or rape of a child; and (ii) whether he has been convicted of a crime of moral turpitude.
Any person making a materially false statement regarding such offense shall be guilty of a Class 1 misdemeanor and, upon conviction, the fact of such conviction shall be grounds for the revocation of the contract to provide such services and, when relevant, the revocation of any license required to provide such services.
ARTICLE 17, STATE CORPORATION COMMISSION ID NUMBER
In accordance with new registration requirements effective July 1, 2010, the Contractor shall include the identification number issued by the State Corporation Commission as proof of registration or justification for non-registration per the requirements in Section 13.1 or Title 50 of the Code of
Virginia.
SCC ID #____________________________________________________________________
ARTICLE 18, COMPLIANCE WITH FEDERAL IMMIGRATION LAW
The Contractor shall not, during the performance of a contract knowingly employ an unauthorized alien as defined in the Federal Immigration Reform and Control Act of 1986.
SAMPLE AGREEMENT SA - 6
SIGNATURE PAGES
IN WITNESS WHEREOF, the parties have caused the Agreement to be executed by the following duly authorized officials.
LUNENBURG COUNTY SCHOOL BOARD,
A Body Corporation
By: _________________________
Chair
Lunenburg County School Board
By: _________________________
Superintendent
NOTARY CLAUSE
Commonwealth of Virginia
City/County________________________________________, to wit: The following instrument was
Acknowledged before me this ________day of _____________________, 2026 by ______________
Name
____________________________________, ________________________________________, and
Name Title
Name Title
My commission expires:________________________
Notary Number:_______________________________
Notary Public
Contractor
By: ____________________________________
Signature
SAMPLE AGREEMENT SA - 7
Print Name
Title
APPROVED AS TO FORM AND CONTENT:
School Board Attorney
SAMPLE AGREEMENT SA - 8
SUPPLEMENTAL CONDITIONS 000800 - 1
SECTION 000800 - SUPPLEMENTAL CONDITIONS
The following Supplemental Conditions modify the "General Conditions of the Contract for
Construction", AIA Document A201, Fifteenth Edition, 2007. Where a portion of the
General Conditions is modified or deleted by these Supplemental Conditions, the unaltered portions of the General Conditions shall remain in full force and effect.
ARTICLE 1; GENERAL PROVISIONS
1.2 CORRELATION AND INTENT OF THE CONTRACT DOCUMENTS
Add to 1.2 the following Clause 1.2.3.1:
1.2.3.1 Where on any drawings a portion of the Work is drawn out and the remainder is indicated in outline, the parts drawn out shall apply also to all other work. Where details or conditions are indicated but started only, such details, or conditions shall be continued throughout the course or parts in which they occur and shall also apply to all other similar parts of the Work unless otherwise indicated or specifically noted. On all Drawings, figures shall take precedence over measurements by scale, and scaling is done at the Contractor’s own risk.
ARTICLE 2; OWNER
2.1. GENERAL
Delete Subparagraph 2.1.2 in its entirety.
2.2 INFORMATION AND SERVICES REQUIRED OF THE OWNER
Delete Subparagraph 2.2.1 in its entirety.
Delete subparagraph 2.2.5 in its entirety and substitute the following:
2.2.5 The Contractor will be furnished, an electronic (PDF) copy of the drawings and specifications. Additional hard copy sets will be furnished at the cost of reproduction, postage and handling.
2.4 OWNER’S RIGHT TO CARRY OUT THE WORK
2.4.1 Delete the sentence in Subparagraph 2.4.1 reading "Such action by the Owner and amounts charged to the Contractor are both subject to prior approval of the Architect."
3.10 CONTRACTOR’S CONSTRUCTION SCHEDULES
Add the following subparagraph 3.10.4:
3.10.4 Contract time adjustments for abnormal inclement weather will be based upon the
SUPPLEMENTAL CONDITIONS 000800 - 2
following requirements:
3.10.4.1 Contractor agrees that Dates under this Contract will not be extended due to normal inclement weather. For a time extension to be granted for abnormal inclement weather: (1) such weather must, in the judgment of the Architect, actually have an adverse effect upon the progress of the Contractor’s work which is of a critical nature; and (2) in the judgment of the Architect, the adverse effect must not be due to any fault or negligence of
Contractor and could not have been avoided by Contractor through proper planning, coordination, and implementation of adequate weather protection necessary to allow the
Work to be continued. Contractor agrees that the fact that abnormal inclement weather may occur, does not, of itself, justify any time extension hereunder.
3.10.4.2 Contractor agrees that it shall not be entitled to a time extension for normal inclement weather which can be expected at the Project locale due to precipitation, based on actual data from the U.S. Department of Commerce, National Oceanic and Atmospheric
Administration (NOAA) for the locale of the Project. Contractor acknowledges and warrants that in making its bid and Construction Schedule for the Work, it gave due care and consideration to this expected number of work days of inclement weather for the locale of the
Project and allowed therefore the impact of inclement weather on subsequent work. During the time of performance, should the expected number of work days of inclement weather for the locale of the Project be less than originally anticipated by Contractor and Owner, at the time of contracting, those days not so affected by inclement weather shall be considered float time.
January 8 July 4
February 8 August 4
March 8 September 4
April 6 October 4
May 4 November 4
June 4 December 6
3.10.4.3 Time extensions for weather delays during a given month will be allowed only for actual work days lost in excess of the anticipated number of work days lost (listed above) and only when those excess lost days adversely impact the current critical path(s) leading to the specified Substantial Completion or Contract Completion dates. Actual work days lost are defined as days that work was prevented on critical path activities for fifty percent (50%) or more of the Contractor’s scheduled workday.
3.10.4.4 Within fourteen (14) calendar days after the end of a given month, the
Contractor must submit its time extension request for any weather related delays along with supporting data. For instance, if the contractor requests a time extension for weather related delays during March, the request is due on April 14. If the extension request is not submitted within the aforementioned timeframe, the Contractor shall have waived any and all rights it may have against the Owner.
Add the following subparagraph 3.10.5:
SUPPLEMENTAL CONDITIONS 000800 - 3
3.10.5 The Contractor shall submit an updated construction schedule monthly with his application for payment. The revised schedule will demonstrate a strategy for overcoming any variances in the previous month's schedule in order to complete the project on time. Pay requests will not be reviewed unless accompanied by the update schedule.
3.12 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES
Amend subparagraph 3.12.5 by adding new sub-paragraphs 3.12.5.1 and 3.12.5.2, as follows:
3.12.5.1 Any Drawings, Schedules, and Catalog Data submitted without the Contractor's stamp of approval will not be considered by the Architect and will be returned to the
Contractor.
3.12.5.2 The Contractor shall be responsible for the satisfactory construction of all Work in accordance with the quantities, dimensions, and designs shown in the Contract documents and the furnishing of all materials necessary for the Work and required by the Contract
Documents even if not indicated on the submittals that have been approved by the Architect.
Amend subparagraph 3.12.8 by adding the following to the end of the paragraph:
Failure to so notify the Architect in writing of such deviations shall constitute just cause for rejection of samples and Shop Drawings, including all finished work resulting therefrom, at any time during the construction and up through the prescribed guarantee period. The
Architect's approval of samples and Shop Drawings is made with the understanding that such
Shop Drawings and samples conform with, and do not deviate from the Contract Documents unless Architect is so informed in writing at the time of submittal thereof.
3.14 CUTTING AND PATCHING
Add to 3.14 the following subparagraph 3.14.3:
3.14.3 No cutouts, access doors or mechanical or electrical conduit or devices of any sort shall be installed in finished materials or areas other than in mechanical rooms, wall chases and…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .