This cost proposal spreadsheet provides pricing details for the RDU HVAC and Fire Alarm Replacement project located at Raleigh-Durham International Airport in Raleigh, North Carolina. The proposal includes line item costs for general site conditions, structural work, roofing, electrical, plumbing, safety and security, and miscellaneous work categories. However, all unit and total costs are currently shown as $0.00, indicating this is a template that will need to be populated with actual cost data for a full proposal. The related federal contract opportunity posted by the Federal Aviation Administration's Southwestern Region seeks to replace HVAC and fire alarm systems at Raleigh-Durham International Airport, as outlined in the attached specifications.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HVAC
| COST PROPOSAL | DATE | SHEET 1 OF 1 | |||
| PROJECT | BASIS FOR ESTIMATE | ||||
| RDU HVAC and Fire Alarm Replacement | STANDARD DESIGN | ||||
| LOCATION | DRAWING REF. NO. | PROJECT DESIGN | |||
| Raleigh, NC | OTHER (SPECIFY) | ||||
| PREPARING ORGANIZATION | SPEC. REF. NO. |
CLASS OF WORK ESTIMATOR CHECKED BY
| ITEM | QUANTITY | MATERIAL COST ($) | LABOR COST ($) | EQUIPMENT COST ($) | TOTAL | ||||
| UNIT | NO. | PER | PER | PER | ITEM | ||||
| MEAS. | UNITS | UNIT | TOTAL | UNIT | TOTAL | UNIT | TOTAL | COST ($) | |
| General / Site Conditions | |||||||||
| Mobilization / Demobilization | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Site Cleanup | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Misc. Utility Relocations | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Site Supervision/PM | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ||
| Structural | |||||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| Roofing | |||||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| Lightning Protection | |||||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| Electrical | |||||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| Plumbing | |||||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| Safety & Security | |||||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| Miscellaneous | |||||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| SUBTOTAL | $0.00 | $0.00 | $0.00 | $0.00 | |
| Overhead | 0% | $0.00 | $0.00 | $0.00 | $0.00 |
| Profit | 0% | $0.00 | $0.00 | $0.00 | $0.00 |
| Bond | $0.00 | $0.00 | $0.00 | $0.00 |
TOTAL COSTS $0.00 $0.00 $0.00 $0.00