United States Department of the Interior
BUREAU OF LAND MANAGEMENT
National Operations Center
Denver Federal Center, Building 50
P.O. Box 25047
Denver, Colorado 80225-0047 http://www.blm.gov
April 7, 2015
AMENDMENT 001
Subject: L15PS00180 001 / Fairbanks District Office Storage Facility
The following questions and answers have been submitted by prospective contractors interested in providing a proposal for subject Solicitation L15PS00180 and have been answered by Bureau of Land Management staff.
QUESTION 1. Reference drawing sheet M2.1 and specification 231113-3.11, Facility Fuel-Oil
Piping, Outdoor Piping Schedule.
Details 3 and 4 show containment pipe for the buried fuel oil piping. However, the specification requires steel pipe with polyethylene coating. Which is correct?
If containment piping is required, please forward a specification.
ANSWER 1. Buried fuel oil piping is double containment piping. Replace specification section 231113 with updated version. (See attachment “L15PS00180 Amendment 001 FDO
Storage Specification 231113 Facility Fuel-Oil Piping”)
QUESTION 2. Reference drawing sheet M2.1, detail 3, Fuel Oil System Schematic.
The scheduled Simplex fuel oil transfer pump P-3 includes a pressure relief valve. Shall this relief valve be piped to the fuel oil return system?
ANSWER 2. Fuel oil transfer pump P-3 pressure relief valve shall be piped to the fuel oil return system. Add specification section 231213. (See attachment “L15PS00180
Amendment 001 FDO Storage Specification 231213 Facility Fuel-Oil Pumps”)
QUESTION 3. Reference drawing sheets M2.0, detail 2, Enlarged Boiler Room Plan, and M2.1, detail 1, Heating Schematic.
No glycol makeup unit is indicated to be provided for the heat transfer fluid.
We suggest that a small packaged makeup unit (tank with pump) be provided for maintaining the heating system.
ANSWER 3. No glycol makeup unit is wanted or required.
L15PS00180 FDO Storage Amendment 001
QUESTION 4. Do bidding questions need to be submitted on RFI form?
ANSWER 4. Per Solicitation Document L.3 SUBMITTAL OF QUESTIONS:
“Offeror is to consolidate questions related to this solicitation and site visit in a request for information (RFI) formatted Word document. RFI is to be emailed as an editable attachment to the Contracting Officer by 15 April 2015 at 2:00 pm (14:00) Local Alaskan
Time with the subject line: L15PS00180/FDO Storage Facility. Only written RFI’s will be considered and responded to by the Contracting Officer. BLM responses to the RFI will be posted as an amendment to the solicitation on FBO.”
Please email John Kelley at jakelley@blm.gov with any and all questions.
QUESTION 5. Are there special requirements for existing parking lot, such as daily sweeping, clean-up, etc?
ANSWER 5. Per specification section 011000 subsection 1.5, "Existing drives, entrances, and parking lots serving premises shall be maintained clear and available to Owner, Owner's employees, and emergency vehicles at all times during regular business hours to permit conduct of Owner's normal operations. Do not use these areas for parking or storage of materials.”
QUESTION 6. Garage piping/conduits to be painted?
ANSWER 6. Exposed conduit, pipe, and other surfaces shall be painted in accordance with specification section 099123.
QUESTION 7. Office access for workers? Daily sign in/out procedures? Garage door access?
ANSWER 7. Per specification section 011000 subsection 1.5, work within the existing FDO building shall be limited to Owner's regular business hours and shall be coordinated with
Government to minimize disruption to building occupants. Policy requires each
Contractor personnel to sign in/out once per day and be escorted/supervised by a government representative. Additionally, the Contractor Superintendent may agree to undergo security clearance for "contractor" badge. This will allow the Superintendent to escort/supervise Contractor personnel and also receive a door key. The garage doors may be used for moving project equipment and materials in and out of the building only under supervision. Special Security Requirement: Work within the second floor electrical room and Communications Room 153 will require Government escort at all times; schedule work in these areas minimum 48 hours in advance to assure availability of Government escort.
QUESTION 8. Height of Fuel Piping in garage space?
ANSWER 8. Per drawing detail 4/M2.1 fuel piping shall be mounted as high as practicable. Practicable shall be considered to be below the steel floor beams.
