Bureau of Land Management SECTION 072600 FDO Storage Facility VAPOR RETARDERS
March 26, 2015 072600 - 1 100% Construction Documents
SECTION 072600 - VAPOR RETARDERS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Polyethylene vapor retarders.
B. Related Requirements:
1. Section 033000 "Cast-in-Place Concrete" for under-slab vapor retarders.
2. Section 072100 "Thermal Insulation" for vapor retarders integral with insulation products.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product.
1.4 INFORMATIONAL SUBMITTALS
A. Product Test Reports: For each product, for tests performed by a qualified testing agency.
PART 2 - PRODUCTS
2.1 POLYETHYLENE VAPOR RETARDERS
A. Polyethylene Vapor Retarders: ASTM D 4397, 10-mil thick sheet, with maximum permeance rating of 0.1 perm.
2.2 ACCESSORIES
A. Vapor-Retarder Tape: Pressure-sensitive tape of type recommended by vapor-retarder manufacturer for sealing joints and penetrations in vapor retarder.
Bureau of Land Management SECTION 072600 FDO Storage Facility VAPOR RETARDERS
March 26, 2015 072600 - 2 100% Construction Documents
B. Adhesive for Vapor Retarders: Product recommended by vapor-retarder manufacturer and has demonstrated capability to bond vapor retarders securely to substrates indicated.
C. Vapor-Retarder Fasteners: Pancake-head, self-tapping steel drill screws; with fender washers.
PART 3 - EXECUTION
3.1 PREPARATION
A. Clean substrates of substances that are harmful to vapor retarders, including removing projections capable of puncturing vapor retarders.
3.2 INSTALLATION OF VAPOR RETARDERS ON FRAMING
A. Place vapor retarders on side of construction indicated on Drawings.
B. Extend vapor retarders to extremities of areas to protect from vapor transmission.
Secure vapor retarders in place with adhesives, vapor retarder fasteners, or other anchorage system as recommended by manufacturer. Extend vapor retarders to cover miscellaneous voids in insulated substrates, including those filled with loose-fiber insulation.
C. Seal vertical joints in vapor retarders over framing by lapping no fewer than two studs and sealing with vapor-retarder tape according to vapor-retarder manufacturer's written instructions. Locate all joints over framing members or other solid substrates.
D. Seal joints caused by pipes, conduits, electrical boxes, and similar items penetrating vapor retarders with vapor-retarder tape to create an airtight seal between penetrating objects and vapor retarders.
E. Repair tears or punctures in vapor retarders immediately before concealment by other work. Cover with vapor-retarder tape or another layer of vapor retarders.
3.3 PROTECTION
A. Protect vapor retarders from damage until concealed by permanent construction.
END OF SECTION 072600