This is a Local Administered Project (LAP) Evaluation Form used by the Georgia Department of Transportation (GDOT) to assess consultant performance on contracted projects. The form evaluates consultants across two primary rating categories: Management and Prosecution and Progress. The Management section assesses whether consultants appropriately managed resources, worked independently without excessive agency staff support, remained within the contracted scope of work, and maintained effective communication and cooperation with GDOT staff. The Prosecution and Progress section evaluates whether consultants completed deliverables by agreed-upon dates, produced complete and accurate invoices, reports, and design requirements with minimal revisions, and stayed within assigned budgets. The evaluation uses a five-point scale where 5 indicates exceeds requirements, 3 indicates meets requirements, and 1 indicates does not meet requirements, with subtotals calculated for each section.
The form requires signature and acknowledgment from multiple parties, including the GDOT Project Manager, project supervisor, consultant project manager, and the agency evaluator's supervisor. When a rating of 1 is recorded in any category, acknowledgment from both the GDOT Assistant Office Head and Office Head is mandatory. The scoring table applies weighted factors based on the number of ratings provided, with single ratings valued at 50 points for a score of 5, 30 points for a score of 3, and 10 points for a score of 1. The form includes fields for the GDOT PI number, project description, scope, phase, and service dates, along with spaces for justification of scores and consultant responses to evaluations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ_484_042026 Drainage Analysis Inventory _ .pdf | ||
| Legacy Evaluation Form.xlsx | XLSX spreadsheet | |
| Statewide Stormwater Field Maps Manual_v3.pdf | ||
| IM_Manual.pdf | ||
| RFQ_484_042026 Addendum 1.pdf | ||
| RFQ_484_042026 Drainage Analysis Inventory (C.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LAP Evaluation Form
Local Administered Project (LAP) Evaluation Form
Evaluation Date:
Consultant:
GDOT PI No:
GDOT PM:
Agency:
Agency PM:
Phone:
Email:
Project Description & Scope:
Project Phase:
Service Dates:
Ratings: 5 = Exceeds Requirement and Expectation; 3 = Meets Requirement and Expectation; 1 = Does not Meet Requirement and Expectation; or N/A Requirement and Expectation
| A | Management | Rating | Factor | ||
| 1 | Consultant appropriately managed resources (manpower, equipment, subconsultants, etc.) | N/A | - - - | 1 | |
| 2 | Consultant worked independently and without significant help from Agency's staff on routine tasks. | N/A | - - - | 1 | |
| 3 | Consultant remained within the scope of work as contracted. | N/A | - - - | 1 | |
| 4 | Consultant communicated well and worked cooperatively with GDOT staff, and Consultant promptly responded to calls, emails, correspondences, and direction given by GDOT staff. | N/A | - - - | 1 | |
| 0 | Ratings | ||||
| Sub Total: | 0.00 | ||||
| GDOT PM/SME Justification for Scores (required): |
Consultant Response to Evaluation (if applicable):
| B | Prosecution and Progress | Rating | Factor | ||
| 5 | Consultant completed the deliverable(s) by the latest agreed upon date or within the duration contracted, as applicable. | N/A | - - - | 1 | |
| 6 | All invoices, studies, reports, design requirements, and details are complete, accurate, clear, and concise. Revisions are minimal. | N/A | - - - | 1 | |
| 7 | Consultant completed the deliverable(s) within the assigned budget. | N/A | - - - | 1 | |
| 0 | Ratings | ||||
| Sub Total: | 0.00 | ||||
| GDOT PM/SME Justification for Scores (required): |
Consultant Response to Evaluation (if applicable):
Total Score: 0
| GDOT PM: | ||
| Signature: | Date: | |
| Supervisor's Acknowledgement: |
Local's Comments:
Local's Acknowledgement:
| The GDOT Assistant Office Head (AOH) and Office Head (OH) Acknowledgements are required if a Rating of 1 is recorded for any item above. |
| AOH Acknowledgement: OH Acknowledgement: |
| Consultant PM: | ||
| Signature: | Date: |
| Agency Evaluator's | ||
| Supervisor (if applicable): | ||
| Signature: | Date: |
&12&A Page &P of &N
Scoring
| 1 | |||||
| 3 | |||||
| 5 | |||||
| N/A | |||||
| Factor Table | |||||
| Section Value: | 50 | 5 | 3 | 1 | |
| 0 | Ratings | 0.00 | 0.00 | 0.00 | |
| 1 | Ratings | 50.00 | 30.00 | 10.00 | |
| 2 | Ratings | 25.00 | 15.00 | 5.00 | |
| 3 | Ratings | 16.67 | 10.00 | 3.33 | |
| 4 | Ratings | 12.50 | 7.50 | 2.50 |