QUESTION 9. Will storage items (existing) in garage space be moved/cleaned up prior to the work beginning?
ANSWER 9. District Office staff will be notified to organize & move storage items out of the Contractor's way in the existing garage space by June 15. Any additional cleaning or moving of items necessary for the work, is the Contractor's responsibility. The Contractor shall restore the space to the pre-work condition upon completion of the work.
QUESTION 10. Panel “IS” type? Space 28 available?
mailto:jakelley@blm.gov
ANSWER 10. Panel "IS" is Square D NQOB. The following spaces are empty: 29, 31, 33, 35, 38, 40, 42.
QUESTION 11. Can bidders come back for additional inspections during the bidding period?
ANSWER 11. Yes, Prospective contractors can come for an additional inspection with an approved appointment time with Contracting Officer Representative Darrin McLeod (907-
474-2207) up to April 15, 2015. All questions resulting from individual contractor inspections will be documented by Darrin McLeod and answered via an amendment.
QUESTION 12. Where shall the Fuel Pump be placed?
ANSWER 12. Fuel pump P-3 to be located as close to the existing column as practicable.
QUESTION 13. Is it possible to get an extension on the deadline for the official response to the
Past Performance Questionnaire? The deadline is April 6, 2015 which is Monday.
ANSWER 13. The revised deadline for the official response to the Past Performance
Questionnaire is April 20, 2015 (See Attachment).
QUESTION 14. Exterior wall detail 1/A4.1 does not indicate a vapor retarder at interior side of exterior wall. Specification Section 07 21 00 Thermal Insulation does not include an interior vapor retarder. Will there be a vapor retarder on exterior wall and what is the basis of design for the vapor retarder? Vapor retarder is written in narrative for the roof assembly detail 2/A4.1, however the vapor retarder type is not provided.
ANSWER 14. No vapor retarder is required for the exterior wall assembly. (See attachment “L15PS00180 Amendment 001 FDO Storage Specification 072600”)
QUESTION 15. The specified metal wall panels are not available in full length as shown on the elevations. Standard panel splice details will be required. Can you give us the panel splice spacing for the metal wall panels?
ANSWER 15. The type of panels specified can be installed with vertical expansion joints if necessary due to limited lengths. Overlapping the panels will not be satisfactory, and the manufacturer’s standard detail will be a means to resolve this, however, the gov't needs to assure that the locations of the vertical joints are placed appropriately and this can be resolved in the submittals process.
QUESTION 16. Section 072100 Thermal Insulation paragraph 3.3.B states we are to adhere insulation on foundation walls. Detail 3/A4.1 shows poly sheeting under slab and extended to top of slab. Typical details for foundation walls are a fluid applied dampproofing or self-adhering low temperature membrane. Both allow for better adhesion of the foundation insulation. Can one of these be utilized in lieu of the poly sheeting?
ANSWER 16. There are no foundation walls. Section 072100 Thermal Insulation paragraph 3.2.A requires adhering insulation to vertical slab surfaces using adhesive.
Section 072600 Vapor Retarders also contains provisions for adhesive. The slab vapor barrier shall be installed as shown.
QUESTION 17. The drawing shows the intermediate fence posts being driven 60" which has become pretty standard on this type of fence in our part of Alaska. The written spec only coverts posts set in concrete. Which method will be required for this project?
ANSWER 17. The line posts (intermediate posts) may be driven to 60" embedment with no concrete encasement.
QUESTION 18. The detail for the terminal and gate posts calls for a sonotube and three wraps of visqueen in each hole. This is a specification that one architect in Fairbanks came up with 25 years as a method to prevent frost heave. On past projects it has not been effective and add a lot of unnecessary cost in material and labor. We have found it to be much more effective to drill a
12"-16" diameter hole 54" deep, pour 36" of concrete in the bottom and backfill the rest of the hole with some of the excavated material. In winter the soil freezes first but the frost cannot lift the concrete footing, and by the time the frost gets to the concrete footing it cannot lift it because of the frozen soil above it. We have been using this method for setting posts for years and have found it to be best at preventing or dramatically slowing frost heave. I am requesting that you consider changing the detail. Again, it would cut costs and make a better product.
ANSWER 18. The method described is also acceptable.
Please email John Kelley at jakelley@blm.gov with any and all questions.
mailto:jakelley@blm.gov